Final | 3/23/2017 | 3/23/2017 | 3/23/2017 | P | PASS |
Eric Strole
|
|
|
Cabana sink is ready Inspection requested via web by Brian Johansen
|
Final | 3/20/2017 | 3/21/2017 | 3/21/2017 | P | NR |
Eric Strole
|
|
|
Cabana Sink install Inspection requested via web by Brian Johansen-Not ready
|
CHANGE STATUS TO (I) | | | 1/26/2017 | | DONE |
|
|
|
as per Eric Strol-was issued by mistake
|
Final | 1/24/2017 | 1/25/2017 | 1/25/2017 | P | PASS |
Eric Strole
|
|
|
Inspection requested via web by Brian Johansen
|
Groundwork | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Eric Strole
|
|
|
Inspection requested via web by Brian Johansen
|
Issue PAID IN FULL permit | | | 11/15/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/15/2016 | | DONE |
|
|
|
This permit was created on the web by Brian Johansen
|
First Notice | 3/23/2017 | 3/23/2017 | | | |
Eric Strole
|
|
|
|
First Notice | 1/25/2017 | 1/25/2017 | | | |
Eric Strole
|
|
|
|