Final | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PASS |
Daryl Spivey
|
|
|
Finish inspection for Building V Phone #: ###-#### Inspection requested via web by Bobbi Shafer
|
PLM-Aging Inspection | 1/3/2017 | 1/3/2017 | 1/3/2017 | | PEND |
Daryl Spivey
|
|
|
wip
|
Plumbing Rough-in | 10/4/2016 | 10/4/2016 | 10/4/2016 | P | PASS |
Daryl Spivey
|
|
|
Rough-in plumbing Building V Phone #: ###-#### Inspection requested via web by Bobbi Shafer
|
PLM-Aging Inspection | 8/4/2016 | 8/4/2016 | 8/4/2016 | | NR |
Daryl Spivey
|
|
|
wip
|
Groundwork | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | PASS |
Daryl Spivey
|
|
|
Building V - Ground Rough Phone #: ###-#### Inspection requested via web by Bobbi Shafer
|
Groundwork | 4/28/2016 | 4/29/2016 | 4/29/2016 | P | PART |
Bill VanDegrift
|
|
|
Building V - Underground plumbing inspection Phone #: ###-#### Inspection requested via web by Bobbi Shafer east 1/4 gw ok
|
Water and/or Sewer | 4/27/2016 | 4/28/2016 | 4/28/2016 | A | PASS |
Daryl Spivey
|
|
|
Building V water main inspection Phone #: ###-#### Inspection requested via web by Bobbi Shafer
|
Groundwork | 3/9/2016 | 3/10/2016 | 3/10/2016 | A | PART |
Jim Little
|
|
|
Partial inspection for sub-rough Phone #: ###-#### Inspection requested via web by Bobbi Shafer >trunk line ok
|
Issue PAID IN FULL permit | | | 2/11/2016 | | DONE |
|
|
|
|
Application received | | | 2/8/2016 | | DONE |
|
|
|
This permit was created on the web by Bobbi Shafer
|
First Notice | 2/23/2017 | 2/23/2017 | | | |
Daryl Spivey
|
|
|
|