BLD-Final | 3/6/2001 | 3/7/2001 | 3/7/2001 | A | PASS |
Jim Storey
|
|
|
fn occ-- bruce--- ###-####
|
Permanent Occupancy | | 3/7/2001 | 3/7/2001 | | DONE |
|
|
|
|
BLD-Final | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | FAIL |
Jim Storey
|
|
|
###-#### door hardware and closers. 3/5/2001 10:02:10 AM
|
FIRE-Final Inspection | 2/28/2001 | 3/2/2001 | 3/2/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/28/2001 3:28:20 PM retest alarms
|
FIRE-Final Inspection | 2/27/2001 | 2/28/2001 | 2/28/2001 | P | FAIL |
Rick Jackson
|
|
|
###-#### alarms not working properly will retest on 3/2/01 2/28/2001 3:37:49 PM
|
BLD-Conference | 2/5/2001 | 2/6/2001 | 2/6/2001 | P | PASS |
Jim Storey
|
|
|
Bruce ###-#### a prearranged conference at 1:30 reviewed hardware isues for compliance/ observed fire pump test. 2/6/2001 5:19:07 PM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | PART |
Jim Storey
|
|
|
###-#### ceilling ok all but wall at battery rm needs perimtor wires and fire stopping. 1/24/2001 12:18:00 PM
|
BLD-Framing/Rough-in | 12/6/2000 | 12/7/2000 | 12/7/2000 | A | PART |
Jim Storey
|
|
|
###-####bld#3 ok for ceilling drop pending fire sprinklre rough in. 12/7/2000 10:57:08 AM
|
BLD-Framing/Rough-in | 11/9/2000 | 11/13/2000 | 11/13/2000 | A | PART |
Jim Storey
|
|
|
BRUCE ###-#### FR INSP
|
BLD-Foundation | 10/26/2000 | 10/26/2000 | 10/26/2000 | P | PART |
Jim Storey
|
|
|
grade beam foundation bruce ###-####placed w/special insp.pending report. 10/26/2000 3:51:15 PM
|
BLD-Concrete | 10/18/2000 | 10/19/2000 | 10/19/2000 | A | PART |
Jim Storey
|
|
|
###-#### grade beam placed w/special insp. pending report. 10/19/2000 10:36:50 AM
|
BLD-Foundation | 10/16/2000 | 10/17/2000 | 10/17/2000 | A | PART |
Jim Storey
|
|
|
grade beam Bruce ###-#### placed w/spec 10/17/2000 9:56:43 AMial insp. pending report. 10/17/2000 9:57:02 AM
|
BLD-Footing | 10/13/2000 | 10/13/2000 | 10/13/2000 | P | PART |
Jim Storey
|
|
|
FT INSP BRUCE ###-#### covered w special insp. pending report. 10/13/2000 4:35:19 PM
|
BLD-Framing/Rough-in | 10/11/2000 | 10/11/2000 | 10/11/2000 | P | FAIL |
Jim Storey
|
|
|
bruce ###-####oversized firedoor/flushbolts approved by plan review not allowed. 10/11/2000 4:28:06 PM
|
BLD-Footing | 10/2/2000 | 10/3/2000 | 10/3/2000 | A | PART |
Jim Storey
|
|
|
###-#### placed with special insp. pend report. 10/3/2000 3:44:55 PM
|
BLD-Framing/Rough-in | 10/2/2000 | 10/2/2000 | 10/2/2000 | P | PART |
Jim Storey
|
|
|
###-#### shafts 3 locations ok thru horrizontal assembly. 10/2/2000 9:16:21 AM
|
BLD-Framing/Rough-in | 9/20/2000 | 9/20/2000 | 9/20/2000 | P | PART |
Jim Storey
|
|
|
###-#### framing west end and ceilling of h occ ok for cover pending others .9/20/2000 5:20:05 PM 9/20/2000 5:21:06 PM
|
BLD-Framing/Rough-in | 9/20/2000 | 9/20/2000 | 9/20/2000 | P | PART |
Jim Storey
|
|
|
###-#### framing west end and ceilling of h occ ok for cover pending others .9/20/2000 5:20:05 PM 9/20/2000 5:21:06 PM
|
BLD-Concrete | 9/12/2000 | 9/13/2000 | 9/13/2000 | A | PART |
Jim Storey
|
|
|
bruce ###-#### masonary covered with special insp. pending report. 9/13/2000 8:02:51 AM
|
BLD-Concrete | 9/11/2000 | 9/12/2000 | 9/12/2000 | A | PART |
Jim Storey
|
|
|
masonry insp Bruce ###-#### pending s/i report. 9/12/2000 11:17:46 AM
|
BLD-Conference | 9/11/2000 | 9/12/2000 | 9/12/2000 | A | FAIL |
Jim Storey
|
|
|
bruce ###-#### for conf engineering changes must have submatals. wall rated location change submitals req./ 2 hr parepet change submatal required. 9/12/2000 11:19:38 AM
|
BLD-Foundation | 8/28/2000 | 8/29/2000 | 8/29/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/28/2000 at 15:29:35. Contact: . placed with special insp. 8/29/2000 7:54:49 AM
|
BLD-Footing | 8/28/2000 | 8/28/2000 | 8/28/2000 | P | PART |
Jim Storey
|
|
|
ft bruce ###-#### covered w/s/i. 8/28/2000 6:12:02 PM
|
BLD-Foundation | 8/21/2000 | 8/22/2000 | 8/22/2000 | A | PART |
Jim Storey
|
|
|
masonry Bruce ###-#### placed w/spical insp. pending report. 8/22/2000 10:25:37 AM
|
BLD-Foundation | 8/22/2000 | 8/22/2000 | 8/22/2000 | P | PART |
Jim Storey
|
|
|
###-#### covered by special insp. pending report. 8/22/2000 2:59:06 PM
|
BLD-Concrete | 8/18/2000 | 8/18/2000 | 8/18/2000 | P | PART |
Jim Storey
|
|
|
masonary Bruce ###-#### placed in the am. 8/18/2000 2:38:24 PM
|
BLD-Concrete | 8/15/2000 | 8/16/2000 | 8/16/2000 | P | PART |
Jim Storey
|
|
|
BRUCE--###-#### CONCRET covered w/s/i 8/16/2000 2:01:32 PM
|
BLD-Conference | 8/14/2000 | 8/15/2000 | 8/15/2000 | A | PART |
Jim Storey
|
|
|
BRUCE-- ###-#### CONF-- genral walk thru west side framing and steel erection in progess. 8/15/2000 11:02:47 AM
|
BLD-Foundation | 8/9/2000 | 8/10/2000 | 8/10/2000 | A | PART |
|
|
|
Bruce ###-#### masonry and foundation with 8/10/2000 2:38:40 PM footings for retaining wall at the north and east elev. bond at the 12 ft 8/10/2000 3:08:40 PM
|
BLD-Foundation | 8/8/2000 | 8/9/2000 | 8/9/2000 | A | PART |
|
|
|
bruce---- ###-#### masonary insp pending sp isp approvals 8/9/2000 11:11:29 AM
|
BLD-Foundation | 8/9/2000 | 8/9/2000 | 8/9/2000 | P | PART |
|
|
|
bruce--- ###-#### masonary insp no answer from bruce 8/9/2000 6:33:27 PM
|
BLD-Foundation | 8/7/2000 | 8/8/2000 | 8/8/2000 | A | PART |
|
|
|
masonry Bruce ###-#### pending sp insp approvals 8/8/2000 2:05:26 PM
|
BLD-Foundation | 7/31/2000 | 7/31/2000 | 7/31/2000 | P | PART |
Jim Storey
|
|
|
bruce-- ###-#### found insp elavator pit walls ok. 7/31/2000 2:04:13 PM
|
BLD-Conference | 7/26/2000 | 7/28/2000 | 7/28/2000 | A | PASS |
Jim Storey
|
|
|
Bruce ###-#### conference at 9am 2hr resole of code idems bld and fire. 7/28/2000 11:06:35 AM
|
BLD-Footing | 7/27/2000 | 7/28/2000 | 7/28/2000 | A | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Foundation | 7/21/2000 | 7/24/2000 | 7/24/2000 | A | PART |
Jim Storey
|
|
|
masonry Bruce ###-#### pending s/i report. 7/24/2000 12:36:10 PM
|
BLD-Foundation | 7/21/2000 | 7/24/2000 | 7/24/2000 | P | PART |
Jim Storey
|
|
|
Bruce ###-####
|
BLD-Foundation | 7/20/2000 | 7/21/2000 | 7/21/2000 | A | PART |
Jim Storey
|
|
|
masonry Bruce ###-#### pending report. 7/21/2000 9:59:23 AM
|
BLD-Concrete | 7/17/2000 | 7/18/2000 | 7/18/2000 | A | PART |
Jim Storey
|
|
|
###-#### pending report s/i. 7/18/2000 3:16:50 PM
|
BLD-Concrete | 7/14/2000 | 7/17/2000 | 7/17/2000 | A | PASS |
Jim Storey
|
|
|
###-#### slab on grade ok pending report on concrete. 7/17/2000 9:21:55 AM
|
BLD-Concrete | 7/13/2000 | 7/14/2000 | 7/14/2000 | P | PART |
Jim Storey
|
|
|
BRUCE--- ###-#### CONCRETE pending s/i report. 7/14/2000 2:29:46 PM
|
BLD-Foundation | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | PART |
Jim Storey
|
|
|
masonary bruce ###-#### pending s/i report. 7/13/00 1:10:28 PM
|
BLD-Concrete | 7/11/2000 | 7/12/2000 | 7/12/2000 | P | PART |
Jim Storey
|
|
|
###-#### RE-BAR INSP
|
BLD-Concrete | 7/10/2000 | 7/11/2000 | 7/11/2000 | A | PART |
Jim Storey
|
|
|
bruce ###-#### masonary groute insp pending s/i report. 7/11/00 1:46:22 PM
|
BLD-Concrete | 7/7/2000 | 7/10/2000 | 7/10/2000 | A | PART |
Jim Storey
|
|
|
###-#### pending report s/i 7/10/00 10:41:54 AM
|
BLD-Concrete | 7/7/2000 | 7/7/2000 | 7/7/2000 | P | PART |
|
|
|
###-#### with psecial insp approvals 7/7/00 3:39:14 PM
|
BLD-Foundation | 7/6/2000 | 7/7/2000 | 7/7/2000 | A | PART |
|
|
|
re-bar for grout Bill ###-#### pending sp insp approvals 7/7/00 12:26:40 PM
|
BLD-Concrete | 7/5/2000 | 7/6/2000 | 7/6/2000 | A | PART |
|
|
|
###-#### with sp insp pending 7/6/00 9:04:14 AM
|
BLD-Footing | 7/5/2000 | 7/5/2000 | 7/5/2000 | P | PART |
|
|
|
Bill ###-#### with sp insp pending 7/6/00 9:03:17 AM
|
BLD-Foundation | 6/30/2000 | 7/3/2000 | 7/3/2000 | A | PART |
Jim Storey
|
|
|
###-#### pending s/i report 7/10/00 10:39:15 AM
|
BLD-Concrete | 6/29/2000 | 6/30/2000 | 6/30/2000 | A | PART |
Jim Storey
|
|
|
masonary ###-####
|
BLD-Foundation | 6/29/2000 | 6/29/2000 | 6/29/2000 | P | PART |
Jim Storey
|
|
|
bruce ###-#### foundation wall
|
BLD-Concrete | 6/27/2000 | 6/28/2000 | 6/28/2000 | A | PART |
Jim Storey
|
|
|
masonary ###-#### bruce pending report s/i. 6/27/00 2:31:46 PM pending report s/i 6/28/00 10:28:44 AM
|
BLD-Footing | 6/27/2000 | 6/28/2000 | 6/28/2000 | A | PART |
Jim Storey
|
|
|
bRUCE ###-#### pending report s/i. 6/27/00 2:32:12 PM pending report s/i. 6/28/00 10:29:19 AM
|
BLD-Concrete | 6/26/2000 | 6/27/2000 | 6/27/2000 | A | PART |
Jim Storey
|
|
|
masonry ###-#### pending report. 6/27/00 2:29:51 PM
|
BLD-Foundation | 6/23/2000 | 6/26/2000 | 6/26/2000 | A | PART |
Jim Storey
|
|
|
bruce-- ###-#### masonary insp
|