Final | 11/13/2015 | 11/16/2015 | 11/16/2015 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy
|
PLM-Aging Inspection | 9/29/2015 | 9/29/2015 | 9/29/2015 | | PART |
Eric Strole
|
|
|
wip
|
Plumbing Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy-Test on mains F-wing pass
|
Plumbing Rough-in | 5/18/2015 | 5/19/2015 | 5/19/2015 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy-G-wing units rough-in complete, ok to cover.
|
Plumbing Rough-in | 5/7/2015 | 5/7/2015 | 5/7/2015 | P | PART |
Eric Strole
|
|
|
2nd flr G wing r/i complete
|
Plumbing Rough-in | 5/7/2015 | 5/7/2015 | 5/7/2015 | A | NR |
Eric Strole
|
|
|
G wing 2nd floor manifolds Phone #: ###-#### Inspection requested via web by Brent Lacy-Not ready
|
Plumbing Rough-in | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | PART |
Eric Strole
|
|
|
G-wing 3rd flr rough-in complete.
|
Water and/or Sewer | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | CANC |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy
|
Plumbing Rough-in | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy-1st flr F-wing ok to cover
|
Plumbing Rough-in | 4/1/2015 | 4/1/2015 | 4/1/2015 | P | PART |
Eric Strole
|
|
|
We would like this done this afternoon. Thank you. Phone #: ###-#### Inspection requested via web by Brent Lacy-2nd flr F-wing r/i complete & 1st,2nd & 3rd flr public bath's F-wing r/i pass.
|
Plumbing Rough-in | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PART |
Eric Strole
|
|
|
We would like to have inspection done this afternoon Phone #: ###-#### Inspection requested via web by Brent Lacy-3rd flr F-wing water complete.
|
Roof Drains | 3/20/2015 | 3/20/2015 | 3/20/2015 | P | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy G roof drains ok roof drains complete through G
|
Plumbing Rough-in | 3/11/2015 | 3/12/2015 | 3/12/2015 | P | PART |
Eric Strole
|
|
|
Would like to schedule this inspection for Thursday afternoon. Phone #: ###-#### Inspection requested via web by Brent Lacy-4th flr F wing ok to cover.
|
Plumbing Rough-in | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy-dwv all flrs of g-wing pass.
|
Roof Drains | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | NR |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy
|
Roof Drains | 2/2/2015 | 2/3/2015 | 2/3/2015 | A | CANC |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy
|
Plumbing Rough-in | 2/2/2015 | 2/3/2015 | 2/3/2015 | A | CANC |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy
|
Plumbing Rough-in | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy 4 floors of dwv test ok south side of the hall and public restroom stack F wing
|
Plumbing Rough-in | 12/30/2014 | 12/31/2014 | 12/31/2014 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy-F-wing north side all 4 flrs dwv pass.All water in common area into kitchen area pass.
|
Roof Drains | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy rood drains south side test ok
|
Roof Drains | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Brent Lacy rain drains 2 sets of 3 north wall F wing test ok
|
Issue PAID IN FULL permit | | | 10/27/2014 | | DONE |
|
|
|
|
Application received | | | 10/23/2014 | | DONE |
|
|
|
This permit was created on the web by Brent Lacy
|
First Notice | 11/16/2015 | 11/16/2015 | | | |