BLD-Final | 1/9/2001 | 1/9/2001 | 1/9/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 01/09/2001 at 08:35:30. Contact: ###-####.
|
BLD-Final | 11/24/2000 | 11/24/2000 | 11/24/2000 | P | NR |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/24/2000 4:18:35 PM need code enf
|
BLD-Final | 11/22/2000 | 11/22/2000 | 11/22/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/22/2000 at 11:29:59. Contact: ###-####. ok for t/o, need p&z & mount extinguisher 11/22/2000 5:39:11 PM
|
BLD-Conference | 11/21/2000 | 11/21/2000 | 11/21/2000 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/21/2000 9:22:37 AM letter from arch ok for struct masonry
|
FIRE-Final Inspection | 11/20/2000 | 11/21/2000 | 11/21/2000 | A | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Framing/Rough-in | 10/24/2000 | 10/25/2000 | 10/25/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/24/2000 at 14:36:25. Contact: ###-####.roof ,dragstruts ok, rec'd arch's letter re beam deletion and masonry insps 10/25/2000 11:01:54 AM east 10/25/2000 11:02:00 AM 10/25/2000 11:02:58 AM
|
BLD-Framing/Rough-in | 10/19/2000 | 10/20/2000 | 10/20/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 15:16:43. Contact: ###-####. keep c/n...also have original c/n asking for insps of masonry...need eng's letter for lack of insps of masonry 10/20/2000 11:56:07 AM
|
BLD-Framing/Rough-in | 10/18/2000 | 10/18/2000 | 10/18/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/18/2000 at 09:59:09. Contact: ###-####. see cn 10/18/2000 5:07:04 PM
|
BLD-Framing/Rough-in | 10/16/2000 | 10/17/2000 | 10/17/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/16/2000 at 13:05:54. Contact: ###-####. needs to resolve masonary inspections 10/17/2000 9:48:50 AM
|
BLD-Foundation | 7/19/2000 | 7/19/2000 | 7/19/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 04:51:02. Contact: ###-####. Steel ok @ 7/20/00 1:59:05 PM
|
BLD-Footing | 7/17/2000 | 7/18/2000 | 7/18/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/17/2000 at 13:39:07. Contact: ###-####. Ftg's. ok (pend. suveyors report). 7/18/00 2:48:01 PM
|
BLD-Conference | 7/17/2000 | 7/17/2000 | 7/17/2000 | A | PASS |
Carl Dependahl
|
|
|
W/Al. H. refound. Req's; need eng's letter (per previous C/N re: compaction.
|
BLD-Conference | 7/17/2000 | 7/17/2000 | 7/17/2000 | A | PASS |
Carl Dependahl
|
|
|
w/alan H. ....need eng's reports prior to pour....keep C/N.
|
BLD-Footing | 7/17/2000 | 7/17/2000 | 7/17/2000 | A | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 07/17/2000 at 04:50:23. Contact: ###-####. No one on site 7/18/00 2:05:33 PM
|
BLD-Footing | 7/14/2000 | 7/14/2000 | 7/14/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/14/2000 at 05:27:58. Contact: ###-####. C/N: soils report & "ok to pour" by engr. 7/18/00 1:31:46 PM
|
BLD-Footing | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | FAIL |
Carl Dependahl
|
|
|
Dane, ###-#### Send compaction reports 7/14/00 9:28:04 AM
|
BLD-Conference | 7/5/2000 | 7/5/2000 | 7/5/2000 | P | PART |
|
|
|
Scheduled by Inspector: 338 On 7/5/00 site visit to confirm soils problems concrete ctr called with concerns; site visit it appears that this area has for some time been used for a fill area and a soils expert should give blessing prior to pouring concrete 7/5/00 4:31:29 PM
|