Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD00-01894
StatusFinaled
Name ELEVATED ROAD
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT-ELEVATED ROAD
Customer Number 
ePlanReviewNo
Description
AIRPORT ELEVATED ROADWAY * TO CONSTRUCT AN APPROXIMATE 800 LIN. FT. CONCRETE, FOUR LANE ELEVATED ROADWAY WITH CONNECTING ROAD ACCESS RAMPS AND PEDESTRIAN WALKWAYS AND EXIT STAIRWAY. THIS PERMIT ALSO INCLUDES THE CONSTRUCTION OF THE SURFACE ACCESS ROADS FOR THE NEW BOISE AIR TERMINAL, AS WELL AS, A NEW COVERED PEDESTRIAN BRIDGE CONNECTING THE EXISTING PARKING GARAGE AND THE NEW ELEVATED ROADWAY PEDESTRIAN WALK. THE ELEVATED ACCESS ROADWAY IS BEING DESIGNED AND CONSTRUCTED UNDER THE APPLICABLE REQUIREMENTS OF THE AASHTO "STANDARD SPECIFICATIONS FOR HIGHWAY BRIDGES" 1996 EDITION. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. DRH99-00206/CUP99-00130/PC#533-00/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/19/20032/20/20032/20/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/19/2003 at 2:17:37 PM. Contact: ###-####. finanl ok all special insp and engineering sign offs in archive. 2/20/2003 10:54:37 AM per approved plan from plan review. 2/20/2003 10:56:38 AM
BLD-Final2/12/20032/13/20032/13/2003PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/12/2003 at 16:05:14. Contact: ###-####. stil need gaurd rail height at west end and east end. 2/13/2003 4:05:15 PM
FIRE-Final Inspection2/11/20032/12/20032/12/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 2/11/2003 at 8:38:50 AM. Contact: ###-####.
BLD-Aging Inspection2/4/20032/4/20032/4/2003 PART
DetailsJim Storey
wip 2/4/2003 7:34:58 AM
Code Occupancy Approval12/5/200212/5/200212/5/2002PDONE
DetailsScott M.Brown
FINAL SIGNRD OFF. 12/5/2002 4:25:01 PM
FIRE-Final Inspection12/4/200212/5/200212/5/2002AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/04/2002 at 09:41:20. Contact: ###-####. need clarification on location of hydrants in relation to the cab road; per Dave Miller he will talk with Ken Schneider about this 12/5/2002 5:02:36 PM
BLD-Final12/2/200212/3/200212/3/2002PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/02/2002 at 10:24:51. Contact: ###-####.gaurdrail min 42 inches/ engineer of record letter of approval for all rfi's and review of all special insp. reports / soil special insp final afadivad sign off/ lock on power doors at parking garage/ all other required signoffs per permit. 12/3/2002 4:55:49 PM
BLD-Foundation10/8/200110/10/200110/10/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/08/2001 at 17:15:53. Contact: ###-####. placed with special insp. unable to get there. 10/10/2001 3:44:41 PM
BLD-Foundation10/8/200110/9/200110/9/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/08/2001 at 17:15:07. Contact: ###-####. east roadway back fill and retaining wall ft ok special insp on site. rebar on bridge deck in progess. engineer to address dope psi loading being crushed under rebar loading will be replaced. followed through special insp with rfi pending./ wating for ducts for pt profils. 10/9/2001 11:46:08 AM
BLD-Foundation9/17/20019/20/20019/20/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/17/2001 at 15:04:56. Contact: ###-####. placed with special insp. pending report. 9/20/2001 3:09:43 PM
BLD-Foundation9/17/20019/19/20019/19/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/17/2001 at 15:04:04. Contact: ###-####. covered w/s/i 9/19/2001 11:13:36 AM
BLD-Foundation9/17/20019/18/20019/18/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/17/2001 at 15:03:12. Contact: ###-####. placed w/special insp. pending reports 9/18/2001 10:40:24 AM
BLD-Foundation8/27/20018/31/20018/31/2001APART
DetailsJim Storey
harry ###-#### covered by special insp. 8/31/2001 10:39:30 AM
BLD-Foundation8/27/20018/30/20018/30/2001AFAIL
DetailsJim Storey
harry ###-#### shat rebar lap splice not per drawings rfi required to justify before placement/ spiral bar pitch being addressed for correction colm forms being removed for reinsp. 8/30/2001 9:58:43 AM
BLD-Foundation8/27/20018/29/20018/29/2001APART
DetailsJim Storey
harry ###-#### placedwith special insp. pending report. 8/29/2001 10:35:20 AM
BLD-Foundation8/27/20018/28/20018/28/2001APART
DetailsSteven Webb
harry ###-#### covered under special inspectors 8/28/2001 8:49:06 AM
BLD-Foundation8/20/20018/21/20018/21/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/20/2001 at 10:39:51. Contact: ###-####. b piling rebar ok. 8/21/2001 9:37:47 AM