BLD-Final | 6/26/2001 | 6/26/2001 | 6/26/2001 | | PASS |
Russ Owen
|
|
|
Final/ok to issue perm. occ.
|
Permanent Occupancy | | 6/26/2001 | 6/26/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/22/2001 | 6/22/2001 | 6/22/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/22/2001 8:57:52 AM
|
BLD-Final | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PART |
Russ Owen
|
|
|
guardrails have been completed ,need the final letter from s-i and efis contractor and signatures for final. 12/21/2001 11:04:18 AM
|
BLD-Final | 5/16/2001 | 5/17/2001 | 5/17/2001 | P | PART |
Russ Owen
|
|
|
temp occ Ted ###-#### ok temp oc,need final letter for s-i and efis system, guardrail.at front. and all other signature. 12/17/2001 5:39:14 PM
|
FIRE-Final Inspection | 5/14/2001 | 5/15/2001 | 5/15/2001 | P | PART |
Joe Tawney
|
|
|
Ted Parrott ###-#### Final OK for temporary occupancy. Remaining items exc FACP to be completed within 2 to 3 days 5/15/2001 3:46:41 PM
|
FIRE-Final Inspection | 5/9/2001 | 5/10/2001 | 5/10/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail Alarm system 5/10/2001 2:28:05 PM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/7/2001 | 5/7/2001 | A | PART |
Russ Owen
|
|
|
handrail ted ###-#### laft stairway at front face has cooetions,also left ramp req handrails or architect to submit. 12/7/2001 12:01:23 PM
|
BLD-Framing/Rough-in | 4/23/2001 | 4/24/2001 | 4/24/2001 | A | PART |
Russ Owen
|
|
|
ceiling ted ###-#### ok to install ceiling grid, noted ext handrails not incompliance,also need approved ext wall cover for studs at 24 oc as per plans. 11/24/2001 1:59:29 PM
|
BLD-Framing/Rough-in | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | PART |
Russ Owen
|
|
|
Ted Parrot ###-#### complete upper floor lights and lower floor adnl pods. 4/3/2001 12:42:39 PM
|
BLD-Framing/Rough-in | 3/1/2001 | 3/1/2001 | 3/1/2001 | P | PASS |
Russ Owen
|
|
|
###-####corrections made and verified by pinacle,project engineer.ok to sheetrock.exterior parapet still requires addnl anchorage. 3/1/2001 5:36:00 PM
|
BLD-Framing/Rough-in | 2/21/2001 | 2/22/2001 | 2/22/2001 | A | PART |
Russ Owen
|
|
|
###-####meet with framer will ,correct items and recall. 2/22/2001 12:22:35 PM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/21/2001 | 2/21/2001 | A | FAIL |
Russ Owen
|
|
|
###-####,will meet with framer am. to go over c/n. 2/21/2001 1:54:36 PM
|
BLD-Foundation | 11/28/2000 | 11/29/2000 | 11/29/2000 | A | PART |
Russ Owen
|
|
|
Ted Parrott ###-#### subject to s-i 11/29/2000 12:25:47 PM
|
BLD-Footing | 11/17/2000 | 11/20/2000 | 11/20/2000 | A | PART |
Tom Arcoraci
|
|
|
will pour at 1:00\\###-#### sp insp 11/20/2000 8:45:51 AM
|
BLD-Footing | 11/13/2000 | 11/14/2000 | 11/14/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; spec insp report pending 11/14/2000 10:23:30 AM
|