BLD-Final | 12/14/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Tom Arcoraci
|
|
|
FN OCC JAN- ###-#### 12/15/2000 3:48:29 PM ok for perm occ 12/15/2000 4:10:56 PM
|
FIRE-Final Inspection | 12/14/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Joe Tawney
|
|
|
JAN -- ###-#### FN FIRE Reinsp OK for certificate of completion 12/17/2000 8:32:51 PM
|
BLD-Final | 12/11/2000 | 12/14/2000 | 12/14/2000 | P | NR |
Tom Arcoraci
|
|
|
JAN -###-#### FN OCC
|
FIRE-Final Inspection | 12/11/2000 | 12/14/2000 | 12/14/2000 | A | FAIL |
Joe Tawney
|
|
|
FIRE FN-- JAN-- ###-#### Final Fail Smoke detector location and s/f damper access 12/14/2000 12:39:39 PM
|
BLD-Framing/Rough-in | 10/30/2000 | 10/30/2000 | 10/30/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/30/2000 phase 2 ok to cover; prior insp by 316
|
BLD-Other | 10/27/2000 | 10/30/2000 | 10/30/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/27/2000 at 12:48:36. Contact: ###-####. conf w/ bldr..need consult w/ fire-safety foe t/o of phase 2. 10/30/2000 2:41:25 PM
|
FIRE-Conference | 10/27/2000 | 10/30/2000 | 10/30/2000 | A | PART |
Joe Tawney
|
|
|
###-####.Discussed Phase II project with Jan 10/31/2000 7:48:21 AM
|
BLD-Framing/Rough-in | 10/26/2000 | 10/26/2000 | 10/26/2000 | P | NR |
Carl Dependahl
|
|
|
temp occ on phase 2 **Jan ###-####
|
BLD-Framing/Rough-in | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/28/2000 at 13:37:21. Contact: .
|
BLD-Framing/Rough-in | 6/9/2000 | 6/12/2000 | 6/12/2000 | A | PART |
Jim Sly
|
|
|
jan ###-#### radiology please call\\ok to cover interior reading room walls only phase one
|