Permanent Occupancy | | 4/18/2001 | 4/18/2001 | | DONE |
|
|
|
|
BLD-Final | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | PART |
Jim Storey
|
|
|
Stan ###-#### temp ok pendig plm sign off for perm. 3/20/2001 5:36:51 PM
|
BLD-Final | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | FAIL |
Jim Storey
|
|
|
fn --stan-- ###-#### door hardware adjustment/ada signage and protection/ occ load sign. 3/19/2001 4:04:44 PM
|
FIRE-Final Inspection | 3/16/2001 | 3/19/2001 | 3/19/2001 | A | PASS |
Rick Jackson
|
|
|
Stan Wiggins ###-####
|
BLD-Final | 3/16/2001 | 3/16/2001 | 3/16/2001 | P | NR |
Jim Storey
|
|
|
after 1:00\\###-####
|
FIRE-Final Inspection | 3/15/2001 | 3/16/2001 | 3/16/2001 | P | NR |
Rick Jackson
|
|
|
Stan ###-#### contractor called and said he rated door in the two hour wall isn't complete and will schedule for next week 3/16/2001 3:07:20 PM
|
FIRE-Final Inspection | 3/14/2001 | 3/14/2001 | 3/14/2001 | A | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/14/2001 10:22:57 AM raed doors not complete; exinguishers; alarm problems
|
BLD-Framing/Rough-in | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | NR |
Carl Dependahl
|
|
|
left msg...unable to contact 3/6/2001 4:23:53 PM
|
BLD-Framing/Rough-in | 3/5/2001 | 3/5/2001 | 3/5/2001 | P | NH |
Jim Storey
|
|
|
###-####
|
FIRE-Sprinkler Rough-in | 2/26/2001 | 2/26/2001 | 2/26/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/26/2001 3:19:20 PM okay to cover
|
BLD-Framing/Rough-in | 2/13/2001 | 2/13/2001 | 2/13/2001 | P | PASS |
Jim Storey
|
|
|
Stan Wiggins ###-####
|
BLD-Framing/Rough-in | 2/7/2001 | 2/7/2001 | 2/7/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/07/2001 at 08:49:38. Contact: ###-####. drinking foutian requied/ele boxe back to back/two layer must turn at door assembly/fire stop above bathroom hard ceillings for penatrations in tunnel corridor/ pending all other insp aprovals call for reinsp for idems listed. 2/7/2001 5:15:36 PM
|
BLD-Framing/Rough-in | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | PART |
Jim Storey
|
|
|
###-#### c/n to reinsp. sheer attchment on east and west bearing walls 6/12 pattern spec.. 1/23/2001 9:32:20 AM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | PART |
Jim Storey
|
|
|
Stan ###-#### exterior sheer ok for cover. 1/23/2001 2:47:22 PM
|
BLD-Framing/Rough-in | 1/17/2001 | 1/17/2001 | 1/17/2001 | P | PART |
Jim Storey
|
|
|
PARTIAL FRAM\\###-#### need to relocate ramp landing per plan at 2 hr doors. 1/17/2001 2:55:52 PM
|
BLD-Footing | 12/19/2000 | 12/20/2000 | 12/20/2000 | A | PART |
Jim Storey
|
|
|
Stan Wiggins ###-#### rebar ok pending special insp./ need engineering doc for sheer wall design at holddowns. 12/20/2000 11:28:29 AM
|