BLD-Final | 8/29/2000 | 8/30/2000 | 8/30/2000 | A | PART |
Jim Storey
|
|
|
GREG-- ###-#### FN OCC final ok pending p/w sign off. 8/30/2000 4:07:50 PM
|
Permanent Occupancy | | 8/30/2000 | 8/30/2000 | | DONE |
|
|
|
|
BLD-Final | 8/23/2000 | 8/28/2000 | 8/28/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 17:26:02. Contact: ###-####. mitals of flod plain to jim wyilie public works waiting for responce/ waitting for p&z sign off no insp. preformed at this time. 8/29/2000 2:11:51 PM
|
FIRE-Final Inspection | 8/25/2000 | 8/28/2000 | 8/28/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/25/2000 at 09:49:11. Contact: ###-####. 8/28/2000 12:55:31 PM
|
FIRE-Final Inspection | 8/23/2000 | 8/24/2000 | 8/24/2000 | P | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 17:24:39. Contact: ###-####. Final Fail C/N issued 8/25/2000 7:38:16 AM
|
BLD-Other | 8/1/2000 | 8/1/2000 | 8/1/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/01/2000 at 07:21:22. Contact: ###-####. ceilling ok for cover. 8/1/2000 2:29:57 PM
|
BLD-Other | 7/28/2000 | 7/31/2000 | 7/31/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/28/2000 at 15:02:36. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/27/2000 | 6/28/2000 | 6/28/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/27/2000 at 21:30:15. Contact: ###-####. interior sheer ok. 6/28/00 3:26:28 PM
|
BLD-Framing/Rough-in | 6/23/2000 | 6/26/2000 | 6/26/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/23/2000 at 15:44:17. Contact: ###-####. archived truss repair and field cert. from idaho truss. 6/26/00 11:21:08 AM
|
BLD-Framing/Rough-in | 6/22/2000 | 6/23/2000 | 6/23/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/22/2000 at 11:42:44. Contact: ###-####. girders west side of bldg require nailling. letter from truss engineer to feild verify truss repair inthe field for approval of patch design. ok to rock east and center portion of bld./ arch to submit revised plan to justify flood plan requirment of play ground equment. 6/23/00 10:11:27 AM
|
BLD-Framing/Rough-in | 6/20/2000 | 6/21/2000 | 6/21/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/20/2000 at 16:05:47. Contact: ###-####. ok to insulate. 6/21/00 10:16:41 AM
|
BLD-Framing/Rough-in | 6/1/2000 | 6/1/2000 | 6/1/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/01/2000 at 08:49:55. Contact: ###-####.
|
BLD-Concrete | 5/8/2000 | 5/9/2000 | 5/9/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/08/2000 at 16:59:19. Contact: ###-####.
|
FIRE-Conference | 5/2/2000 | 5/2/2000 | 5/2/2000 | | PART |
Rick Jackson
|
|
|
reviewed plans at job site - superindentant not there; access still not resolved
|
BLD-Foundation | 4/19/2000 | 4/20/2000 | 4/20/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 14:53:48. Contact: ###-####. walls rebar and hold downs ok for placement. 4/20/00 2:02:10 PM
|
BLD-Footing | 4/17/2000 | 4/18/2000 | 4/18/2000 | A | PASS |
Jim Storey
|
|
|
###-#### ft ok rebar ok grund in place. 4/18/00
|
BLD-Footing | 4/14/2000 | 4/17/2000 | 4/17/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Greg Bolton ###-#### No app plans Elec. ground in ft. 4/17/00 1:24:02 PM
|