BLD-Final | 3/15/2002 | 3/15/2002 | 3/15/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by Inspector: 301 On 3/15/2002 4:19:52 PM final ok 3/15/2002 4:32:26 PM
|
Permanent Occupancy | | 3/15/2002 | 3/15/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Rick Jackson
|
|
|
dave- ###-#### fire fn
|
FIRE-Final Inspection | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/20/2001 7:34:23 PM basement battery room doors; hazard signs
|
BLD-Final | 11/15/2001 | 11/16/2001 | 11/16/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/15/2001 at 07:50:17. Contact: ###-####. temp ok pendingf others. 11/16/2001 12:56:24 PM
|
BLD-Conference | 10/18/2001 | 10/19/2001 | 10/19/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/18/2001 at 10:10:23. Contact: ###-####.
|
BLD-Final | 10/13/2001 | 10/15/2001 | 10/15/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/13/2001 at 16:05:47. Contact: ###-####. steve will e-mail c/n punch list. door isues/ some fire chalking. 10/15/2001 3:49:38 PM
|
BLD-Final | 10/9/2001 | 10/10/2001 | 10/10/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 14:40:52. Contact: ###-####. need door butt listing for rated assemblie. 10/11/2001 9:46:08 AM
|
BLD-Final | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/26/2001 at 09:39:30. Contact: ###-####. fire stopping/fire prooffing 1st floor. 9/27/2001 6:24:12 PM
|
BLD-Final | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | NR |
Jim Storey
|
|
|
###-#### STEVE
|
BLD-Final | 9/13/2001 | 9/14/2001 | 9/14/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/13/2001 at 17:23:16. Contact: ###-####. cable trays 2 floor ok all but 2 locations/ c/n for grid wires. 9/17/2001 1:04:54 PM
|
BLD-Final | 9/12/2001 | 9/14/2001 | 9/13/2001 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 14:17:25. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/13/2001 at 17:21:53.
|
BLD-Framing/Rough-in | 6/27/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/27/2001 at 17:20:17. Contact: ###-####. cafatria curtian walls ok/ interior framing ok pending others 6/29/2001 10:37:15 AM
|
FIRE-Sprinkler Rough-in | 5/21/2001 | 5/22/2001 | 5/22/2001 | P | FAIL |
Rick Jackson
|
|
|
Forrest ###-#### heads overspaced in areas 7 and 8 first floor. main office areas from soffit and office walls; not approved for cover 5/22/2001 3:24:48 PM
|
BLD-Wall cover | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 12:11:42. Contact: ###-####. cable coridor assemblies in place at south end of coridor ok at marked locations only ok. 5/18/2001 11:39:38 AM
|
BLD-Other | 5/14/2001 | 5/14/2001 | 5/14/2001 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 09:42:10. Contact: . fire stopping and lights for grid/ need fire and mec. insp. 5/15/2001 11:06:27 AM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Jim Storey
|
|
|
wall cover steve- ###-####
|
BLD-Wall cover | 4/24/2001 | 4/25/2001 | 4/25/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/24/2001 at 09:22:04. Contact: ###-####. previous c/n made ok. 4/25/2001 4:58:09 PM
|
BLD-Wall cover | 4/18/2001 | 4/19/2001 | 4/19/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/18/2001 at 14:43:14. Contact: ###-####. corridor bld b an c 1st and 2nd floors ok top of walls/raised floor sys need to fire stop bld b. 4/19/2001 5:25:35 PM
|
BLD-Conference | 4/2/2001 | 4/5/2001 | 4/5/2001 | A | PASS |
Jim Storey
|
|
|
11:00 is the time you set with him. ###-#### ext 241
|
BLD-Framing/Rough-in | 3/28/2001 | 3/29/2001 | 3/29/2001 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/28/2001 at 16:50:54. Contact: ###-####. area septration and shaft opening protection c/n/// 3/30/2001 11:41:06 AM
|
BLD-Wall cover | 3/9/2001 | 3/12/2001 | 3/12/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/09/2001 at 08:51:19. Contact: ###-####. 1 st floor area 7 and 8 ok for cover. 3/12/2001 9:38:50 AM
|
BLD-Framing/Rough-in | 3/2/2001 | 3/5/2001 | 3/5/2001 | A | PART |
Jim Storey
|
|
|
###-#### ext 241 2nd floor area 7/8 ok to top hang walls pending ele approval. for balance of wall cover reinsp required. 3/5/2001 4:34:34 PM
|
BLD-Framing/Rough-in | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | NR |
Jim Storey
|
|
|
Steve Smith ###-####
|
BLD-Framing/Rough-in | 2/12/2001 | 2/12/2001 | 2/12/2001 | P | PART |
Jim Storey
|
|
|
Added by Inspector: 301 On 2/12/2001 1:02:44 PM c/n submital for colum protection, ele box protection < 24 spacing, pre rock for plumb pipe fire stopping at 17/d,e , wrap beam to maintain corrdor at 16,17/d,e.
|