Permit NumberPLM96-02302
StatusFinaled
Name DANIEL MILLER
Site Address 8000 S FEDERAL WAY
Project NameMIC #24 (FAB#4 PHS2)
Customer Number 
ePlanReview 
Description
(MICRON BLDG. #24)(FAB #4 PHASE 2) D & Z PLUMBING WILL FINISH THIS JOB FOR CMPA. ORIGINAL FEES PAID ON PLM96-1676. THERE WILL BE A $20.00 FEE ATTACHED TO THIS PERMIT FOR THE FINAL INSPECTION..DF
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Sewer line10/9/199610/10/199610/10/1996APASS
DetailsBill VanDegrift
10/10/96 330 - did yesterday
INSP - Final10/9/199610/9/199610/9/1996 PASS
DetailsBill VanDegrift
/ / 330 - perm occ ok
INSP - Plumbing Rough-in10/8/199610/7/199610/7/1996PPART
DetailsBill VanDegrift
containment piping for iw test ok
INSP - Plumbing Rough-in10/1/199610/1/199610/1/1996 PART
DetailsBill VanDegrift
/ / 330 - pumped IW TEST OK, STILL NEED BOTH CONTAINMENT TESTS
INSP - Plumbing Rough-in9/9/19969/9/19969/9/1996 PART
DetailsBill VanDegrift
/ / 330 - retest on 4x6 interior piping after it failed after witness lasttime, ok plus 6" pumped IW inner containment tested ok 9/7/96 witnessed by casey, and barry
PLM - Partial final8/30/19969/3/19969/3/1996ACANC
DetailsBill VanDegrift
09/03/96 330 - pump waste/ roof top system fab 4 phase 2 Andy called an
INSP - Plumbing Rough-in9/3/19969/3/19969/3/1996 PART
DetailsBill VanDegrift
/ / 330 - pumped OHF from subfab across roof to drop to repump station still need containment test.
Issue PAID IN FULL permit  8/26/1996
Issue & PRINT FEE-DUE permit  8/6/1996
Application received  8/6/1996