Permit Information
Permit NumberBLD00-02170
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMIC #35-(PCS 3158)
Customer Number35-003158
ePlanReviewNo
Description
MICRON BUILDING #35 * TO CONSTRUCT A NEW 52,000 SQ. FT., TWO STORY FACILITIES MAINTENANCE SHOP AND OFFICE BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS, STEEL INTERIOR FRAME, CONCRETE AND METAL FLOOR PAN AND METAL ROOF DECK WITH CLASS I ROOF COVERING. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPINKLERS ARE BEING USED FOR ALLOWABLE AREA INCREASE. THIS BUILDING WILL CONTAIN MAINTENANCE SHOPS AND LAUNDRY FACILITY AT THE FIRST FLOOR AND OFFICES ON THE SECOND FLOOR. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. PC#598-00/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/1/20023/4/20023/4/2002APASS
DetailsJim Storey
Scheduled by Inspector: 407 On 3/1/2002 11:26:04 AM final ok for c.o. 3/4/2002 2:52:12 PM
Permanent Occupancy 3/4/20023/4/2002 DONE
Details
BLD-Final2/28/20023/1/20023/1/2002ACANC
DetailsRuss Owen
###-#### John ,I called left message to call me back I have set this back up for am monday.1/2002 11:51:03 AM 3/1/2002 11:54:03 AM
BLD-Final2/20/20022/21/20022/21/2002AFAIL
DetailsJim Storey
###-#### DON fire stopping needed at plm. 2/21/2002 9:20:13 AM
BLD-Final1/31/20022/1/20022/1/2002PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/31/2002 at 08:04:18. Contact: ###-####. recieved engineers approval letter and special insp approval. ok for temp. 2/1/2002 2:41:28 PM
FIRE-Final Inspection1/31/20022/1/20022/1/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/31/2002 at 08:03:29. Contact: ###-####.
FIRE-Final Inspection1/17/20021/17/20021/17/2002AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 1/17/2002 11:01:35 AM need exit signs on second floor; sprinkler certification paperwork; tested alarms - okay with monor corections
BLD-Conference11/15/200111/16/200111/16/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/15/2001 at 10:55:35. Contact: ###-####. fire shudder test req/ fire stop top of corridor walls south east exit. pending all other trades. need engineers sign off and special insp. final letter. 11/16/2001 11:02:24 AM
BLD-Conference11/15/200111/19/200111/15/2001ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/15/2001 at 10:34:15. Contact: . Disp set to [CANC] by a contractor via Hello! on 11/15/2001 at 10:54:16.
BLD-Final10/30/200111/5/200111/1/2001ACANC
DetailsJim Storey
###-#### Disp set to [CANC] by a contractor via Hello! on 11/01/2001 at 14:37:43.
FIRE-Final Inspection10/29/200111/1/200111/1/2001ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/29/2001 at 14:46:09. Contact: ###-####. will reschedule 10/31/2001 5:07:37 PM
BLD-Conference10/18/200110/19/200110/19/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/18/2001 at 14:46:29. Contact: ###-####.
BLD-Other9/17/20019/18/20019/18/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/17/2001 at 12:59:16. Contact: ###-####. 2 nd floor ceilling/ need speader bars. 9/18/2001 10:40:59 AM
BLD-Other9/5/20019/7/20019/7/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/05/2001 at 15:22:43. Contact: ###-####. south 1/2 ceilling ok. 9/10/2001 5:54:47 PM
BLD-Framing/Rough-in8/8/20018/9/20018/9/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/08/2001 at 09:42:32. Contact: ###-####. hard ceilling at west dock beams protccted and support grid ok for cover/ grid ceilling 2 nd floor work in progess no problems. 8/9/2001 11:39:12 AM
BLD-Framing/Rough-in7/9/20017/10/20017/10/2001APASS
DetailsJim Storey
Jualo ###-####
BLD-Framing/Rough-in5/16/20015/17/20015/17/2001APASS
DetailsJim Storey
Hulo ###-#### 1 & 2nd floor framing ok for cover / arch to address west stair for opening protection. 5/17/2001 9:50:16 AM
BLD-Framing/Rough-in5/10/20015/14/20015/14/2001APASS
DetailsJim Storey
###-#### 2nd floor ok for cover. 5/14/2001 4:34:15 PM
BLD-Framing/Rough-in5/3/20015/8/20015/8/2001AFAIL
DetailsJim Storey
Jullo ###-#### c/n for rfi to arch. 5/8/2001 1:03:24 PM
BLD-Framing/Rough-in5/1/20015/3/20015/3/2001APART
DetailsSteven Webb
julio-- ###-#### fr Partial--Building 35-2nd floor offices at east and west end. 5/3/2001 9:55:27 AM
BLD-Framing/Rough-in4/16/20014/16/20014/16/2001PPART
DetailsJim Storey
###-#### fur out walls ok for cover / c/n for out standing special insp. issues. 4/16/2001 6:31:30 PM
BLD-Framing/Rough-in3/14/20013/15/20013/15/2001APART
DetailsJim Storey
###-#### diaphram roof welds ok south end. reviewed col/fire assemblie/ 3/15/2001 4:37:51 PM
BLD-Framing/Rough-in3/12/20013/13/20013/13/2001AFAIL
DetailsJim Storey
WELDING ON ROOF AND FLOOR DECKING\\###-#### missing welds and botton punching on roof and 2 nd floor / special insp need to verify when corected. 3/13/2001 10:18:49 AM
BLD-Other2/28/20012/28/20012/28/2001 FAIL
DetailsJim Storey
special insp report feb 16 2001. tilt panels 14,15,16,20,22,23 air spec. 4% to 7% test results were 2% need engineer of record to justify not meetting freeze protection provision and design spec.
BLD-Foundation1/18/20011/18/20011/18/2001PPART
DetailsJim Storey
re-bar julio ###-#### placed with special insp. pending report. 1/18/2001 4:14:29 PM
BLD-Framing/Rough-in1/4/20011/5/20011/5/2001PPART
DetailsJim Storey
REBAR JULIO-- ###-#### placed with special insp. pending report. 1/8/2001 7:57:48 AM
BLD-Other12/29/200012/29/200012/29/2000AFAIL
DetailsBill VanDegrift
Added by Inspector: 330 On 12/29/2000 3:57:54 PM left correction notice - secure a permit for sewer and water lines relocated outside the building, provide documentation from micron reguarding testing and inspection for determination of code compliance, - secure a licensed plumbing contractor to permit 10" storm drain under the building apply test and call for inspection- do not lay asphalt over exterior piping or concrete over interior storm drain untill all waor has been approved for cover.
BLD-Footing12/21/200012/22/200012/22/2000APART
DetailsCarl Dependahl
Garry ###-####; pend spec. insp reports 12/22/2000 10:14:24 AM
BLD-Footing12/14/200012/15/200012/15/2000ANR
DetailsJim Storey
###-####
BLD-Foundation12/13/200012/13/200012/13/2000PPART
DetailsJim Storey
###-#### REBAR placed with special insp. 12/13/2000 4:43:04 PM
BLD-Foundation12/5/200012/5/200012/5/2000PPART
DetailsJim Storey
###-#### work in progess covered with s/i 12/5/2000 3:34:36 PM
BLD-Footing11/27/200011/28/200011/28/2000PPART
DetailsJim Storey
###-#### p/w/s/i/ pending report. 11/28/2000 3:49:21 PM
FIRE-Final Inspection11/27/200011/28/200011/28/2000PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/27/2000 at 14:55:29. Contact: ###-####.//// entered by contractor in error 11/28/2000 3:22:58 PM