Final | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Eric Strole
|
|
|
House is trimmed out and ready for final. Barb is contact for access. Has lock box as well. Thanks. Scott. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Plumbing Rough-in | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | PASS |
Eric Strole
|
|
|
Groundwork, rough in ready for inspection. Building permit is issued, ready for inspection this am and under test. Lock box for access is 1122 combo Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Groundwork | 11/30/2017 | 11/30/2017 | 11/30/2017 | A | PEND |
Eric Strole
|
|
|
Ground work plumbing is complete to include ejector vault, toilet, lavatory, floor drain and corner neo angle shower and clothes washer. Under test. Key pad lock box code is 1122 on front door, vacant home, gutted. Phone #: ###-#### Inspection requested via web by Scott Sparrell-Need a building permit before a plumbing inspection will be done.
|
Issue PAID IN FULL permit | | | 11/30/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/30/2017 | | DONE |
|
|
|
This permit was created on the web by Scott Sparrell
|