BLD-Final | 12/27/2000 | 12/28/2000 | 12/28/2000 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/27/2000 at 11:31:33. Contact: ###-####.
|
FIRE-Final Inspection | 12/27/2000 | 12/27/2000 | 12/27/2000 | P | PASS |
Joe Tawney
|
|
|
###-####. Reinsp OK for permanant occupancy 12/29/2000 2:27:49 PM
|
BLD-Final | 12/21/2000 | 12/22/2000 | 12/22/2000 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/21/2000 at 07:57:06. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/22/2000 at 05:56:13.
|
FIRE-Final Inspection | 12/21/2000 | 12/21/2000 | 12/21/2000 | P | FAIL |
Joe Tawney
|
|
|
###-####.Reinsp Fail Curb lettering 12/29/2000 2:10:00 PM
|
BLD-Final | 12/8/2000 | 12/8/2000 | 12/8/2000 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/08/2000 at 08:37:11. Contact: ###-####. sighed off for temp occ. 12/8/2000 3:21:45 PM
|
FIRE-Final Inspection | 12/8/2000 | 12/8/2000 | 12/8/2000 | P | PART |
Joe Tawney
|
|
|
###-####. 12/8/2000 1:35:49 PM Reinsp OK for temporary occupancy. Curb striping 12/11/2000 8:05:25 AM
|
FIRE-Final Inspection | 12/7/2000 | 12/7/2000 | 12/7/2000 | P | FAIL |
Joe Tawney
|
|
|
fire fn per david hannah Final Fail C/N issued 12/7/2000 4:49:46 PM
|
BLD-Other | 12/5/2000 | 12/6/2000 | 12/6/2000 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/05/2000 at 11:34:05. Contact: ###-####.
|
BLD-Final | 12/1/2000 | 12/1/2000 | 12/1/2000 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/01/2000 at 08:33:49. Contact: ###-####.NEEDS FINAL INSPECTION 12/1/2000 3:37:07 PM
|
BLD-Framing/Rough-in | 10/27/2000 | 10/27/2000 | 10/27/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/27/2000 at 06:11:54. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/23/2000 at 14:09:35. Contact: ###-####. wip needs a few 10/24/2000 10:23:24 AM light boxes need boxed in 10/24/2000 10:23:54 AM
|
BLD-Framing/Rough-in | 10/18/2000 | 10/19/2000 | 10/19/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/18/2000 at 17:48:01. Contact: ###-####. wip 10/19/2000 9:47:50 AM
|
BLD-Framing/Rough-in | 10/13/2000 | 10/16/2000 | 10/16/2000 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/13/2000 at 09:59:44. Contact: ###-####. wip 1 hr 10/17/2000 8:38:32 AM
|
BLD-Framing/Rough-in | 10/12/2000 | 10/13/2000 | 10/13/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/12/2000 at 16:14:44. Contact: ###-####. Dbl top plate (blocks), fireblocks, some light gyp boxes, OK. 10/13/2000 9:48:52 AM
|
BLD-Conference | 10/11/2000 | 10/11/2000 | 10/11/2000 | A | PART |
Tom Arcoraci
|
|
|
Sheetrock to be continueos at ceiling in duct chases', all partion walls need additional blocking at top plate.
|
BLD-Framing/Rough-in | 10/9/2000 | 10/10/2000 | 10/10/2000 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/09/2000 at 14:14:30. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/10/2000 at 07:29:45.
|
BLD-Framing/Rough-in | 10/5/2000 | 10/6/2000 | 10/6/2000 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/05/2000 at 11:13:26. Contact: ###-####. arch to make field insp 10/6/2000 10:10:36 AM
|
BLD-Framing/Rough-in | 9/11/2000 | 9/12/2000 | 9/12/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/11/2000 at 09:39:57. Contact: ###-####. Need all trade R/I insp and approvals prior to calling for OK to cover. 9/12/2000 9:39:31 AM
|
BLD-Framing/Rough-in | 9/7/2000 | 9/8/2000 | 9/8/2000 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/07/2000 at 12:00:48. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/08/2000 at 07:54:40.
|
BLD-Framing/Rough-in | 8/21/2000 | 8/22/2000 | 8/22/2000 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/21/2000 at 10:24:17. Contact: ###-####. roof nailing ok 8/23/2000 8:15:17 AM
|
BLD-Foundation | 6/23/2000 | 6/23/2000 | 6/23/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/23/2000 at 08:19:39. Contact: ###-####.
|
BLD-Foundation | 6/21/2000 | 6/22/2000 | 6/22/2000 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/21/2000 at 13:03:35. Contact: ###-####. all but drive thru area 6/23/00 11:22:38 AM
|
BLD-Footing | 6/19/2000 | 6/20/2000 | 6/20/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/19/2000 at 08:14:04. Contact: ###-####. Need new detail for step down 6/21/00 11:44:25 AM
|
BLD-Foundation | 6/16/2000 | 6/20/2000 | 6/19/2000 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/16/2000 at 10:43:58. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/19/2000 at 08:12:03.
|
BLD-Footing | 6/16/2000 | 6/19/2000 | 6/19/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/16/2000 at 10:42:50. Contact: ###-####. Not ready 6/21/00 11:18:58 AM
|