Water and/or Sewer | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Dan Ediger
|
|
|
Sewer ok from the building to the grease interceptor. Inspection is for the outlet
|
DOC - Permit Finaled | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Dan Ediger
|
|
|
|
Water and/or Sewer | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PART |
Dan Ediger
|
|
|
complete 24hr test. test ok. Sewer from the building to the tank pressure test passed.
|
Other | 1/3/2018 | 1/3/2018 | 1/3/2018 | P | PASS |
Dan Ediger
|
|
|
start 24hr test
|
Issue PAID IN FULL permit | | | 12/19/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/19/2017 | | DONE |
|
|
|
This permit was created on the web by jennifer Hankins
|
First Notice | 1/4/2018 | 1/4/2018 | | | |
Dan Ediger
|
|
|
|