Print Statement | | | 5/7/2020 | | DONE |
|
|
|
2nd notice
|
Print Statement | | | 4/13/2020 | | DONE |
|
|
|
1st notice
|
Print Statement | | | 2/26/2020 | | DONE |
|
|
|
|
Final | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 7/30/2019 | 7/30/2019 | 7/30/2019 | P | CANC |
Matt Wrobel
|
|
|
remove disposals and pipe drains to floor sinks talked to plumber about disposals having to be removed per code
|
CHANGE STATUS TO (I) | | | 7/26/2019 | | DONE |
|
|
|
per eric strole temp final ok. permit should not be fully passed
|
Final | 7/18/2019 | 7/19/2019 | 7/19/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige final occ pass
|
Final | 7/15/2019 | 7/17/2019 | 7/17/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige temp occupancy ok
|
Other | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | DONE |
Matt Wrobel
|
|
|
consultPhone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 7/3/2019 | 7/9/2019 | 7/8/2019 | A | CANC |
Matt Wrobel
|
|
|
part final Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 7/3/2019 | 7/8/2019 | 7/8/2019 | A | PART |
Matt Wrobel
|
|
|
part final Phone #: ###-#### Inspection requested via web by Nicholas Paige temp occ ok A,B, and C.
|
Med/Gas Systems | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PART |
Matt Wrobel
|
|
|
24 hr check pass
|
Med/Gas Systems | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start 24 hour test
|
Other | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PART |
Matt Wrobel
|
|
|
consult Phone #: ###-#### Inspection requested via web by Nicholas Paige walkthru
|
Other | 6/4/2019 | 6/5/2019 | 6/4/2019 | A | CANC |
Matt Wrobel
|
|
|
consult Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Inspection cancelled from web by: Nicholas Paige
|
Med/Gas Systems | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige med gas test pass
|
Med/Gas Systems | 5/9/2019 | 5/13/2019 | 5/13/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start 24 hr. test
|
Groundwork | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PART |
Matt Wrobel
|
|
|
grease trap piping Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Plumbing Rough-in | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige rough in complete except exposed piping in mech room
|
Med/Gas Systems | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. start pressure test on service
|
Plumbing Rough-in | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | CANC |
Dan Ediger
|
|
|
Grease Duct Rough Phone #: ###-#### Inspection requested via web by Nicholas Paige under mechanical permit
|
Plumbing Rough-in | 4/4/2019 | 4/5/2019 | 4/5/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige med gAS 24 HR O.K. ROUGH OK
|
Med/Gas Systems | 4/3/2019 | 4/4/2019 | 4/4/2019 | A | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start 24 hour test
|
Plumbing Rough-in | 3/28/2019 | 3/29/2019 | 3/29/2019 | P | PART |
Matt Wrobel
|
|
|
Ryan Phone #: ###-#### sections E,F.G, wall rough in ok to cover
|
Plumbing Rough-in | 3/15/2019 | 3/15/2019 | 3/15/2019 | P | PASS |
Matt Wrobel
|
|
|
e and f raindrains 1st half of e rough in
|
Med/Gas Systems | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PART |
Matt Wrobel
|
|
|
med gas area d ok
|
Med/Gas Systems | 3/8/2019 | 3/11/2019 | 3/11/2019 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Start test 150 psi last 2 rooms area D and stub of mains into area E
|
Med/Gas Systems | 3/4/2019 | 3/5/2019 | 3/5/2019 | P | PART |
Matt Wrobel
|
|
|
med gas test area d pass
|
Plumbing Rough-in | 3/1/2019 | 3/4/2019 | 3/4/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige area d rough in ok to cover
|
Med/Gas Systems | 3/1/2019 | 3/4/2019 | 3/4/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige 24 hr test start
|
Med/Gas Systems | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | CANC |
Matt Wrobel
|
|
|
Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Inspection cancelled from web by: Nicholas Paige
|
Med/Gas Systems | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | PART |
Matt Wrobel
|
|
|
med gas pressure test ok
|
Med/Gas Systems | 2/21/2019 | 2/25/2019 | 2/25/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start med gas test mains thru c
|
Plumbing Rough-in | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige area c rough in and raindrains ok to cover
|
Med/Gas Systems | 2/7/2019 | 2/8/2019 | 2/8/2019 | A | PART |
Matt Wrobel
|
|
|
area b med gas 24 hour test pass
|
Med/Gas Systems | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start 24 hour med gas area b area b interior section rough in ok to cover
|
Other | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Matt Wrobel
|
|
|
inspector conference Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Plumbing Rough-in | 1/25/2019 | 1/28/2019 | 1/28/2019 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige section b exteriors ok to cover center section l;ater this week
|
Plumbing Rough-in | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige section a rain drains ok to cover
|
Plumbing Rough-in | 1/18/2019 | 1/18/2019 | 1/18/2019 | P | PASS |
Matt Wrobel
|
|
|
|
Med/Gas Systems | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Matt Wrobel
|
|
|
med gas 24 hour test pass
|
Med/Gas Systems | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | CANC |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige 24 hour test pass
|
Med/Gas Systems | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige 10;00 start 24 hour test
|
Plumbing Rough-in | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige Area "A" waste and vent ok to cover
|
Groundwork | 12/17/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Med/Gas Systems | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PART |
Matt Wrobel
|
|
|
start test 130 pm
|
Med/Gas Systems | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | CANC |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige start test 130 pm
|
Groundwork | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 11/16/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 10/22/2018 | 10/23/2018 | 10/23/2018 | P | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige areas C and D ok
|
Groundwork | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige sewer between east and west corridors.
|
Groundwork | 10/18/2018 | 10/19/2018 | 10/18/2018 | A | CANC |
Dan Ediger
|
|
|
Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Inspection cancelled from web by: Nicholas Paige
|
Groundwork | 10/9/2018 | 10/10/2018 | 10/10/2018 | P | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige Area "B" approved for cover
|
Groundwork | 10/4/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Dan Ediger
|
|
|
section A ok to cover.
|
Groundwork | 10/4/2018 | 10/5/2018 | 10/4/2018 | P | CANC |
Dan Ediger
|
|
|
|
Groundwork | 10/4/2018 | 10/4/2018 | 10/4/2018 | P | CANC |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige Rained out
|
Issue PAID IN FULL permit | | | 10/3/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/3/2018 | | DONE |
|
|
|
This permit was created on the web by Nicholas Paige
|
First Notice | 8/22/2019 | 8/22/2019 | | | |
Matt Wrobel
|
|
|
|
First Notice | 7/19/2019 | 7/19/2019 | | | |
Matt Wrobel
|
|
|
|