First Notice | 7/19/2017 | 7/19/2017 | 7/27/2020 | | DONE |
Eric Strole
|
|
|
This permit finaled on the web by RM Mechanical
|
Print Statement | | | 8/17/2017 | | DONE |
|
|
|
|
Final | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Eric Strole
|
|
|
Onsite contact: Renato Albanese Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Final | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PART |
Eric Strole
|
|
|
Onsite contact: Renato Albanese Phone #: ###-#### Inspection requested via web by Melissa Kaae-Need to add 3 rpba's, 1-dbca & a thermal expantion tank.
|
Plumbing Rough-in | 7/6/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Eric Strole
|
|
|
Gas- Roger Phone #: ###-####-20 lb gas test and corrections pass.
|
Other | 7/6/2017 | 7/6/2017 | 7/6/2017 | A | FAIL |
Eric Strole
|
|
|
natural gas rough-in above ground inspection. Call Roger. Phone #: ###-#### Inspection requested via web by Melissa Kaae-20 b gas test pass. Need to use listed nailplates per manufacurers instructions and remove all straps on gas flex in walls.
|
Med/Gas Systems | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | CANC |
Eric Strole
|
|
|
natural gas rough-in above ground inspection. Call Roger. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Plumbing Rough-in | 7/5/2017 | 7/5/2017 | 7/5/2017 | P | PASS |
Eric Strole
|
|
|
Roger Phone #: ###-####
|
Groundwork | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Eric Strole
|
|
|
Onsite contact: Roger Elam. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Issue PAID IN FULL permit | | | 6/15/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 6/15/2017 | | |
|
|
|
|
Application received | | | 6/15/2017 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|