Final | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Jim Johnson
|
|
|
backflow installed and tested for corrections. Stan Hafferman for access if not home ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Sparrell
|
Final | 5/12/2015 | 5/13/2015 | 5/13/2015 | A | FAIL |
Jim Johnson
|
|
|
Bathroom is finished and ready for inspection. Customer Will be home for access Phone #: ###-#### >> Inspection requested via web by Scott Sparrell need double check installed on steam unit called contractor will recall when ready
|
Plumbing Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Jim Johnson
|
|
|
Will be ready after 1. Steamer will be in closet with pan. Phone #: ###-#### >> Inspection requested via web by Scott Sparrell
|
Issue PAID IN FULL permit | | | 4/22/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/22/2015 | | DONE |
|
|
|
This permit was created on the web by Scott Sparrell
|