Telephone call | | | 3/3/2016 | | DONE |
|
|
|
called talked to Angie about past due amount. She emailed me the actual invoice for the job. See attached
|
Print Statement | | | 2/9/2016 | | DONE |
|
|
|
sent past due notice
|
Print Statement | | | 12/22/2015 | | DONE |
|
|
|
sent statement with past due stamp
|
Print Statement | | | 11/9/2015 | | DONE |
|
|
|
sent past due notices
|
Print Statement | | | 11/9/2015 | | DONE |
|
|
|
sent late notice
|
Print Statement | | | 9/18/2015 | | DONE |
|
|
|
|
Print Statement | | | 7/23/2015 | | DONE |
|
|
|
|
Final | 4/6/2015 | 4/6/2015 | 4/6/2015 | P | PASS |
Jim Johnson
|
|
|
|
Final | 4/6/2015 | 4/6/2015 | 4/6/2015 | A | PART |
Jim Johnson
|
|
|
General contractor and store manager should be there. If they are not please contact me at above number. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson need to have sprinkler backflow and tie-in permitted prior to building plumbing final oked temp
|
Final | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | PART |
Jim Johnson
|
|
|
General Contractor or store manager should be on site all day. Please call me with any issues. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson need 120 degree hot water limitation to public laves called contractor will recall when ready
|
Plumbing Rough-in | 2/19/2015 | 2/19/2015 | 2/19/2015 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Issue PAID IN FULL permit | | | 2/18/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/18/2015 | | |
|
|
|
|
Application received | | | 2/18/2015 | | DONE |
|
|
|
This permit was created on the web by Josh Johnson
|
First Notice | 4/6/2015 | 4/6/2015 | | | |
Jim Johnson
|
|
|
|