Permit Information
Permit NumberPLM17-02501
StatusFinaled
Name PAIGE MECHANICAL GROUP INC
Site Address 4125 S EAGLESON RD
Project Name 
Customer Number17.6605
ePlanReviewNo
Description
Addition: Work Includes:
• Safe off for demo (demo by others)
• Sanitary Sewer & Vent (PVC DWV)
• Domestic Water (PEX/Copper)
• Piping Insulation on first 8’ of water heater.
• Furnish & Install Plumbing Fixtures
• Final Connection of owner supplied equipment
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final11/14/201711/14/201711/14/2017PPASS
DetailsDan Ediger
rp is certified Phone #: ###-#### Inspection requested via web by Nicholas Paige
Final10/10/201710/11/201710/11/2017APART
DetailsDan Ediger
Partial Final Phone #: ###-#### Inspection requested via web by Nicholas Paige. RR, laundry and water heater ok. RP to ice machine to be certified before hook-up. Contractor to notify. To be cert. this morning
Plumbing Rough-in8/4/20178/4/20178/4/2017PPART
DetailsDan Ediger
Phone #: ###-#### Inspection requested via web by Nicholas Paige.
Maint. area: Oil and fuel interceptor vent ok. The outlet vent tested to outside of the building and needs connected.
The rest/shower area wall ok to cover.
Plumbing Rough-in8/4/20178/7/20178/4/2017PCANC
DetailsDan Ediger
Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Inspection cancelled from web by: Nicholas Paige
Groundwork7/27/20177/28/20177/28/2017APART
DetailsDan Ediger
Phone #: ###-#### Inspection requested via web by Nicholas Paige.
Groundwork in the maint. pit side of the building. Plumbing outside of the building not done.
Other7/26/20177/27/20177/27/2017ACANC
DetailsDan Ediger
chect new interceptor tank water test.
Pass 24 hr test on outdoor tank
Groundwork7/25/20177/26/20177/26/2017APART
DetailsBill VanDegrift
24 hr tank test Phone #: ###-#### Inspection requested via web by Nicholas Paige start of the test on the new tank.
Other7/19/20177/19/20177/19/2017PPASS
DetailsDan Ediger
24hr test
Other7/18/20177/18/20177/18/2017PPART
DetailsDan Ediger
Start 24 hour test on two interceptor tanks
Groundwork7/17/20177/18/20177/18/2017ACANC
DetailsDan Ediger
Phone #: ###-#### Inspection requested via web by Nicholas Paige Start 24 hour test on the two interceptors.
Groundwork7/6/20177/7/20177/7/2017APART
DetailsDan Ediger
Phone #: ###-#### Inspection requested via web by Nicholas Paige. GW on the truckers lounge ok to cover.
Issue PAID IN FULL permit  7/6/2017 DONE
Payment received via Govolutions
Application received  7/6/2017 DONE
This permit was created on the web by Nicholas Paige
First Notice11/14/201711/14/2017   
DetailsDan Ediger