First Notice | 5/21/2013 | 5/21/2013 | 1/9/2014 | | DONE |
Jim Johnson
|
|
|
|
Final | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | PASS |
Jim Johnson
|
|
|
Thank you Phone #: ###-#### >> Inspection requested via web by Aaron Johns
|
Plumbing Rough-in | 5/7/2013 | 5/7/2013 | 5/7/2013 | P | PASS |
Jim Johnson
|
|
|
the back half is ready for inspection this after noon thank you for your help Phone #: ###-#### >> Inspection requested via web by Aaron Johns
|
Plumbing Rough-in | 4/25/2013 | 4/26/2013 | 4/26/2013 | A | PART |
Jim Johnson
|
|
|
Top out on bathroom and back flow equipment Phone #: ###-#### >> Inspection requested via web by Aaron Johns restroom and equipment room rough-in test ok ok to cover
|
Water and/or Sewer | 4/23/2013 | 4/24/2013 | 4/24/2013 | A | PASS |
Jim Johnson
|
|
|
new water line to existing outside the building Phone #: ###-#### >> Inspection requested via web by Aaron Johns
|
Groundwork | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PASS |
Jim Johnson
|
|
|
aaron Phone #: ###-####
|
Application received | | | 4/22/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/22/2013 | | DONE |
Tisha Gallop
|
|
|
|