PLM-Aging Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | | PASS |
Dan Ediger
|
|
|
|
DOC - Permit Finaled | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Dan Ediger
|
|
|
|
Water and/or Sewer | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Dan Ediger
|
|
|
Will be at work and not home. Come anytime you want. Call if needed. Phone #: ###-#### Inspection requested via web by Kevin Hanners
|
Water and/or Sewer | 10/3/2017 | 10/3/2017 | 10/3/2017 | P | PART |
Dan Ediger
|
|
|
Back flow is installed ; would like to bury the water main. Currently at work so would need notification to be present. The sprinkler system is not complete but manifold and valves are . installed. Hoping this is the proper time to do the inspection. If not let me know. Phone #: ###-#### Inspection requested via web by Kevin Hanners. OK to cover. Have backflow certified then call for a final.
|
Issue PAID IN FULL permit | | | 9/29/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/29/2017 | | DONE |
|
|
|
This permit was created on the web by Kevin Hanners
|