Final | 7/24/2012 | 7/25/2012 | 7/25/2012 | P | PASS |
Jim Johnson
|
|
|
General Contractor will be on site, other contractors will also be on site, door will be open. Any questions please call. Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Plumbing Rough-in | 5/25/2012 | 5/29/2012 | 5/29/2012 | A | PASS |
Jim Johnson
|
|
|
If we''re no there Larry Hobbs the general contractor should be. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Issue PAID IN FULL permit | | | 5/25/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/25/2012 | | DONE |
|
|
|
This permit was created on the web by Josh Johnson
|
First Notice | 7/25/2012 | 7/25/2012 | | | |
Jim Johnson
|
|
|
|