First Notice | 11/14/2016 | 11/14/2016 | 2/9/2019 | | DONE |
Dan Ediger
|
|
|
This permit finaled on the web by Rob Bristol
|
Final | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Dan Ediger
|
|
|
Sewer dump to be finaled, is on the south side of building ( in the back ) outside. The RP devise for hose bib, is on the inside of building, just behind the hose bib. Phone #: ###-#### Inspection requested via web by Rob Bristol
|
Groundwork | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PASS |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Bristol gw ok trap will be protected from freezing by the anti freeze in the bus waste tank in the winter.
|
Issue PAID IN FULL permit | | | 9/12/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 9/12/2016 | | |
|
|
|
|
Application received | | | 9/12/2016 | | DONE |
|
|
|
This permit was created on the web by Rob Bristol
|