Permanent Occupancy | | 3/7/2001 | 3/7/2001 | | DONE |
|
|
|
|
BLD-Final | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PASS |
Russ Owen
|
|
|
###-####
|
BLD-Final | 2/8/2001 | 2/9/2001 | 2/9/2001 | A | PART |
Russ Owen
|
|
|
Jim House ###-####. ok for perm oc pending final from zoning. 2/9/2001 11:59:52 AM
|
BLD-Final | 1/18/2001 | 1/19/2001 | 1/19/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 01/18/2001 at 10:11:01. Contact: ###-####.items to correct,c/n posted. 1/19/2001 3:12:05 PM
|
FIRE-Final Inspection | 1/18/2001 | 1/19/2001 | 1/19/2001 | A | PASS |
Joe Tawney
|
|
|
###-####. Reinsp OK for permanant occupancy 1/19/2001 12:31:14 PM
|
FIRE-Final Inspection | 1/18/2001 | 1/18/2001 | 1/18/2001 | P | FAIL |
Joe Tawney
|
|
|
###-####. Final Fail C/N issued 1/19/2001 8:11:35 AM
|
BLD-Other | 1/12/2001 | 1/16/2001 | 1/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/12/2001 at 09:48:37. Contact: ###-####. grid ok 1/16/2001 10:46:45 AM
|
BLD-Framing/Rough-in | 12/8/2000 | 12/11/2000 | 12/11/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/08/2000 at 10:25:05. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/4/2000 | 12/5/2000 | 12/5/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/04/2000 at 10:45:40. Contact: ###-####.basement fire block at stairs and top of mec room wall 2 layers drywall req.also draft stop req. note plan indicates access thru floor to wall above ,needs chase no details in plans. 12/5/2000 12:38:08 PM 12/5/2000 12:44:15 PM
|
BLD-Framing/Rough-in | 11/28/2000 | 11/29/2000 | 11/29/2000 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/28/2000 at 15:08:59. Contact: ###-####.no elec or plm inspections done notified contractor ,to obtain these prior to calling frame insp. 11/29/2000 2:43:58 PM 11/29/2000 2:44:40 PM
|
BLD-Framing/Rough-in | 10/25/2000 | 10/26/2000 | 10/26/2000 | A | PART |
Carl Dependahl
|
|
|
Bill ###-#### masonry ok pend. si report 10/26/2000 10:17:12 AM
|
BLD-Concrete | 10/24/2000 | 10/24/2000 | 10/24/2000 | P | PART |
Carl Dependahl
|
|
|
grout and rebar Bill ###-#### ok pending report, strat 10/24/2000 4:15:33 PM a onsite 10/24/2000 4:15:38 PM
|
BLD-Foundation | 10/20/2000 | 10/20/2000 | 10/20/2000 | P | PART |
Carl Dependahl
|
|
|
block wall Bill ###-####1st lift 10/20/2000 4:05:27 PM
|
BLD-Footing | 10/12/2000 | 10/13/2000 | 10/13/2000 | A | PART |
Alan Hauser
|
|
|
###-####
|
BLD-Framing/Rough-in | 10/10/2000 | 10/11/2000 | 10/11/2000 | A | NR |
Carl Dependahl
|
|
|
SEPEGE BED FOR STORAGE DRAIN --DAVE ###-#### referred to p.w. 10/11/2000 8:56:02 AM
|
BLD-Footing | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### ok pending report 9/29/2000 9:16:31 AM
|
BLD-Concrete | 9/26/2000 | 9/27/2000 | 9/27/2000 | A | PART |
Tom Arcoraci
|
|
|
Bill ###-#### slab on grade only spec insp for concrete stren 9/27/2000 11:22:39 AM
|
BLD-Footing | 9/14/2000 | 9/15/2000 | 9/15/2000 | P | PART |
Jim Storey
|
|
|
Bill ###-#### covered w/s/i. 9/15/2000 4:51:14 PM
|
BLD-Conference | 9/8/2000 | 9/8/2000 | 9/8/2000 | P | PASS |
Tom Arcoraci
|
|
|
Added by Inspector: 408 On 9/8/2000 conf on project first inspection 9/8/2000 11:48:49 AM
|
BLD-Footing | 9/7/2000 | 9/8/2000 | 9/8/2000 | A | PART |
Carl Dependahl
|
|
|
Mikeque ###-####... 9/8/2000 10:51:40 AM
|