DOC - Permit Finaled | 9/2/2015 | 9/2/2015 | 9/2/2015 | P | PASS |
Jim Little
|
|
|
|
PLM-Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 | | PASS |
Jim Little
|
|
|
finaled by BV but never doc finaled.
|
Case Summary (PLM) | | | 6/15/2015 | | DONE |
Christina Prado
|
|
|
|
Water and/or Sewer | 6/3/2015 | 6/4/2015 | 6/4/2015 | A | PASS |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Erin Whiting
|
Plumbing Rough-in | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting
|
Plumbing Rough-in | 4/13/2015 | 4/14/2015 | 4/13/2015 | P | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting Inspection cancelled from web by: Erin Whiting
|
Plumbing Rough-in | 4/10/2015 | 4/13/2015 | 4/13/2015 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting
|
Plumbing Rough-in | 4/10/2015 | 4/10/2015 | 4/10/2015 | P | FAIL |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting need to replace fernco coupling with an approved shielded band as noted in correction notice issued on 4/7/2015 at building drain and sewer connection in crawl other correction have been made test on DWV test ok correction notice on site contractor to recall when ready
|
Plumbing Rough-in | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | FAIL |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting need to make correction,s noted on correction notice posted on site
|
Plumbing Rough-in | 4/6/2015 | 4/7/2015 | 4/7/2015 | P | FAIL |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Erin Whiting 1. test failed on DWV 2. need to repipe water closet on horizontal wet vent entering horizontal branch drain in vertical. each individual fixture drain or trap arm SHALL connect horizontally to the wet-vented horizontal branch drain. as per908.2 2009 upc. 3. need to repipe abs to pvc with approved glue or an approved shielded band not abs glue at building drain to building sewer connection in crawl correction notice on site contractor to recall rough-in when ready
|
Issue PAID IN FULL permit | | | 3/6/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/6/2015 | | DONE |
|
|
|
This permit was created on the web by Erin Whiting
|