Final | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Daryl Spivey
|
|
|
Homeowners name is James cell # ###-#### Thank you! Phone #: ###-#### Inspection requested via web by KEVIN FRANKLIN
|
Plumbing Rough-in | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Dan Ediger
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by KEVIN FRANKLIN
|
Groundwork | 6/28/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Dan Ediger
|
|
|
looking at the house go thru the gate on the left side of the house and the plumbing project is in the 1st. door on the right Phone #: ###-#### Inspection requested via web by KEVIN FRANKLIN
|
Issue PAID IN FULL permit | | | 6/28/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/28/2018 | | DONE |
|
|
|
This permit was created on the web by KEVIN FRANKLIN
|