Permit Information
Permit NumberBLD00-00829
StatusFinaled
Name OLSON & ASSOCIATES ARCHITECTS
Site Address 11655 W MCMILLAN RD
Project NameCROSS OF CHRIST
Customer Number 
ePlanReviewNo
Description
CROSS OF CHRIST LUTHERAN CHURCH * TO CONSTRUCT A 6,010 SQ. FT. ONE STORY, TYPE V1HR CHURCH BUILDING WITH PARKING LOT AND LANDSCAPING PER APPROVED PLANS AND ATTACHMENTS, CUP00-00015 PC#224-00
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/27/200012/28/200012/28/2000APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/27/2000 at 11:31:33. Contact: ###-####.
FIRE-Final Inspection12/27/200012/27/200012/27/2000PPASS
DetailsJoe Tawney
###-####. Reinsp OK for permanant occupancy 12/29/2000 2:27:49 PM
BLD-Final12/21/200012/22/200012/22/2000ACANC
DetailsJim Sly
Scheduled by a contractor via Hello! on 12/21/2000 at 07:57:06. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/22/2000 at 05:56:13.
FIRE-Final Inspection12/21/200012/21/200012/21/2000PFAIL
DetailsJoe Tawney
###-####.Reinsp Fail Curb lettering 12/29/2000 2:10:00 PM
BLD-Final12/8/200012/8/200012/8/2000PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/08/2000 at 08:37:11. Contact: ###-####. sighed off for temp occ. 12/8/2000 3:21:45 PM
FIRE-Final Inspection12/8/200012/8/200012/8/2000PPART
DetailsJoe Tawney
###-####. 12/8/2000 1:35:49 PM Reinsp OK for temporary occupancy. Curb striping 12/11/2000 8:05:25 AM
FIRE-Final Inspection12/7/200012/7/200012/7/2000PFAIL
DetailsJoe Tawney
fire fn per david hannah Final Fail C/N issued 12/7/2000 4:49:46 PM
BLD-Other12/5/200012/6/200012/6/2000PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/05/2000 at 11:34:05. Contact: ###-####.
BLD-Final12/1/200012/1/200012/1/2000PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/01/2000 at 08:33:49. Contact: ###-####.NEEDS FINAL INSPECTION 12/1/2000 3:37:07 PM
BLD-Framing/Rough-in10/27/200010/27/200010/27/2000APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/27/2000 at 06:11:54. Contact: ###-####.
BLD-Framing/Rough-in10/23/200010/24/200010/24/2000APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/23/2000 at 14:09:35. Contact: ###-####. wip needs a few 10/24/2000 10:23:24 AM light boxes need boxed in 10/24/2000 10:23:54 AM
BLD-Framing/Rough-in10/18/200010/19/200010/19/2000APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/18/2000 at 17:48:01. Contact: ###-####. wip 10/19/2000 9:47:50 AM
BLD-Framing/Rough-in10/13/200010/16/200010/16/2000PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/13/2000 at 09:59:44. Contact: ###-####. wip 1 hr 10/17/2000 8:38:32 AM
BLD-Framing/Rough-in10/12/200010/13/200010/13/2000APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/12/2000 at 16:14:44. Contact: ###-####. Dbl top plate (blocks), fireblocks, some light gyp boxes, OK. 10/13/2000 9:48:52 AM
BLD-Conference10/11/200010/11/200010/11/2000APART
DetailsTom Arcoraci
Sheetrock to be continueos at ceiling in duct chases', all partion walls need additional blocking at top plate.
BLD-Framing/Rough-in10/9/200010/10/200010/10/2000ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/09/2000 at 14:14:30. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/10/2000 at 07:29:45.
BLD-Framing/Rough-in10/5/200010/6/200010/6/2000ANR
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/05/2000 at 11:13:26. Contact: ###-####. arch to make field insp 10/6/2000 10:10:36 AM
BLD-Framing/Rough-in9/11/20009/12/20009/12/2000APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 09/11/2000 at 09:39:57. Contact: ###-####. Need all trade R/I insp and approvals prior to calling for OK to cover. 9/12/2000 9:39:31 AM
BLD-Framing/Rough-in9/7/20009/8/20009/8/2000PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/07/2000 at 12:00:48. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/08/2000 at 07:54:40.
BLD-Framing/Rough-in8/21/20008/22/20008/22/2000PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 08/21/2000 at 10:24:17. Contact: ###-####. roof nailing ok 8/23/2000 8:15:17 AM
BLD-Foundation6/23/20006/23/20006/23/2000PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/23/2000 at 08:19:39. Contact: ###-####.
BLD-Foundation6/21/20006/22/20006/22/2000PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/21/2000 at 13:03:35. Contact: ###-####. all but drive thru area 6/23/00 11:22:38 AM
BLD-Footing6/19/20006/20/20006/20/2000APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/19/2000 at 08:14:04. Contact: ###-####. Need new detail for step down 6/21/00 11:44:25 AM
BLD-Foundation6/16/20006/20/20006/19/2000PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/16/2000 at 10:43:58. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/19/2000 at 08:12:03.
BLD-Footing6/16/20006/19/20006/19/2000AFAIL
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/16/2000 at 10:42:50. Contact: ###-####. Not ready 6/21/00 11:18:58 AM