Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-02437
StatusFinaled
Name VISTA INN BEST WESTERN
Site Address 2645 W AIRPORT WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
VISTA INN * ADDITION OF 6,092 SQ. FT. TO THE SOUTHEAST CORNER OF THE EXISTING MOTEL. EXTEND EXISTING AREA SEPARATION WALL ACROSS CORRIDOR AND TO THE EXTERIOR WALL. THE ADDITION INCLUDES A 3,000 SQ.FT. CONFERENCE ROOM WHICH HAS PARTITION WALLS TO DIVIDE THE AREA INTO THREE SMALLER CONFERENCE ROOMS. THIS AREA ALSO INCLUDES A BOARD ROOM, RESTROOMS & PANTRY. ALL WORK PER THE APPROVED PLANS, ATTACHED COMMENT LIST AND CABO/ANSI A117.1. NOTE: THIS PORTION OF THE BUILDING IS FIRE SPRINKLERED FOR ONE-HOUR SUBSTITUTION AND THE MOTEL AREA IS FIRE SPRINKLERED FOR AREA INCREASE. DRH00-00124 PC#670-00 MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 4/18/20014/18/2001 DONE
Details
BLD-Final3/20/20013/20/20013/20/2001PPART
DetailsJim Storey
Stan ###-#### temp ok pendig plm sign off for perm. 3/20/2001 5:36:51 PM
BLD-Final3/19/20013/19/20013/19/2001PFAIL
DetailsJim Storey
fn --stan-- ###-#### door hardware adjustment/ada signage and protection/ occ load sign. 3/19/2001 4:04:44 PM
FIRE-Final Inspection3/16/20013/19/20013/19/2001APASS
DetailsRick Jackson
Stan Wiggins ###-####
BLD-Final3/16/20013/16/20013/16/2001PNR
DetailsJim Storey
after 1:00\\###-####
FIRE-Final Inspection3/15/20013/16/20013/16/2001PNR
DetailsRick Jackson
Stan ###-#### contractor called and said he rated door in the two hour wall isn't complete and will schedule for next week 3/16/2001 3:07:20 PM
FIRE-Final Inspection3/14/20013/14/20013/14/2001AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 3/14/2001 10:22:57 AM raed doors not complete; exinguishers; alarm problems
BLD-Framing/Rough-in3/6/20013/6/20013/6/2001PNR
DetailsCarl Dependahl
left msg...unable to contact 3/6/2001 4:23:53 PM
BLD-Framing/Rough-in3/5/20013/5/20013/5/2001PNH
DetailsJim Storey
###-####
FIRE-Sprinkler Rough-in2/26/20012/26/20012/26/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 2/26/2001 3:19:20 PM okay to cover
BLD-Framing/Rough-in2/13/20012/13/20012/13/2001PPASS
DetailsJim Storey
Stan Wiggins ###-####
BLD-Framing/Rough-in2/7/20012/7/20012/7/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/07/2001 at 08:49:38. Contact: ###-####. drinking foutian requied/ele boxe back to back/two layer must turn at door assembly/fire stop above bathroom hard ceillings for penatrations in tunnel corridor/ pending all other insp aprovals call for reinsp for idems listed. 2/7/2001 5:15:36 PM
BLD-Framing/Rough-in1/22/20011/23/20011/23/2001APART
DetailsJim Storey
###-#### c/n to reinsp. sheer attchment on east and west bearing walls 6/12 pattern spec.. 1/23/2001 9:32:20 AM
BLD-Framing/Rough-in1/23/20011/23/20011/23/2001PPART
DetailsJim Storey
Stan ###-#### exterior sheer ok for cover. 1/23/2001 2:47:22 PM
BLD-Framing/Rough-in1/17/20011/17/20011/17/2001PPART
DetailsJim Storey
PARTIAL FRAM\\###-#### need to relocate ramp landing per plan at 2 hr doors. 1/17/2001 2:55:52 PM
BLD-Footing12/19/200012/20/200012/20/2000APART
DetailsJim Storey
Stan Wiggins ###-#### rebar ok pending special insp./ need engineering doc for sheer wall design at holddowns. 12/20/2000 11:28:29 AM