Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberPLM12-01756
StatusFinaled
Name TUFFY EXCAVATION INC
Site Address 800 W MAIN ST
Project Name 
Customer NumberBLD12-0093
ePlanReviewNo
Description
Plumbing Permit - New: Install Greasae Interceptor and Sewer service
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final11/19/201311/19/201311/19/2013PPASS
DetailsDaryl Spivey
per 353 request
roof drain tie in to site drainage ok........ds
CHANGE STATUS TO (I)  11/19/2013 DONE
DetailsTisha Gallop
work still in progress per 353
Water and/or Sewer9/5/20139/5/20139/5/2013APASS
DetailsDaryl Spivey
24 test ok on grease int............ds
DOC - Permit Finaled9/5/20139/5/20139/5/2013PPASS
DetailsDaryl Spivey
Final9/3/20139/4/20139/4/2013PPART
DetailsDaryl Spivey
for grease interceptor // tim jensen Phone #: ###-####
start 24 hr test on tank..........ds
CHANGE STATUS TO (I)  9/3/2013 DONE
DetailsTisha Gallop
still need insp on grease interceptor per Tuffy Excavation
PLM-Aging Inspection2/14/20132/14/20132/15/2013 PASS
DetailsDaryl Spivey
DOC - Permit Finaled2/15/20132/15/20132/15/2013PPASS
DetailsDaryl Spivey
Water and/or Sewer11/15/201211/15/201211/15/2012APEND
DetailsDaryl Spivey
Gave Jamaal from ESI a correction notice to resubmit plan reflecting changes to sewer and water service's that deviate from approved submitted set of plans....Per BV.............ds
Water and/or Sewer10/31/201210/31/201210/31/2012APART
DetailsDaryl Spivey
Last entry by mistake

tie in from flammable intercepter to six inch building drain done and passed ok.......ds
Water and/or Sewer10/30/201210/31/201210/31/2012AFAIL
DetailsDaryl Spivey
Tim Phone #: ###-####
Pan drain not installed correctly and T&P needs to be ran to within 6 inches of floor. T&P drain not to be drained into pan..............ds
Water and/or Sewer7/30/20127/31/20127/31/2012ACANC
DetailsDaryl Spivey
>> Inspection requested via web by Michael Nuxoll
Water and/or Sewer7/30/20127/30/20127/30/2012PPART
DetailsDaryl Spivey
sewer tie in to 8 inch at street, between ele vault aturned north just past north vault and capped.............ds
Issue PAID IN FULL permit  7/25/2012 DONE
Payment received via Govolutions
Application received  7/25/2012 DONE
This permit was created on the web by Michael Nuxoll
First Notice11/19/201311/19/2013   
DetailsDaryl Spivey