BLD-Conference | 4/2/2001 | 4/2/2001 | 4/2/2001 | | PASS |
Carl Dependahl
|
|
|
Issued c/o to big easy but included letter stating posted occupant load of assembly area of first floor was 564 standing and 263 with seating and it would be adhered to. Present was Phil of simplot const. Carl Dependahl building inspector, George Slane supervisor and Jenifer Gilliland Deputy Director PDS.
|
BLD-Final | 4/2/2001 | 4/2/2001 | 4/2/2001 | P | PASS |
Carl Dependahl
|
|
|
fn occ-- phil ###-####
|
Permanent Occupancy | | 4/2/2001 | 4/2/2001 | | DONE |
|
|
|
|
BLD-Final | 3/27/2001 | 3/27/2001 | 3/27/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### Contr opted to get final insp from original inspector or other inspectors involved with project from start. 3/27/2001 3:45:51 PM 3/27/2001 3:46:35 PM
3/27/2001 3:49:48 PM
|
BLD-Conference | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/15/2001 4:07:19 PM w/ BFD re c/n; met w/ Simplot & Bravo Ent...provide monitoring of loads or risk revocation of occ. cert.
|
BLD-Final | 1/8/2001 | 1/8/2001 | 1/8/2001 | P | PART |
Carl Dependahl
|
|
|
8###-#### c/n, ok for t/o 1/8/2001 6:32:11 PM
|
FIRE-Final Inspection | 1/8/2001 | 1/8/2001 | 1/8/2001 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | FAIL |
Jim Storey
|
|
|
FN OCC PHIL ###-#### no aproved plans on site resubmitals for occ. exiting changes. 1/5/2001 5:32:35 PM
|
FIRE-Final Inspection | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | FAIL |
Rick Jackson
|
|
|
FN FIRE ###-#### PHIL resubmittals not available for stair and occupant load changes 1/8/2001 11:20:18 AM
|
BLD-Final | 12/28/2000 | 12/29/2000 | 12/29/2000 | A | PART |
Jim Storey
|
|
|
###-#### phil l/c for only one night 12/31/2000 12/29/2000 4:58:47 PM
|
FIRE-Final Inspection | 12/28/2000 | 12/28/2000 | 12/29/2000 | P | PART |
Rick Jackson
|
|
|
phil ###-####/// okay to occupy for 12/31 only 1/2/2001 8:33:32 AM
|
FIRE-Final Inspection | 12/19/2000 | 12/19/2000 | 12/21/2000 | P | FAIL |
Rick Jackson
|
|
|
PER PHIL FOR CONF/// met with architecft about exiting and occupant loads 12/21/2000 10:36:28 AM
|
BLD-Conference | 12/14/2000 | 12/14/2000 | 12/14/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/14/2000 3:59:51 PM w/ YMC re hvac...need letter of clarification for corridor
|
BLD-Conference | 12/13/2000 | 12/13/2000 | 12/13/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/13/2000 5:55:17 PM re stairs
|
BLD-Framing/Rough-in | 12/6/2000 | 12/7/2000 | 12/7/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; need clarify cooridor door addns, gate at stairs, hvac at corridor; ok to place 1st layer lid & rock bath area 12/7/2000 12:27:59 PM
|
BLD-Conference | 12/1/2000 | 12/1/2000 | 12/1/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/1/2000 12:08:25 PM referred to fire insp re sprinklers below stage
|