Final | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Matt Wrobel
|
|
|
Larry Phone #: ###-#### there never was a sewer and water it was miss labeled on rough
|
CHANGE STATUS TO (I) | | | 6/14/2019 | | DONE |
|
|
|
did more work than just the water and sewer line
|
Water and/or Sewer | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Matt Wrobel
|
|
|
Phone #: ###-#### Inspection requested via web by Larry Wehr
|
DOC - Permit Finaled | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Matt Wrobel
|
|
|
|
Plumbing Rough-in | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PASS |
Matt Wrobel
|
|
|
Please contact h/o for further scheduling. 2083155530. We did the piping for the water heater but we did not install the water heater. Phone #: ###-#### Inspection requested via web by Robert Gomez
|
Issue PAID IN FULL permit | | | 3/20/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/20/2019 | | DONE |
|
|
|
This permit was created on the web by Robert Gomez
|