FIRE-Final Inspection | 12/27/2001 | 12/28/2001 | 12/28/2001 | A | PASS |
Troy Cobbley
|
|
|
fire fn -- ###-####- kent fire finaled 12/28/2001 8:37:45 AM
|
Permanent Occupancy | | 12/28/2001 | 12/28/2001 | | DONE |
|
|
|
|
BLD-Final | 12/21/2001 | 12/26/2001 | 12/26/2001 | A | PART |
Tony Young
|
|
|
###-####
ok for final after other trade inspectors are ok 12/26/2001 10:56:21 AM
|
BLD-Aging Inspection | 10/24/2001 | 10/24/2001 | 10/24/2001 | | PART |
Tony Young
|
|
|
wip 10/24/2001 2:30:20 PM
|
BLD-Conference | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | CANC |
Tony Young
|
|
|
|
BLD-Other | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/23/2001 at 07:59:32. Contact: ###-####.final,, ok for temp. occ. 8/24/2001 8:23:27 AM
|
FIRE-Final Inspection | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Joe Tawney
|
|
|
Reinsp OK for temporary occupancy Temp FDC and access road. 2landings at rear of bldg. Fax of alarm signals 8/23/2001 4:45:30 PM
|
BLD-Final | 8/21/2001 | 8/22/2001 | 8/22/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/21/2001 at 17:20:40. Contact: ###-####.still need fire sign off, conf. on rest of final 8/22/2001 12:15:49 PM
|
FIRE-Final Inspection | 8/22/2001 | 8/22/2001 | 8/22/2001 | A | FAIL |
Joe Tawney
|
|
|
###-#### Reinsp Fail all issues not resolved 8/22/2001 12:20:40 PM
|
BLD-Final | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/21/2001 at 09:34:06. Contact: ###-####.
need trades signed off, misc. other items 8/21/2001 3:49:52 PM
|
FIRE-Final Inspection | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | NR |
Joe Tawney
|
|
|
Reinsp not ready all issues not resolved 8/21/2001 3:45:00 PM
|
BLD-Conference | 8/19/2001 | 8/20/2001 | 8/20/2001 | A | PASS |
Carl Dependahl
|
|
|
meet w/ Tony please 8/19/2001 11:09:33 PM keep c/n, no occupancy til reinsp ok'd by fire 8/20/2001 9:53:00 AM
|
BLD-Other | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 17:59:49. Contact: ###-####. met w/ Joe Tawney to go over job,
I had to leave to go to other jobs 8/20/2001 11:44:54 AM
|
FIRE-Final Inspection | 8/19/2001 | 8/20/2001 | 8/20/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail Multiple items 8/20/2001 11:54:23 AM
|
BLD-Conference | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/17/2001 5:30:58 PM final walk-thru w/ Tony & Petra...c/n issued re exits, fire & other insps not complete, storage below stairs, etc. Partial insp only (to identify life-safety issues.) Phase 1 of project.
|
BLD-Final | 8/16/2001 | 8/17/2001 | 8/17/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/16/2001 at 16:23:24. Contact: ###-####.kent 8/17/2001 2:11:12 PM
met w/ 340, c/n posted , DO NOT OCCUPY 8/17/2001 5:03:19 PM
|
BLD-Framing/Rough-in | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Tony Young
|
|
|
lower south 6/28/2001 9:41:23 AMok to cover lower south 6/29/2001 3:16:23 PM
|
BLD-Framing/Rough-in | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/27/2001 at 11:05:18. Contact: ###-####.
c/n on fire blocks in stud cavitys w/ combustion, ok to cover lower south area small rooms only 6/28/2001 9:40:15 AM
|
BLD-Framing/Rough-in | 6/1/2001 | 6/11/2001 | 6/11/2001 | A | CANC |
Dave Hannah
|
|
|
6/1/2001 3:28:02 PM
|
BLD-Framing/Rough-in | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/04/2001 at 15:01:52. Contact: ###-####. WIP 6/5/2001 10:59:56 AM
|
BLD-Framing/Rough-in | 5/31/2001 | 6/1/2001 | 6/1/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/31/2001 at 12:11:57. Contact: ###-####.some int. ok, pending elec. on other 6/1/2001 3:28:41 PM
|
BLD-Framing/Rough-in | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/18/2001 at 14:18:57. Contact: ###-####.
c/n posted, ok after trade sign offs to cover 2nd floor, int. walls 5/21/2001 11:00:58 AM
|
BLD-Concrete | 3/20/2001 | 3/20/2001 | 3/20/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 07:28:15. Contact: ###-####.
masonary, pending S.I. report 3/20/2001 1:05:50 PM
|
BLD-Concrete | 3/14/2001 | 3/15/2001 | 3/15/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/14/2001 at 17:02:26. Contact: ###-####.
pending S.I. report 3/15/2001 9:45:09 AM
|
BLD-Concrete | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/13/2001 at 15:59:50. Contact: ###-####.
pending S.I. report 3/14/2001 10:03:26 AM
|
BLD-Concrete | 3/12/2001 | 3/13/2001 | 3/13/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 08:40:10. Contact: ###-####.
pending S. I. report 3/13/2001 1:40:59 PM
|
BLD-Concrete | 3/8/2001 | 3/9/2001 | 3/9/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 16:11:30. Contact: ###-####.
|
BLD-Concrete | 3/7/2001 | 3/8/2001 | 3/8/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 14:58:03. Contact: ###-####.
pending special inspector report 3/8/2001 10:26:48 AM
|
BLD-Concrete | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/05/2001 at 14:33:41. Contact: ###-####.
masonary, bond beams, plates, wip, ok pending special inspector report 3/6/2001 9:42:36 AM
|
BLD-Concrete | 3/1/2001 | 3/2/2001 | 3/2/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/01/2001 at 20:05:37. Contact: ###-####. masonry, spec. insp onsite...wip. Met w/ new supt. 3/2/2001 9:11:17 AM
|
BLD-Concrete | 2/28/2001 | 3/1/2001 | 3/1/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/28/2001 at 16:17:32. Contact: ###-####.
pending mti report 3/1/2001 9:58:46 AM
|
BLD-Concrete | 2/26/2001 | 2/27/2001 | 2/27/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/26/2001 at 16:01:23. Contact: ###-####.
masonary, pending mti report 2/27/2001 9:44:27 AM
|
BLD-Concrete | 2/23/2001 | 2/26/2001 | 2/26/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/23/2001 at 16:25:16. Contact: ###-####.
bond beam wip, pending special insp. report 2/26/2001 9:30:32 AM
|
FIRE-Hydro test above ground | 2/22/2001 | 2/23/2001 | 2/23/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel should be structural insp 2/26/2001 8:07:40 AM
|
BLD-Foundation | 2/15/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/15/2001 at 17:19:48. Contact: ###-####.
wip, pending special rpt. 2/21/2001 8:35:33 AM
|
BLD-Footing | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/15/2001 at 09:04:46. Contact: ###-####.
met w/ kent, new job super, wip ok pending special insp. report, also t/w s. inspector 2/15/2001 3:50:18 PM
|
BLD-Footing | 2/6/2001 | 2/7/2001 | 2/7/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/06/2001 at 12:19:06. Contact: ###-####.
east wall and more int. ftgs., wip, still waiting for survey , pending special inspection report 2/7/2001 11:36:38 AM
|
BLD-Footing | 2/5/2001 | 2/6/2001 | 2/6/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/05/2001 at 09:47:44. Contact: ###-####.
special on site, Gary w/ mti// wip, verbal corrections to be taken care of b-4 pour, south and west wall and interior pads pending report from special 2/6/2001 9:47:01 AM
|
BLD-Footing | 1/31/2001 | 2/1/2001 | 2/1/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/31/2001 at 09:43:29. Contact: ###-####. met w/ supt. onsite; need suvey report, all spec. insp's called to city et 2/1/2001 10:11:07 AM c. 2/1/2001 10:11:13 AM
|
BLD-Footing | 1/29/2001 | 1/30/2001 | 1/30/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 14:43:13. Contact: ###-####. mti report pending...need surveyors statement for p.l. 1/30/2001 9:43:43 AM
|