Final | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Dan Ediger
|
|
|
Passed for work competed. New contractor pulled permit to take over incomplete work under PLM18-00960.
|
CHANGE STATUS TO (I) | | | 1/3/2020 | | DONE |
|
|
|
per dan reopen permit
|
Permit EXPIRED | | | 1/31/2018 | | DONE |
|
|
|
Per Dale, Red Lion took over and hired another company to finish the plumbing work
|
Plumbing Rough-in | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | PART |
Eric Strole
|
|
|
1st floor (no insp on bathrooms only per SWO) // Victor Phone #: ###-####-1st flr sinks pass
|
Plumbing Rough-in | 12/4/2017 | 12/5/2017 | 12/5/2017 | A | PEND |
Eric Strole
|
|
|
Victor-4th floor rough in as well as a section on the 1st floor (115-125) Phone #: ###-####-Plumbing in rooms requested looks good but no inspections till a mechanical permit is issued for all bath exhausts.
|
Final | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PEND |
Eric Strole
|
|
|
4th floor rooms 401-425 (odd numbers only), 1st floor 115-125 (odd numbers only) // Viktor Phone #: ###-####-No inspections till permits are worked out.
|
Final | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | PART |
Eric Strole
|
|
|
2nd flr except unit 208 & 3rd flr except units 302, 304, 306, & 308 pass.
|
CHANGE STATUS TO (I) | | | 8/15/2017 | | DONE |
Christina Prado
|
|
|
Re-opened per Eric S
|
PLM-Aging Inspection | 7/25/2017 | 7/25/2017 | 7/25/2017 | | PASS |
Eric Strole
|
|
|
|
DOC - Permit Expired | 7/25/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
Eric Strole
|
|
|
|
Application received | | | 12/27/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/27/2016 | | DONE |
|
|
|
|
First Notice | 1/3/2020 | 1/3/2020 | | | |
Dan Ediger
|
|
|
|