VOIDED CHANGE STATUS | | | 6/6/2018 | | DONE |
|
|
|
as per Derick with Rocky Top Const-void permit-no longer doing job
|
Other | 5/31/2018 | 5/31/2018 | 5/31/2018 | A | PEND |
Dan Ediger
|
|
|
Nate-homeowner needs conference with inspector even though he did not pull the permit Phone #: ###-####. Met with Nate (homeowner and Mike Blessing (plumber). The sewer line in the trench is flat the majority of the run with slight grade to 1/4"/ft from the 100 foot make to the house. There is ensuffecient grade from the street to the house connection. The homeowner states that there is 24" approx. from the saddle to the 45 to horizontal in the street. The excavator walked off the job and will not return. I suggested to the owner, Nate to contact another excavator and work with them on lowering the connection at the sewer tap after a calculation is done to verify that will permit an 1/8" /foot grade.
|
Water and/or Sewer | 5/28/2018 | 5/29/2018 | 5/29/2018 | P | FAIL |
Dan Ediger
|
|
|
Inspection requested via web by Dereck Cumpton. Need 1/8"/ft grade
|
Water and/or Sewer | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | NR |
Dan Ediger
|
|
|
sewer line to existing dwelling.// Derek ###-####
|
Water and/or Sewer | 5/17/2018 | 5/18/2018 | 5/18/2018 | P | NR |
Dan Ediger
|
|
|
Inspection requested via web by Dereck Cumpton. Spoke to the contractor
|
Telephone call | | | 5/18/2018 | | DONE |
|
|
|
called contractor about type new or alt and what the correct valuation is-left message on his phone
|
Telephone call | | | 5/18/2018 | | DONE |
|
|
|
talked to Kenneth @ Rocky Top Construction-he said they were hooking up to city services after being on a septic tank-he said they were going to split the parcel into 3 seperate parcels.-i emailed Rachael and Morgan in PW to let know
|
Issue PAID IN FULL permit | | | 5/17/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/17/2018 | | DONE |
|
|
|
This permit was created on the web by Dereck Cumpton
|