First Notice | 11/22/2013 | 11/22/2013 | 5/29/2014 | | DONE |
Bill VanDegrift
|
|
|
|
Final | 11/22/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Bill VanDegrift
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Kelley
|
Final | 11/5/2013 | 11/5/2013 | 11/5/2013 | P | PART |
Eric Strole
|
|
|
Need seperate water supply for soap dispensor at mop sink, need rpba on steamer and dbca on ice tea and coffee maker.Temp final ok.
|
Final | 10/31/2013 | 10/31/2013 | 10/31/2013 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Kelley-Will finall when all equipment is installed
|
Final | 10/30/2013 | 10/30/2013 | 10/30/2013 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Kelley-Need to add 2 rpba's on dishwashers, All backflows need tested and certified, caulk all fixtures, seperate drain lines on ice machine and secure all fixtures in bar area. Temp final ok
|
Plumbing Rough-in | 8/27/2013 | 8/28/2013 | 8/28/2013 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Kelley
|
Issue PAID IN FULL permit | | | 8/27/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Groundwork | 6/28/2013 | 6/28/2013 | 6/28/2013 | P | PART |
Eric Strole
|
|
|
Josh Phone #: ###-####-ok to cover, contractor to call when all flr sinks, trap primers and pipe wrap are complete
|
Water and/or Sewer | 6/26/2013 | 6/27/2013 | 6/27/2013 | P | PASS |
Eric Strole
|
|
|
24 hr test pass
|
Groundwork | 6/25/2013 | 6/25/2013 | 6/25/2013 | P | PASS |
Eric Strole
|
|
|
JOSH Phone #: ###-####-ground work and upstream and downstream piping of interceptor pass.
|
Override - Parcel Holds | 6/25/2013 | 1/1/1900 | 6/25/2013 | | |
|
|
|
THIS IS FOR GROUND WORK
|
Issue PAID IN FULL permit | | | 6/24/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/24/2013 | | |
|
|
|
|