Permit Information
Permit NumberPLM14-03499
StatusFinaled
Name BAKERS PLUMBING SOLUTIONS LLC
Site Address 5369 W IRVING ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Plumbing Permit - Addition: Install plumbing system for bio lab// added sewer line install per call from Bakers plumbing, value $650 12-17-14 blh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/18/20158/18/20158/18/2015PPASS
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Travis Baker
Final8/17/20158/17/20158/17/2015PPART
DetailsEric Strole
Phone #: ###-#### Inspection requested via web by Travis Baker-Need to label all non-potable water, T&P needs air gap & need to caulk all sinks.
PLM-Aging Inspection7/22/20157/22/20157/22/2015 PART
DetailsJim Little
wip
Plumbing Rough-in4/22/20154/23/20154/23/2015APASS
DetailsJim Johnson
entire drain,vent and water system is on test. Phone #: ###-#### >> Inspection requested via web by Travis Baker
Plumbing Rough-in4/10/20154/10/20154/10/2015PCANC
DetailsJim Johnson
1st floor rough-in wall inspection is complete Phone #: ###-#### >> Inspection requested via web by Travis Baker 1st floor in wall rough-in test ok ok to cover
Plumbing Rough-in3/26/20153/27/20153/27/2015APART
DetailsJim Johnson
Partial rough-in on exterior walls is complete Phone #: ###-#### >> Inspection requested via web by Travis Baker partial rough-in on exterior wall test ok ok to cover
Plumbing Rough-in2/24/20152/25/20152/25/2015PPART
DetailsJim Johnson
All pipe penetrations trough 2nd floor pan deck are complete and ready for inspection before pour. Phone #: ###-#### >> Inspection requested via web by Travis Baker pipe penetration,s through 2nd deck ok ok to cover
Groundwork12/24/201412/24/201412/24/2014PPASS
DetailsJim Johnson
Phone #: ###-#### >> Inspection requested via web by Travis Baker holding tank and piping test ok ok to cover
Groundwork12/16/201412/17/201412/17/2014PPASS
DetailsJim Johnson
Groundwork completed up to tank but not including tank located outside Phone #: ###-#### >> Inspection requested via web by Travis Baker
Issue PAID IN FULL permit  12/16/2014 DONE
Payment received via Govolutions
Owner Supplied Equipment  12/16/2014  
Application received  12/16/2014 DONE
This permit was created on the web by Travis Baker