BLD-Final | 1/3/2002 | 1/4/2002 | 1/4/2002 | A | PASS |
Jim Sly
|
|
|
###-#### OK for Perm Occ. 1/4/2002 3:47:39 PM
|
Permanent Occupancy | | 1/4/2002 | 1/4/2002 | | DONE |
|
|
|
|
BLD-Final | 11/16/2001 | 11/19/2001 | 11/19/2001 | A | PART |
Jim Sly
|
|
|
###-#### VAL OK for Temp Occ. 11/20/2001 4:15:41 PM
|
FIRE-Final Inspection | 11/16/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/16/2001 10:30:21 AM OK for perm occ
|
FIRE-Supply Line Hydro | 11/5/2001 | 11/6/2001 | 11/6/2001 | P | FAIL |
Troy Cobbley
|
|
|
3rd floor a/v's wrong candella, batteries in facp wrong, plans need resubmitted with additional detectors shown, provide map at facp, post sign on riser door, provide phone jacks, provide proper recall, provide address for remote station 11/7/2001 9:50:29 AM
|
BLD-Conference | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PART |
Jim Sly
|
|
|
TAYLOR ###-#### Handrails/landings 9/20/2001 9:06:54 AM
|
BLD-Framing/Rough-in | 7/31/2001 | 7/31/2001 | 7/31/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### C/N...3rd floor...Nail hangers, need all trade R/I appr incl. sprinkler, Nail Gyp at 1hr 7" OC, Maintain 1hr at ceiling or Architect to provide letter omitting Rated ceiling. 7/31/2001 1:57:20 PM
|
BLD-Framing/Rough-in | 6/29/2001 | 7/2/2001 | 7/2/2001 | A | PART |
Jim Sly
|
|
|
###-#### Val Taylor OK to cover 2nd floor. 7/2/2001 9:36:54 AM
|
BLD-Framing/Rough-in | 6/22/2001 | 6/25/2001 | 6/25/2001 | A | PART |
Jim Sly
|
|
|
val ###-#### Frame OK 1st floor only. 6/25/2001 10:42:48 AM
|
BLD-Framing/Rough-in | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | FAIL |
Jim Sly
|
|
|
Val Taylor ###-#### Need all trade finals. 6/5/2001 12:37:36 PM
|
BLD-Framing/Rough-in | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Jim Sly
|
|
|
nail pattern for siding ###-#### Shear nailing OK. 5/30/2001 8:50:50 AM
|
BLD-Conference | 5/8/2001 | 5/9/2001 | 5/9/2001 | A | PART |
Jim Sly
|
|
|
for conf-- val--###-#### -call 1st before insp Review of plans and work completed. 5/9/2001 11:56:31 AM
|
BLD-Foundation | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | PART |
Carl Dependahl
|
|
|
stem wall insp - mike ###-#### , ok pending report 3/19/2001 3:28:35 PM
|
BLD-Footing | 3/16/2001 | 3/16/2001 | 3/16/2001 | P | PART |
Jim Sly
|
|
|
pouring at 1:30 ###-#### Elevator and front column pads OK pending special insp and approval. 3/16/2001 3:38:30 PM
|
BLD-Footing | 3/13/2001 | 3/14/2001 | 3/14/2001 | P | PART |
Russ Owen
|
|
|
###-#### WILL POUR AT 1:30subject to s-i. 3/14/2001 4:10:12 PM
|
BLD-Footing | 3/12/2001 | 3/12/2001 | 3/12/2001 | P | PART |
Jim Sly
|
|
|
###-#### Advised contr. his need of special insp for concrete (3500PSI) 3/12/2001 1:58:41 PM
|