Permit Information
Permit NumberBLD00-01783
StatusFinaled
Name THE HOME DEPOT
Site Address 3639 S FEDERAL WAY
Project NameHOME DEPOT
Customer Number 
ePlanReviewNo
Description
THE HOME DEPOT * TO CONSTRUCT A NEW 115,405 SQ. FT., ONE STORY HOME IMPROVEMENT RETAIL SALES BUILDING WITH AJOINING 20,125 SQ. FT. GARDEN CENTER AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF EXTERIOR MASONRY WALLS WITH STEEL STRUCTURAL FRAME AND METAL ROOF SYSTEM. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST THIS BUILDING IS FULLY FIRE SPRINKLERED. THE SPRINKLERS ARE USED FOR UNLIMITED AREA. FIRE SPRINKLER AND ALARM PLANS ARE REQUIRED ON SEPARATE PERMITS PRIOR TO ANY OVERHEAD OR UNDERGROUND WORK. THE AREA IS INCLUDED WITH THE OTHER ATTACHED RETAIL BUILDINGS PER NONBUILD AREA AGREEMENTS. DRH00-00099/CUP00-00040/PC#498-00/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection5/14/20015/14/20015/14/2001PPASS
DetailsRick Jackson
Added by Inspector: 409 On 5/14/2001 3:20:41 PM
Permanent Occupancy 5/14/20015/14/2001 DONE
Details
BLD-Final5/10/20015/11/20015/11/2001PFAIL
DetailsJim Storey
Keith ###-#### handrail height back stair wrong/ exit sign westend of eile/ sign offs from fire/p&z/achd/ ele 5/11/2001 3:29:24 PM
BLD-Framing/Rough-in3/9/20013/12/20013/12/2001APASS
DetailsJim Storey
###-#### kitchen area framing ok. 3/12/2001 3:34:24 PM
BLD-Framing/Rough-in3/8/20013/9/20013/9/2001APART
DetailsJim Storey
Keith ###-#### interior walls for kitchen area hold downs ok per plan recal for sheathing and top plate hardware. 3/9/2001 11:08:54 AM
BLD-Framing/Rough-in3/9/20013/9/20013/9/2001PCANC
DetailsJim Storey
###-#### called in for monday pm 3/9/2001 2:43:44 PM
BLD-Framing/Rough-in2/16/20012/16/20012/16/2001PPASS
DetailsJim Storey
###-#### front and garden center ok. 2/20/2001 11:43:09 AM
BLD-Framing/Rough-in2/8/20012/9/20012/9/2001AFAIL
DetailsJim Storey
###-#### nfpa sprinkler under stair required/soffit store front fastner shot pins and # of rfi for approval from engineer. nuts at east stair colum to beam need tighten. 2/9/2001 10:33:34 AM
BLD-Framing/Rough-in1/31/20012/1/20012/1/2001APART
DetailsTom Arcoraci
###-#### ok to cover one side cnotice posted 2/1/2001 10:36:40 AM
BLD-Framing/Rough-in1/22/20011/23/20011/23/2001PPART
DetailsJim Storey
Keith ###-#### recieved submital letter to follow with drawings to fire block mezanine floor system duct penatrations and revise smoke fire dampers. d.lightfoot and my self reviewed field plan and are waiting for resubmitals for review. 1/23/2001 2:11:32 PM
BLD-Framing/Rough-in1/22/20011/23/20011/23/2001PPART
DetailsJim Storey
Keith ###-#### recieved submital letter to follow with drawings to fire block mezanine floor system duct penatrations and revise smoke fire dampers. d.lightfoot and my self reviewed field plan and are waiting for resubmitals for review. 1/23/2001 2:11:32 PM
BLD-Framing/Rough-in1/16/20011/17/20011/17/2001APART
DetailsJim Storey
Keith ###-#### arch. to resubmit to address shafts, rated wall configuration at east and west stair off mez., grout required at elavator bar joist, straps need nailled at wall cmu to i joist., 1/17/2001 9:47:56 AM
BLD-Framing/Rough-in1/12/20011/16/20011/16/2001ANR
DetailsCarl Dependahl
Keith ###-####, recall 1/16/2001 9:21:16 AM
BLD-Other1/11/20011/11/20011/11/2001PFAIL
DetailsBill VanDegrift
Added by Inspector: 330 On 1/11/2001 4:08:08 PM american paving installed roof drainage system without a permit, permit, expose, test, call for inspection, double fee
BLD-Framing/Rough-in12/26/200012/27/200012/27/2000APASS
DetailsSteven Webb
###-#### inspected roof deck welds 12/27/2000 9:51:20 AM
BLD-Footing11/30/200012/1/200012/1/2000APASS
DetailsJim Storey
###-####
BLD-Other11/16/200011/16/200011/16/2000AFAIL
DetailsJim Storey
Added by Inspector: 301 On 11/16/2000 9:51:05 AM c/n to hold all cost at north east corner of bldg do to resubmital to maintane 60 ft set back . resubmital routed with p//z, pw/planreview.
BLD-Footing11/3/200011/6/200011/6/2000PPART
DetailsJim Storey
Keith ###-#### interior ft ok rebar ok pending special insp. report. 11/6/2000 3:03:05 PM
BLD-Footing10/30/200010/31/200010/31/2000APART
DetailsJim Storey
Keith ###-#### work in progess covered with special insp. / need colum anchor bolt epoxy lay out missed. from engineer. 10/31/2000 8:52:56 AM
BLD-Footing10/19/200010/20/200010/20/2000PPART
DetailsJim Storey
###-#### placed witpecial insp. pending report. 10/20/2000 11:57:24 AM
BLD-Footing10/17/200010/18/200010/18/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/17/2000 at 16:24:03. Contact: ###-####. 1-4 a line ok pending s/i report. 10/18/2000 3:06:16 PM
BLD-Footing10/16/200010/17/200010/17/2000PPART
DetailsJim Storey
###-#### south wall alin to 10 grid pipes to be protected pend s/i report. 10/17/2000 2:34:02 PM