First Notice | 4/18/2018 | 4/18/2018 | 4/19/2018 | | DONE |
Dan Ediger
|
|
|
This permit finaled on the web by Stacia Haumann
|
Final | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | PASS |
Dan Ediger
|
|
|
if questions call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann. Med gas report in the building docs
|
Final | 3/27/2018 | 3/27/2018 | 3/27/2018 | A | PART |
Dan Ediger
|
|
|
Contact Ryan for questions ###-#### inspection is for a temp occ. Inspection requested via web by Stacia Haumann. Waiting on final Med Gas report from Norco. Have a verbal pass from Ryan. Final report a week out. Temp occupancy ok.
|
Med/Gas Systems | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | PASS |
Dan Ediger
|
|
|
3:15. Pass pressure test 150psi gas 100psi air
|
Med/Gas Systems | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | CANC |
Dan Ediger
|
|
|
complete 24hr test 3:15. CT Scan 2. rescheduled to afernoon
|
Med/Gas Systems | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PEND |
Dan Ediger
|
|
|
Med Gas Pressure Test Witness. If questions call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann. Start 24hr med gas test 3:15pm
|
Med/Gas Systems | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PART |
Dan Ediger
|
|
|
Med Gas - Wall Inspection. If there are any questions please contact Ryan J. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann. Wall risers are ok to cover. Tested and soaped
|
Issue PAID IN FULL permit | | | 2/21/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/21/2018 | | DONE |
|
|
|
This permit was created on the web by Stacia Haumann
|