First Notice | 11/20/2013 | 11/20/2013 | 12/6/2013 | | DONE |
Jim Johnson
|
|
|
|
Print Statement | | | 12/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
Final | 11/20/2013 | 11/20/2013 | 11/20/2013 | P | PASS |
Jim Johnson
|
|
|
The sign off sheet is on site. Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Final | 11/19/2013 | 11/19/2013 | 11/19/2013 | P | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker canc by contractor will recall when ready
|
Final | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker Inspection cancelled from web by: Travis Baker
|
Plumbing Rough-in | 10/16/2013 | 10/16/2013 | 10/16/2013 | P | PART |
Jim Johnson
|
|
|
Entire water system is complete and on test Phone #: ###-#### >> Inspection requested via web by Travis Baker overhead water over ymca daycare area test ok north side of building ok to cover
|
Plumbing Rough-in | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PART |
Jim Johnson
|
|
|
The rest of the walls are ready for inspection Phone #: ###-#### >> Inspection requested via web by Travis Baker in wall rough-in test ok ok tocover
|
Plumbing Rough-in | 10/4/2013 | 10/4/2013 | 10/4/2013 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker all D W V test ok in wall water for rest room,s test ok still need to rough-in water for kit area and run hot and cold water trunk lines
|
Issue PAID IN FULL permit | | | 10/4/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Groundwork | 9/13/2013 | 9/16/2013 | 9/16/2013 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Issue PAID IN FULL permit | | | 9/13/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/13/2013 | | DONE |
|
|
|
This permit was created on the web by Travis Baker
|