Final | 7/28/2017 | 7/31/2017 | 7/31/2017 | P | PASS |
Daryl Spivey
|
|
|
Final plumbing inspection, awaiting backflow certification, scheduled 7/28 (friday). Phone #: ###-#### Inspection requested via web by Caleb Case
|
Final | 7/28/2017 | 7/31/2017 | 7/28/2017 | A | CANC |
Daryl Spivey
|
|
|
Final inspection to be done after backflow certification is done on Friday 7/28 Phone #: ###-#### >> Inspection requested via web by Caleb Case Inspection cancelled from web by: Caleb Case
|
Final | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Caleb Case ok for cover.....need to test dcva...........ds
|
Issue PAID IN FULL permit | | | 6/12/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/12/2017 | | DONE |
|
|
|
This permit was created on the web by Caleb Case
|
Telephone call | | | 6/12/2017 | | DONE |
|
|
|
per phone call from Trista at Viking Sewer, this permit should have been pulled as multifamily with water line(outside) fixture only. fee due should have been 42$. Will send Rita e-mail request for refund.
|
First Notice | 7/31/2017 | 7/31/2017 | | | |
Daryl Spivey
|
|
|
|