Final | 1/7/2015 | 1/8/2015 | 1/8/2015 | A | PASS |
Jim Johnson
|
|
|
John Phone #: ###-####
|
Final | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | FAIL |
Jim Johnson
|
|
|
Jeremy Phone #: ###-####
|
Plumbing Rough-in | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Jim Johnson
|
|
|
Jeremy Phone #: ###-####
|
Final | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | FAIL |
Jim Johnson
|
|
|
Jeremy Phone #: ###-#### need to support abs every 4 feet in crawl and overhead vent,s need to cap off old sewer line stub in crawl space need to repipe copper T&P drain line 3/4 inch min piping size to outside building called contractor will recall when ready
|
Plumbing Rough-in | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | FAIL |
Jim Johnson
|
|
|
Jeremy-tests-would like as early as possible Phone #: ###-#### need to support abs in crawl and overhead every four feet need to replace fernco coupling on two inch drain line in crawl space with an approved sheilded band not D W V and water test ok called contractor will recall when ready correction notice on site
|
Plumbing Rough-in | 10/24/2014 | 10/24/2014 | 10/24/2014 | P | FAIL |
Jim Johnson
|
|
|
need to repipe dwv as per conversation with contractor
|
Plumbing Rough-in | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | NH |
Jim Johnson
|
|
|
Jeremy Phone #: ###-#### no access building locked
|
Issue PAID IN FULL permit | | | 10/23/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Issue PAID IN FULL permit | | | 10/23/2014 | | DONE |
|
|
|
|
Application received | | | 10/23/2014 | | |
|
|
|
|
First Notice | 1/8/2015 | 1/8/2015 | | | |
Jim Johnson
|
|
|
|