Final | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Anderson
|
Final | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | PART |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Anderson need backflow certified
|
Plumbing Rough-in | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Anderson
|
Groundwork | 3/13/2019 | 3/14/2019 | 3/14/2019 | A | PASS |
Matt Wrobel
|
|
|
Hi Matt I talked to you concerning the Prusik Construction TI today...General Contractor resubmitted plan to the city who said they did not need to be resubmitted... you said to call in the groundwork inspection, go ahead and bury it. Phone #: ###-#### Inspection requested via web by Jeremy Anderson
|
Groundwork | 3/8/2019 | 3/8/2019 | 3/8/2019 | P | NR |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Anderson contractor moved sink other than on plan under review
|
Issue PAID IN FULL permit | | | 3/8/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/8/2019 | | DONE |
|
|
|
This permit was created on the web by Jeremy Anderson
|
First Notice | 6/4/2019 | 6/4/2019 | | | |
Matt Wrobel
|
|
|
|