Final | 2/7/2013 | 2/8/2013 | 2/8/2013 | A | PASS |
Eric Strole
|
|
|
Final inspection for RP Backflow on make-up water to boiler, toilet, hydronics & water heater. Hydronics & water heater have been added. Contact is Chris. Phone #: ###-#### >> Inspection requested via web by Julie Dobransky
|
Issue PAID IN FULL permit | | | 2/7/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Final | 1/25/2013 | 1/28/2013 | 1/28/2013 | A | FAIL |
Eric Strole
|
|
|
Plumbing final inspection. Contact is Chris. Phone #: ###-#### >> Inspection requested via web by Julie Dobransky-Need an rpba on make-up water to boiler, need to caulk toilet and add hydronics and water heater to permit.
|
CHANGE STATUS TO (I) | | | 1/25/2013 | | |
|
|
|
|
Final | 12/13/2012 | 12/13/2012 | 12/13/2012 | P | PASS |
Eric Strole
|
|
|
|
Plumbing Rough-in | 12/12/2012 | 12/13/2012 | 12/13/2012 | A | NR |
Eric Strole
|
|
|
|
Plumbing Rough-in | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | CANC |
Eric Strole
|
|
|
Contact is Chris. Phone #: ###-#### >> Inspection requested via web by Julie Dobransky
|
Plumbing Rough-in | 11/21/2012 | 11/21/2012 | 11/21/2012 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Meghan Sainsbury-rough-in except mech room pass.
|
Groundwork | 10/8/2012 | 10/8/2012 | 10/8/2012 | P | PASS |
Eric Strole
|
|
|
Second Phase Groundwork. Contact is Chris. Phone #: ###-#### >> Inspection requested via web by Julie Dobransky
|
Plumbing Rough-in | 10/2/2012 | 10/3/2012 | 10/3/2012 | A | PASS |
Eric Strole
|
|
|
Contact is Mike. Phone #: ###-#### >> Inspection requested via web by Amber Morck-test on hydronic piping in slab pass.
|
Groundwork | 9/26/2012 | 9/27/2012 | 9/27/2012 | A | PASS |
Eric Strole
|
|
|
Contact is Steve. Phone #: ###-#### >> Inspection requested via web by Julie Dobransky
|
Issue PAID IN FULL permit | | | 9/24/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/24/2012 | | DONE |
|
|
|
This permit was created on the web by Julie Dobransky
|