Water Heater Final | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Matt Wrobel
|
|
|
The stop work order is not there now. Will you final this now? Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
Plumbing Rough-in | 8/30/2019 | 9/3/2019 | 9/3/2019 | A | PART |
Matt Wrobel
|
|
|
BRYAN Phone #: ###-#### install ok cant pass at this time job under stop work order
|
Override - Parcel Holds | 8/30/2019 | 1/1/1900 | 8/30/2019 | | |
|
|
|
THIS IS FOR A MEC
|
Issue PAID IN FULL permit | | | 8/28/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/28/2019 | | DONE |
|
|
|
This permit was created on the web by Mary LaFayette
|
First Notice | 9/5/2019 | 9/5/2019 | | | |
Matt Wrobel
|
|
|
|