Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-02920
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMIC 24D/24E-TI
Customer NumberPCS3141
ePlanReviewNo
Description
MICRON BUILDING 24D & 24E - CP4 - TENANT IMPROVEMENT FOR FAB (B24D) AND LAB (B24E) * (24D-003141) TO FINISH MICRON FABRICATION BUILDING 24D AND LABORATORY BUILDING 24E FOR OCCUPANCY. THIS PERMIT WILL INCLUDE THE CONSTRUCTION AND INSTALLATION OF ALL NECESSARY MATERIAL AND EQUIPMENT TO COMPLETE THIS BUILDING FOR FULL OPERATION. BUILDING #24D CONSISTS OF A 36,635 SQ. FT. BASEMENT, A 50,350 SQ. FT. SUBFABRICATION AREA, A 52,000 SQ. FT. FIRST FLOOR FABRICATION AREA AND A 47,000 SQ. FT. SECOND STORY UNOCCUPPIED FAN DECK. THIS BUILDING ALSO CONTAINS AN INTERSTITIAL CATWALK LEVEL BETWEEN THE FAB AND FAN DECK LEVELS. BUILDING #24E CONSISTS OF A 19,200 SQ. FT. BASEMENT LEVEL CONTAINING RESTROOMS, OFFICE AND LAB AREAS; AND A 24,100 SQ. FT. FIRST STORY CONTAINING OFFICE, LAB AND CHEMICAL STORAGE AREAS. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPRINKLERS ARE USED FOR AREA INCREASE. THIS PERMIT IS ALSO FOR THE CONSTRUCTION OFAN APPROXIMATE 775 LIN. FT., 52 FT. TALL, STRUCTURAL STEEL BRIDGE TO BE USED TO SUPPORT PRODUCTION PROCESS PIPING FROM BUILDING #25. THIS PIPE BRIDGE IS BEING CONSTRUCTED ALONG THE WEST SIDE OF BUILDING #24 TO BUILDING #25. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THE SHELL BUILDING WAS CONSTRUCTED UNDER PERMIT BLD00-01988. PC#793-00/JCM This sign-off card is for a temporary occupancy requested for a portion of the this building that will include occupancy of all portions of Building #24D, with the exception of first floor rooms #160A Synthisis Lab, #161A Non Clean Bench and #161B Clean Bench. This temporary occupancy will not include any portions of Building #24E with the exception of the first floor areas #100CH Corridor, #100CI Corridor, #101CE Hazards, #101CF TGM and #101CG Pyrophoric. See the attached conditions sheet for a more comprehensive list of rooms and areas to be EXCLUDED from the temporary occupancy request. JCM 10/15/01
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/11/20023/11/20023/11/2002PPASS
DetailsJim Storey
Added by Inspector: 301 On 3/11/2002 3:04:52 PM final ok
Permanent Occupancy 3/11/20023/11/2002 DONE
Details
BLD-Conference3/5/20023/6/20023/6/2002APART
DetailsJim Storey
walk through list of c/n idems and sign offs required. 3/6/2002 2:48:22 PM
FIRE-Final Inspection2/20/20022/20/20022/20/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 2/20/2002 4:18:37 PM
BLD-Conference1/3/20021/4/20021/4/2002APART
DetailsJim Storey
###-#### e 1st fl. restarooms,lockerrm/synthesis rm and clean bench ok for temp occ. 1/7/2002 9:36:10 AM
BLD-Conference12/17/200112/18/200112/18/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/17/2001 at 13:37:22. Contact: ###-####. basement ok fire stop at grade level west ele penatations. 12/19/2001 11:33:52 AM
BLD-Final11/10/200111/10/200111/10/2001APART
DetailsJim Storey
Scheduled by Inspector: 301 On 11/10/2001 8:33:22 AM temp occ. ok for area of modified scope of work on file. must maintain egress coridors for opening protection and width for egress. per agreement for occ.on file with city with plan review. 11/10/2001 10:19:51 AM
FIRE-Final Inspection11/13/200111/10/200111/10/2001APART
DetailsRick Jackson
Added by Inspector: 409 On 11/13/2001 7:15:11 AM okay to occupy bldg 24D only; Micron to finsish work in gas bunker
BLD-Wall cover11/7/200111/7/200111/7/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/07/2001 at 07:21:35. Contact: ###-####. wip 11/8/2001 3:59:14 PM
BLD-Framing/Rough-in11/5/200111/6/200111/6/2001PPASS
DetailsJim Storey
###-#### HUGO ARCHITECTURAL FIRE fire stopping ok at 2 hr and 4 hr process piping penatrations. 11/8/2001 3:56:52 PM
BLD-Conference11/2/200111/5/200111/5/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/02/2001 at 09:53:47. Contact: ###-####. wip. 11/6/2001 12:52:02 PM
FIRE-Conference11/5/200111/5/200111/5/2001APART
DetailsRick Jackson
Added by Inspector: 409 On 11/5/2001 10:39:52 AM checked operation of blast doors at bunker; all shipping screws removed and tested the operation - all okay
FIRE-Conference11/2/200111/2/200111/2/2001ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/02/2001 at 06:21:50. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/02/2001 at 06:23:53.
FIRE-Conference11/2/200111/2/200111/2/2001ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/02/2001 at 06:29:58. Contact: ###-####. talked to hugo and he said to disregard this request 11/2/2001 10:00:35 AM
FIRE-Final Inspection11/1/200111/2/200111/2/2001ACANC
DetailsRick Jackson
###-#### HUGO wrong type of inspection called in 11/2/2001 10:00:09 AM
BLD-Conference10/31/200111/1/200111/1/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/31/2001 at 14:38:52. Contact: ###-####. 4hr wall penetration needs 1/4 strip past sheetrock. 11/2/2001 8:22:26 AM
BLD-Final11/1/200111/1/200111/1/2001PPART
DetailsRuss Owen
###-#### hugo. 4hr wall missing collar at west side . location basement. 11/2/2001 11:02:13 AM
BLD-Wall cover10/30/200110/30/200110/30/2001ANR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/30/2001 at 05:53:31. Contact: ###-####. Above restroom 3 pipes req fire stoping will verify by access above retroom ceiling pipes approx 5 from access hatch. 10/30/2001 11:05:20 AM
BLD-Wall cover10/29/200110/29/200110/29/2001APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 10/29/2001 10:51:17 AM . Ok to place ceiling tile at main floor only. 10/29/2001 10:54:16 AM
BLD-Wall cover10/26/200110/26/200110/26/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/26/2001 at 06:32:16. Contact: ###-####.. Will recall. 10/26/2001 1:49:32 PM
FIRE-Conference10/25/200110/25/200110/25/2001PPART
DetailsRick Jackson
FIRE STOPS PENATRATION HUGO ###-#### okay to proceed with cover; insulation installed 10/25/2001 4:10:28 PM
FIRE-Conference10/24/200110/24/200110/24/2001PPART
DetailsJim Storey
fire penatration wall hazzards bunk walk hugo ###-#### 1/2 of assemblie ok to proceed with closer. 10/24/2001 2:42:40 PM
BLD-Conference10/23/200110/23/200110/23/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/23/2001 at 07:15:14. Contact: ###-####. c/n posted. 10/23/2001 5:00:52 PM
BLD-Other10/23/200110/23/200110/23/2001APART
DetailsJim Storey
Added by Inspector: 301 On 10/23/2001 11:58:52 AM chem tray fire stopping assemblies at fab/ basement chem distrution rooms ok./ pending 4 hr north / fab west stainless steel at cat walk assemblie ok to continue.
BLD-Wall cover10/23/200110/23/200110/23/2001PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/23/2001 at 11:02:16. Contact: ###-####.
BLD-Conference10/16/200110/17/200110/17/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/16/2001 at 09:38:20. Contact: ###-####. stair inclosers to have all other idems incapsulated from this inviroment. 10/17/2001 3:18:13 PM
BLD-Conference10/9/200110/9/200110/9/2001PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/09/2001 at 07:39:40. Contact: ###-####. c/n posted. 10/10/2001 3:38:11 PM
BLD-Wall cover10/5/200110/5/200110/5/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/05/2001 at 08:51:26. Contact: ###-####. east hpm corridor ok for ceilling 4 hr north to drum unload rm. 10/5/2001 4:26:57 PM
BLD-Framing/Rough-in10/3/200110/3/200110/3/2001PPART
DetailsJim Storey
tony ###-#### r/i conf to review fire stopping assemblies and insp. 10/4/2001 3:56:03 PM
BLD-Wall cover10/2/200110/2/200110/2/2001PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/02/2001 at 06:09:10. Contact: ###-####. dock stair well to fan deck need horrizontal bar welded before cover. 10/2/2001 3:00:18 PM
BLD-Wall cover9/26/20019/27/20019/27/2001ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/26/2001 at 07:21:02. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/27/2001 at 05:07:57.
BLD-Wall cover9/27/20019/27/20019/27/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/27/2001 at 05:06:22. Contact: ###-####. basement ceilling/ south fur out wall north side. 9/27/2001 6:27:05 PM
BLD-Framing/Rough-in9/24/20019/25/20019/25/2001APART
DetailsJim Storey
r/i- xenon-- ###-#### reviewed fire stopping of areas to be done by YMC work to begin soon. 9/25/2001 4:50:28 PM
BLD-Wall cover9/21/20019/24/20019/24/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/21/2001 at 14:43:02. Contact: ###-####. occ wall at sub-fab into ele room openings not protected/ h3 drum unload floor openings unprotcted. 9/24/2001 4:09:16 PM
BLD-Wall cover9/14/20019/17/20019/17/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/14/2001 at 12:43:19. Contact: ###-####. ceilling at gas bunker corridor ok to start./ tenp power fan deck and di water 4 hr wall hold those areas as well as floor safe assemblie/west wall ok for cover fab level/south 4 hr patch in ok for cover above gas rm corridor south side. 9/17/2001 1:03:37 PM
BLD-Wall cover9/13/20019/13/20019/13/2001ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/13/2001 at 07:11:30. Contact: ###-####.
BLD-Wall cover9/11/20019/12/20019/12/2001PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/11/2001 at 13:56:44. Contact: ###-####.
BLD-Wall cover9/7/20019/7/20019/7/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/07/2001 at 06:12:25. Contact: ###-####. done prevously 9/7/2001 1:52:47 PM
BLD-Wall cover9/6/20019/6/20019/6/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/06/2001 at 09:12:32. Contact: ###-####. 2 hr grade chem rm north. 9/7/2001 1:52:15 PM
BLD-Wall cover9/5/20019/5/20019/5/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/05/2001 at 06:46:29. Contact: ###-####. c/n 9/5/2001 12:55:18 PM Scheduled by a c/ncontractor via Hello! on 09/05/2001 at 06:46:29. Contact: ###-####. c/n 9/5/2001 12:55:18 PM 9/5/2001 3:11:00 PM
BLD-Conference8/28/20018/28/20018/28/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/28/2001 at 06:17:16. Contact: ###-####. working on fire door listing. 8/28/2001 4:36:08 PM
BLD-Conference8/27/20018/27/20018/27/2001PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/27/2001 at 09:18:28. Contact: ###-####.
BLD-Wall cover8/16/20018/17/20018/17/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/16/2001 at 08:51:14. Contact: ###-####. c/n posted on site/ damper in basement ok at 2 hr chem rm wall configuation resolved ok for cover. 8/17/2001 12:30:42 PM
BLD-Wall cover8/16/20018/16/20018/16/2001PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/16/2001 at 08:47:40. Contact: ###-####.
BLD-Wall cover8/15/20018/15/20018/15/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/15/2001 at 06:21:34. Contact: ###-####. 2 hr wall at 36 cafateria to fab tube steel incapsulated c/n this idem ok/ basement fire collors at chem room 2-2'' emt instalation ok c/n idem ok. 8/15/2001 11:45:32 AM
BLD-Wall cover8/10/20018/10/20018/10/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/10/2001 at 05:35:11. Contact: ###-####. pipe penatrations basement not per listing8/10/2001 4:55:44 PM 8/10/2001 4:55:58 PM
BLD-Wall cover8/8/20018/8/20018/8/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/08/2001 at 07:52:42. Contact: ###-####. basement chem rooms firestopping ok pending engineered judgments for 2 locations/ 8/9/2001 10:49:19 AM
BLD-Conference8/7/20018/7/20018/7/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/07/2001 at 06:37:37. Contact: ###-####. approved detail for corridor 100 door frame to enped into wall with gyp return and fire chalking perimitor. 8/7/2001 9:57:02 AM
BLD-Conference8/2/20018/2/20018/2/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/02/2001 at 09:06:39. Contact: ###-####. conf. 8/3/2001 10:08:38 AM
BLD-Wall cover7/31/20018/1/20018/1/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/31/2001 at 15:03:28. Contact: ###-####. basement exsust duct wrap ok. 8/1/2001 11:15:21 AM
BLD-Wall cover7/26/20017/30/20017/30/2001PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/26/2001 at 07:40:54. Contact: ###-####. fire stopping cof. 7/30/2001 4:34:28 PM
BLD-Wall cover7/27/20017/27/20017/27/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/27/2001 at 05:48:34. Contact: ###-####. sub fab interior wall ok for cover wip 7/27/2001 12:39:00 PM
BLD-Conference7/16/20017/16/20017/16/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/16/2001 at 06:08:46. Contact: ###-####.
BLD-Wall cover6/29/20017/2/20017/2/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/29/2001 at 14:42:04. Contact: ###-####. ele panels no envlelop at top at back/ colums need box rating / fire door need listing for fram. 7/6/2001 11:32:20 AM
BLD-Conference6/27/20016/28/20016/28/2001APASS
DetailsJim Storey
Chris ###-####
FIRE-Conference6/27/20016/27/20016/27/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/27/2001 at 08:10:54. Contact: ###-####. request made by mistake 6/27/2001 2:43:18 PM
BLD-Wall cover6/21/20016/21/20016/21/2001PFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/21/2001 at 07:54:19. Contact: ###-####. rm#101 2hr wall tpo track/fds/beam framing/cut back to maintane assembly. stair 10# fire stop emt an beams./ fan deck 2 inch pvc collor. 6/21/2001 5:16:52 PM
BLD-Wall cover5/15/20015/16/20015/16/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/15/2001 at 15:41:17. Contact: ###-####. 1/2 east wall of fab ok for cover/ 5/16/2001 10:46:44 AM
BLD-Wall cover5/14/20015/14/20015/14/2001ANR
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/14/2001 at 06:43:03. Contact: ###-####.
BLD-Wall cover5/7/20015/8/20015/8/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/07/2001 at 17:17:02. Contact: ###-####.
BLD-Wall cover5/7/20015/7/20015/7/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/07/2001 at 10:07:51. Contact: ###-####.
BLD-Wall cover4/26/20014/27/20014/27/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/26/2001 at 12:30:38. Contact: ###-####. 4 hr wall ok to procced/ coridor ok at south fan deck. 4/27/2001 1:26:26 PM
BLD-Wall cover4/16/20014/16/20014/16/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/16/2001 at 07:33:10. Contact: ###-####. chem rm in basement duct s/f still not installed corectly/ fan deck coridor ok all but room to tunel hold this area until fixed. 4/16/2001 6:29:59 PM
BLD-Wall cover3/27/20013/28/20013/28/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/27/2001 at 14:01:40. Contact: ###-####. fab and north 4 hr ok. 3/28/2001 9:11:50 AM
BLD-Wall cover3/19/20013/19/20013/19/2001ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/19/2001 at 07:19:33. Contact: ###-####.
BLD-Wall cover3/16/20013/16/20013/16/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/16/2001 at 06:28:44. Contact: ###-####.
BLD-Wall cover3/13/20013/13/20013/13/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/13/2001 at 05:48:00. Contact: ###-####. c/n pending. 3/13/2001 12:54:35 PM
BLD-Wall cover3/6/20013/7/20013/7/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/06/2001 at 14:48:44. Contact: ###-####. sub faB CORRIDORS C1 AND WEST WALL OK FOR COVER.C/N FOR DETAIL OF PIPI RACKING AT ROOF FAN DECK HANGER SPACING/ LATERAL BAR SPACING AND ATCHMENT OVER HEIGHT STUDS. 3/7/2001 5:33:46 PM
BLD-Wall cover2/20/20012/21/20012/21/2001ANR
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/20/2001 at 17:23:06. Contact: ###-####.
BLD-Framing/Rough-in2/16/20012/20/20012/20/2001ANR
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/16/2001 at 10:27:32. Contact: ###-####.
BLD-Framing/Rough-in2/12/20012/12/20012/12/2001PPART
DetailsJim Storey
Added by Inspector: 301 On 2/12/2001 1:06:26 PM c2/27 stair beam must maintane 6ft 8 in. headroom will require engineering and resubmital for design.previous c/n idems ok pending 1. deflection of fab wall at beam for intagraty of assembly.
BLD-Framing/Rough-in2/12/20012/12/20012/12/2001PPASS
DetailsJim Storey
Added by Inspector: 301 On 2/12/2001 1:13:09 PM basement ok ro cover of walls rm# 001k,1l,1m,1n,0h,oc
BLD-Wall cover2/9/20012/9/20012/9/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/09/2001 at 05:46:22. Contact: ###-####. ceilling ok will check on final fo primetor wires/ tennet walls need protection. 2/9/2001 3:26:12 PM
BLD-Framing/Rough-in2/5/20012/5/20012/5/2001PFAIL
DetailsJim Storey
Added by Inspector: 301 On 2/5/2001 10:20:35 PM c/n isued 1# 307.1.4 h-3 area over 150 sq/ft required to have min 2 hr wall. aproved plan has a 1 hr wall designation a3.6/e&k27a refrance to floor plan 2.0.3 at grid lines a9 - c8 and 27 - 30.
2# doors in these walls requied to be 1 1/2 hr rated.
3# chemical exsust duct passing from one h-3 occ to h-6 occ and into another h-3 occ rm. will need to be protected to meet ubc 1202.2.5 2hr protection.
4# walls 28/c2,c8 and 29/c2.c8 struc. I beam restricks 2hr wall configration for gyp. attchament provide wall and listing design.
5# bottom fo beams on grid line c2 and c8 missing 1 layer of gyp. protection.
6#I beams perpendickular to 2hr and 1 hr walls requier wall stud framing into web for screw sch. of listing for gyp. atchment.
7# bottom track pin to slab and track to gyp. must be per plan and gyp. assemblie listing.
8#fab ground level walls at grid line c2 and 29 must have detail submitted for collums incapsaluated with in the 1hr corridor assemblie this is a full height wall struc. frame conections and deflection for height to be addressed.
9# ele. boxes less than 24 inches must be procted two locations 2hr walls basement.
10# all trades must submit fire stopping listings to address there idems for insp.
11#fab wall must have horrisontal bar for steel stud framing height of wall.
BLD-Framing/Rough-in2/5/20012/5/20012/5/2001PPASS
DetailsJim Storey
Added by Inspector: 301 On 2/5/2001 9:45:21 PM recieved resubmital for top of the wall head-joint to replace the approved plan detail and listing on 3.6 / 3.6.1 . listed ul/cul no.hw-d-0077system #. this listing is april 21, 2000 and meets the new std. for fire stopping as a class II movement capabilies = 17% comp or extention. submital approved and archived to documents with city plan.