Final | 6/26/2018 | 6/27/2018 | 6/28/2018 | P | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
Final | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | FAIL |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen 1. Perm cap the garage floor drain. 2. No air gap at the water softener drain. 3. Loop dw drain as high as possible. 4 set wc.
|
PLM-Aging Inspection | 6/11/2018 | 6/11/2018 | 6/11/2018 | | PEND |
Dan Ediger
|
|
|
wip
|
Plumbing Rough-in | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
Groundwork | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
Issue PAID IN FULL permit | | | 9/25/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/25/2017 | | DONE |
|
|
|
This permit was created on the web by Brian Johansen
|