BLD-Final | 5/22/2001 | 5/22/2001 | 5/22/2001 | P | PASS |
Tom Arcoraci
|
|
|
Gene ###-#### please call first before going out ok for perm occ 5/22/2001 1:56:41 PM
|
BLD-Final | 5/16/2001 | 5/17/2001 | 5/17/2001 | A | PART |
Tom Arcoraci
|
|
|
Gene ###-#### please call first ok for temp occ need letters from spec insp and eng of record 5/17/2001 11:21:31 AM
|
BLD-Final | 5/15/2001 | 5/15/2001 | 5/15/2001 | A | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 5/15/2001 10:41:01 AM Reinsp OK FOR CERTIFICATE OF CONPLETION
|
FIRE-Final Inspection | 5/11/2001 | 5/11/2001 | 5/11/2001 | P | FAIL |
Joe Tawney
|
|
|
Gean ###-#### please call first Reinsp Fail hydro test FDC and spud in inspector test line 5/11/2001 2:08:10 PM
|
FIRE-Final Inspection | 4/30/2001 | 5/1/2001 | 5/1/2001 | A | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail C/N issued 5/1/2001 12:13:49 PM
|
FIRE-Final Inspection | 4/27/2001 | 4/30/2001 | 4/30/2001 | A | CANC |
Joe Tawney
|
|
|
###-#### call first Cancel To be rescheduled 4/30/2001 12:04:37 PM
|
BLD-Conference | 3/15/2001 | 3/16/2001 | 3/16/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 3/15/2001 10:55:19 AM
|
BLD-Framing/Rough-in | 3/14/2001 | 3/15/2001 | 3/15/2001 | A | PART |
Tom Arcoraci
|
|
|
Gene ###-#### rough in on the mechincal room. wip ok to cover elec room 3/15/2001 10:51:38 AM
|
BLD-Framing/Rough-in | 1/29/2001 | 1/29/2001 | 1/29/2001 | P | PART |
Tom Arcoraci
|
|
|
###-#### welding for joist, metal deck on roof wip 1/29/2001 3:10:25 PM
|
BLD-Concrete | 1/3/2001 | 1/5/2001 | 1/5/2001 | A | PASS |
Dave Hannah
|
|
|
GENE ###-####- CONCRETE PANEL TILT UPS
|
BLD-Foundation | 1/3/2001 | 1/3/2001 | 1/3/2001 | P | PART |
Tom Arcoraci
|
|
|
COLUMN & REBAR-- GENE ###-#### spec insp 1/3/2001 1:29:52 PM
|
BLD-Footing | 12/18/2000 | 12/18/2000 | 12/18/2000 | P | PART |
Tom Arcoraci
|
|
|
FT -WILL POUR 3-- GENE ###-#### wip sp insp 12/18/2000 2:09:43 PM
|
BLD-Concrete | 12/14/2000 | 12/15/2000 | 12/15/2000 | A | PASS |
Dave Hannah
|
|
|
CONCRETE-- GENE ###-####special inspector on site 12/15/2000 10:35:34 AM
|
BLD-Concrete | 12/12/2000 | 12/13/2000 | 12/13/2000 | A | PART |
Tom Arcoraci
|
|
|
rebar and tilt up panels Jean ###-#### pouring at 9:00 wip 12/13/2000 10:30:40 AM
|
BLD-Concrete | 12/5/2000 | 12/5/2000 | 12/5/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/5/2000 5:03:52 PM mti onsite
|
BLD-Conference | 12/4/2000 | 12/4/2000 | 12/4/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/4/2000 3:16:49 PM w/ John Menard re plans
|
BLD-Concrete | 11/17/2000 | 11/20/2000 | 11/20/2000 | A | PART |
Alan Hauser
|
|
|
###-#### slab insp
|
BLD-Concrete | 11/14/2000 | 11/14/2000 | 11/14/2000 | P | PART |
Dave Hannah
|
|
|
###-#### please call first
|