Permit Information
Permit NumberBLD00-03428
StatusFinaled
Name NEW TERMINAL BUILDING
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT-NEW TERMINAL
Customer Number 
ePlanReviewNo
Description
BOISE AIRPORT PASSENGER TERMINAL BUILDING - TO CONSTRUCT A NEW 321,450 SQ. FT. (INCLUDING MODIFICATION CCD-008 & PR-082.1 & PR082.2), THREE STORY WITH 45,000 SQ. FT. BASEMENT AIRPORT PASSENGER TERMINAL BUILDING AND RELATED SITE IMPROVEMENTS. THE NEW TERMINAL BUILDING WILL BE CONSTRUCTED OF CONCRETE AND STEEL STRUCTURAL FRAME; IT WILL BE FULLY FIRE SPRINKLERED. THIS TERMINAL BUILDING IS BEING CONSTRUCTED TO REPLACE THE EXISTING TERMINAL BUILDING. THE PROJECT WILL BE CONSTRUCTED IN PHASES. SCHEDULE I WILL BE CONSTRUCTED OUTSIDE OF THE EXISTING TERMINAL FOOTPRINT AND WILL INCLUDE THE BASEMENT SUPPORT AREAS, FIRST FLOOR BAGGAGE CLAIM/MAKE-UP, SECOND FLOOR TICKETING, ATO AND LEASE AREAS AND THE THIRD FLOOR ADMINISTRATIVE AND LEASE AREAS. SCHEDULE II WILL INCLUDE DEMOLITION OF THE WEST END OF THE EXISTING TERMINAL BUILDING AND THE CONSTRUCTION OF THE FIRST FLOOR RENTAL CAR LOBBY AND GROUND LOAD LOBBY AND SECOND FLOOR SECURITY CHECKPOINT, FOOD COURT AREAS AND PASSANGER LINK TO EXISTING CONCOURSE 'B'. SCHEDULE I ALSO INCLUDES CONSTRUCTION OF TEMORARY ELEVATED WALKWAYS AND SECURITY CHECKPOINTS CONSTRUCTED OVER THE EXISTING TERMINAL BUILDING, TO CONNECT THE COMPLETED AND OPERATING SCHEDULE I BUILDING WITH THE EXISTING CONCOURSES. AFTER COMPLETION OF SCHEDULE II, THE REMAINDER OF THE EXISTING TERMINAL BUILDING, THE TEMPORARY ELEVATED WALKWAYS AND CONCOURSE 'A' WILL BE DEMOLISHED AND REMOVED. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. DRH99-00206/CUP99-0130/PC#970-00/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/23/200412/23/200412/23/2004PPASS
DetailsJim Storey
final ok 12/23/2004 4:44:57 PM
Permanent Occupancy 12/23/200412/23/2004 DONE
Details
FIRE-Final Inspection11/8/200411/8/200411/8/2004PPASS
DetailsRick Jackson
Calvin; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner Exit signs in tunnel are okay as is; hydrant by job trailer to remain inside fence as the fence is being relocated back from retaining wall 11/8/2004 3:12:55 PM
BLD-Final9/16/20049/17/20049/17/2004APART
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore temp ok pending resolve of restarooms to meet a117 ada/and others based on phasing. 9/17/2004 4:26:21 PM
BLD-Final9/16/20049/17/20049/17/2004ACANC
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
FIRE-Final Inspection9/17/20049/17/20049/17/2004PPART
DetailsRick Jackson
Phased project - Area D okay to occupy 9/17/2004 3:23:51 PM
BLD-Final9/15/20049/16/20049/16/2004ANR
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ada restarooms pending/ 3rd floor mech damper lables/screws/fire proofing. 9/16/2004 11:04:05 AM
FIRE-Final Inspection9/14/20049/14/20049/14/2004PFAIL
DetailsRick Jackson
calvin--exit signs; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Test overhead door release; install exit signs as shown on plans; complete sprinkler tie-in to concourse B and complete hydro test on second floor; remove tape and add escutcheons on all sprinklers; complete rated doors with seals and closures; NFPA 72 record of completion for alarms; provide certificates for sprinkler system and add calc stickers on risers; install signs for auxiliary drains and control valves; certify fire extinguishers 9/14/2004 3:45:36 PM
BLD-Framing/Rough-in9/13/20049/13/20049/13/2004PPASS
DetailsJim Storey
ceiling grid- call 1st before insp calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in9/10/20049/10/20049/10/2004PPASS
DetailsJim Storey
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie fire proofing patch. 9/10/2004 4:01:45 PM
BLD-Final9/3/20049/3/20049/3/2004APART
DetailsJim Storey
area c rental car area for temp occ. temp ok for area c. 9/3/2004 9:50:16 AM
BLD-Final8/30/20049/2/20049/2/2004PPASS
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Annette Moore area c rental car area alarms and 2 areas complet per c/n. 9/3/2004 1:12:27 AM
FIRE-Final Inspection9/1/20049/2/20049/2/2004PPART
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Inspection from 11:00 pm - 2 am to test fire alarms; Area C first floor forcar rental area okay to occupy 9/3/2004 9:08:01 AM
BLD-Framing/Rough-in8/31/20049/1/20049/1/2004PPASS
DetailsJim Storey
calvin - Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Conference8/25/20048/26/20048/26/2004PPART
DetailsRick Jackson
1:30 at Layton trailer Met with Al and Bill about testing the fire alarms for this phase - I agreed to test after hours pending a request to Sam Rogers for approval; reviewed the exiting for this phase and there may be a problem with concourse A and one exit - Bill will check into it and to also let Jim S. know about the problem 8/26/2004 3:58:41 PM
FIRE-Sprinkler Rough-in8/17/20048/23/20048/23/2004AFAIL
DetailsRick Jackson
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Not a sprinkler rough-in but to test smoke/fire damper operation - damper at device M4-8 not working and need tot est damper at south end in office area on first floor 8/23/2004 12:36:32 PM
BLD-Framing/Rough-in8/17/20048/18/20048/18/2004APART
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles after 10:00
BLD-Framing/Rough-in8/16/20048/17/20048/17/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles after 10:00 out of time rolled over. 8/17/2004 4:18:46 PM
BLD-Framing/Rough-in8/13/20048/16/20048/16/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles rolled over to am 8/16/2004 3:16:48 PM
BLD-Framing/Rough-in8/4/20048/4/20048/4/2004PPART
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ceilling grid ok 1 st floor/glazing sg 4 locations 1st floor. 8/4/2004 4:46:03 PM
BLD-Other7/19/20047/20/20047/20/2004APASS
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ceilling in car rental area ok pending fd and ele approval. 7/20/2004 9:46:55 AM
BLD-Framing/Rough-in7/15/20047/19/20047/19/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in6/30/20047/1/20047/1/2004APASS
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes fire proofing repaired handrailling reviewed for compliance in west stair well. 7/1/2004 9:13:38 AM
FIRE-Sprinkler Rough-in7/1/20047/1/20047/1/2004PPART
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Will need additional EQ's at expansion joint and at 4 inch line to walkway to concourse 7/2/2004 10:18:15 AM
BLD-Framing/Rough-in6/29/20046/30/20046/30/2004APART
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes damper at car rental stair/ blow patch/fire stop/exalator 2 beam patches fp. 6/30/2004 9:27:04 AM
BLD-Framing/Rough-in6/21/20046/22/20046/22/2004PPASS
DetailsJim Storey
calvin - ceiling grid inspection please!; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles over escalator 2nd floor ok.fire proofing ok for c/n posted by si. 6/22/2004 3:20:35 PM
BLD-Framing/Rough-in6/17/20046/18/20046/18/2004PPASS
DetailsJim Storey
Randy; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes n & s soffits of walkway ok 6/18/2004 3:51:33 PM
BLD-Framing/Rough-in6/4/20046/7/20046/7/2004APASS
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes east walls floor fire saffing 2 and 3 rd floors complet only west and coridor left. 6/7/2004 9:17:35 AM
BLD-Framing/Rough-in6/4/20046/4/20046/4/2004PCANC
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes out of time 6/4/2004 4:23:29 PM
BLD-Wall cover6/2/20046/2/20046/2/2004PPART
DetailsJim Storey
curtin wall ok all but east wall at dog leg to rotunda. 6/2/2004 4:26:03 PM
FIRE-Final Inspection6/1/20046/2/20046/2/2004PCANC
DetailsRick Jackson
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Wrong inspection called in - needed structural inspector for wall cover 6/2/2004 12:26:11 PM
BLD-Other5/28/20045/28/20045/28/2004PFAIL
DetailsJim Storey
Jeff Peterson, ###-#### - call 1st cutrin wall fire stop missing at 4 locations/ele need fire stop. 5/28/2004 3:33:15 PM
FIRE-Final Inspection5/25/20045/26/20045/26/2004ACANC
DetailsRick Jackson
Jeff; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Wrong type inspection called in - needed structural inspection 5/28/2004 8:31:18 AM
BLD-Framing/Rough-in5/17/20045/17/20045/17/2004PPASS
DetailsJim Storey
Cal; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes offices at rental area lowest level ok for cover. 5/17/2004 1:14:21 PM
BLD-Framing/Rough-in5/6/20045/10/20045/10/2004APART
DetailsJim Storey
###-#### calvin 2 hr septration at walkway at concorse b must be complet thru soffit areas . 5/10/2004 10:13:33 AM
BLD-Framing/Rough-in5/10/20045/10/20045/10/2004PPASS
DetailsJim Storey
floor curtin wall firesafing.ok for cover at corridor west side of 2nd floor. 5/10/2004 3:45:03 PM
BLD-Framing/Rough-in5/6/20045/6/20045/6/2004PPART
DetailsJim Storey
###-#### CALVIN remove vizqueen at sky lights/ fire proofing patch required throughout. 5/6/2004 3:46:01 PM
FIRE-Sprinkler Rough-in4/16/20044/19/20044/19/2004PPART
DetailsRick Jackson
calvin ###-#### See sprinkler FIR for info 4/19/2004 4:07:00 PM
BLD-Framing/Rough-in4/7/20044/12/20044/12/2004APASS
DetailsJim Storey
###-#### calvin wip ok 4/12/2004 9:40:49 AM
BLD-Framing/Rough-in4/6/20044/8/20044/8/2004ACANC
DetailsJim Storey
###-#### calvin rolled over to monday. 4/7/2004 5:40:46 PM
BLD-Framing/Rough-in3/9/20043/10/20043/10/2004APASS
DetailsJim Storey
CALVIN ###-#### conf with calvin ok 3/10/2004 9:19:43 AM
BLD-Framing/Rough-in3/4/20043/5/20043/5/2004APART
DetailsJim Storey
calvin ###-#### walk thru progess ok fire proofing in progess/ noted defence talk with special insp. and contractor for follow up / review of rated walls for opening protection at bagage claim rfi to arch. through contractor. 3/5/2004 11:39:38 AM
BLD-Foundation1/20/20041/23/20041/23/2004APART
DetailsJim Storey
randy ###-#### pwsi 1/23/2004 2:38:49 PM
BLD-Foundation1/20/20041/22/20041/22/2004APART
DetailsJim Storey
randy ###-#### pwsi 1/22/2004 3:26:43 PM
BLD-Foundation1/20/20041/21/20041/21/2004APART
DetailsJim Storey
randy ###-#### 1/21/2004 8:06:28 AM placed with special inspection. 1/21/2004 8:07:20 AM
BLD-Framing/Rough-in1/20/20041/20/20041/20/2004PPART
DetailsJim Storey
###-#### CALIVIN framing ok for north sky light/ mech space exterior hold at colum and beam fire proofing patches to be verified latter. 1/20/2004 1:34:27 PM
BLD-Framing/Rough-in1/5/20041/9/20041/9/2004PPART
DetailsJim Storey
BLD-Concrete1/8/20041/8/20041/8/2004PPART
DetailsJim Storey
wip 2nd floor deck pour/ roof framing inprogess. 1/8/2004 3:54:56 PM
BLD-Framing/Rough-in1/5/20041/8/20041/8/2004PCANC
DetailsJim Storey
cloned 1/8/2004 3:54:03 PM
BLD-Concrete1/7/20041/7/20041/7/2004PPART
DetailsJim Storey
2nd floor deck floor/tunnel lid 1/7/2004 4:11:58 PM
BLD-Framing/Rough-in1/5/20041/7/20041/7/2004PNR
DetailsJim Storey
cloned 1/7/2004 4:10:11 PM
BLD-Framing/Rough-in1/5/20041/6/20041/6/2004PNR
DetailsJim Storey
wip 1/6/2004 4:11:35 PM
BLD-Framing/Rough-in1/5/20041/5/20041/5/2004PPART
DetailsJim Storey
###-#### randy floor 2nd concrete placement. 1/5/2004 4:39:42 PM
BLD-Concrete12/4/200312/11/200312/11/2003APART
DetailsJim Storey
Randy ###-#### wip 12/11/2003 1:54:13 PM
BLD-Concrete12/4/200312/10/200312/10/2003APART
DetailsJim Storey
Randy ###-#### 2 nd floor deck pour j line ok pending density reports. 12/10/2003 9:18:34 AM
BLD-Concrete12/4/200312/9/200312/9/2003APART
DetailsJim Storey
Randy ###-#### wip covered with special insp. 12/9/2003 4:25:05 PM
BLD-Concrete12/4/200312/8/200312/8/2003APART
DetailsJim Storey
###-#### Randy recieved special insp. reports for truck load of steel damaged in shipment engineers of fabracator and site as well as special insp. records justified to repair minor isues. repairs complet and all parties sign off for use with out replacement of major componants. archived into city for record. 12/8/2003 10:13:34 AM wip placed with si. 12/8/2003 10:15:37 AM
BLD-Conference12/8/200312/8/200312/8/2003APASS
DetailsJim Storey
###-#### Randy recieved special insp. reports for truck load of steel damaged in shipment engineers of fabracator and site as well as special insp. records justified to repair minor isues. repairs complet and all parties sign off for use with out replacement of major componants. archived into city for record. 12/8/2003 10:13:34 AM
BLD-Conference12/8/200312/8/200312/8/2003APASS
DetailsJim Storey
responce to non-compliance report 400-599/b30418c/rpt081.doc ok under ubc table 7b # 6 cmu protection. to negate adheation testing. 12/10/2003 9:19:33 AM
BLD-Concrete12/4/200312/5/200312/5/2003APART
DetailsTom Arcoraci
###-#### randy spec on site mti 12/5/2003 8:19:39 AM 12/5/2003 8:21:08 AM
BLD-Footing11/21/200311/28/200311/28/2003PPART
DetailsJim Storey
###-#### Randy wip 12/1/2003 1:42:59 PM
BLD-Foundation11/21/200311/28/200311/28/2003PPART
DetailsJim Storey
###-#### Randy wip 12/1/2003 1:43:07 PM
BLD-Footing11/21/200311/26/200311/26/2003PPART
DetailsJim Storey
###-#### Randy
BLD-Foundation11/21/200311/26/200311/26/2003PPART
DetailsJim Storey
###-#### Randy
BLD-Footing11/21/200311/25/200311/25/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/25/2003 4:20:08 PM
BLD-Foundation11/21/200311/25/200311/25/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/25/2003 4:20:24 PM
BLD-Conference11/21/200311/24/200311/24/2003APASS
DetailsJim Storey
###-#### Randy meet with calvin over colm. protection.
BLD-Footing11/21/200311/24/200311/24/2003PPART
DetailsJim Storey
###-#### randy cwsi 11/24/2003 2:21:25 PM
BLD-Foundation11/21/200311/24/200311/24/2003PPART
DetailsJim Storey
###-#### Randy cwsi 11/24/2003 2:21:32 PM
BLD-Footing11/21/200311/21/200311/21/2003PPART
DetailsJim Storey
###-#### Randy pwsp 11/21/2003 5:05:28 PM
BLD-Foundation11/21/200311/21/200311/21/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/21/2003 5:05:49 PM
BLD-Framing/Rough-in11/20/200311/20/200311/20/2003PFAIL
DetailsJim Storey
field reports req from fabractor and struc. engineer of record for truck load of steel that fell off truck in transant as to acceptance for damage to meet building standards. truck load 190/
BLD-Footing10/13/200310/14/200310/14/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore rfi archived 00747 to justify bar lap and spacing on stair towersd and e ok. 10/14/2003 2:54:06 PM
BLD-Footing10/9/200310/9/200310/9/2003PPASS
DetailsJim Storey
RANDY; Phone #: ###-#### Internet Inspection Request from: Annette Moore massanary in progess/ west footing line progressing.special insp. on site and no descrepenes. 10/9/2003 2:06:35 PM
BLD-Footing10/8/200310/8/200310/8/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore placed with special insp. unable to insp. with work load. 10/8/2003 4:55:06 PM
BLD-Footing10/6/200310/6/200310/6/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore placed with special insp. 10/6/2003 4:29:15 PM
BLD-Footing10/2/200310/2/200310/2/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Foundation10/2/200310/2/200310/2/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Footing9/30/20039/30/20039/30/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/30/2003 at 7:55:58 AM. Contact: ###-####.placed with si. 9/30/2003 2:16:58 PM
BLD-Footing9/29/20039/29/20039/29/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Foundation9/29/20039/29/20039/29/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Footing9/23/20039/23/20039/23/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/23/2003 at 7:43:13 AM. Contact: ###-####. placed with special insp. pending report. 9/23/2003 3:59:27 PM
BLD-Foundation9/18/20039/18/20039/18/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Marc Lileks walls at previous ft location placed with special insp as well as elavator pit. 9/18/2003 2:55:39 PM
BLD-Footing9/16/20039/16/20039/16/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore west ft rebar ok 8 inches oc for massanary wall up to not including elavator pit ft. 9/16/2003 2:55:55 PM
BLD-Footing9/8/20039/8/20039/8/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/8/2003 at 9:25:30 AM. placed with special insp. 9/8/2003 3:10:26 PM
BLD-Footing9/2/20039/3/20039/3/2003APASS
DetailsJim Storey
RANDY; Phone #: ###-#### Internet Inspection Request from: Marc Lileks first pad ft. off rotunda south wip pending special insp. 9/3/2003 9:08:28 AM
BLD-Aging Inspection8/25/20038/25/20038/25/2003 PASS
DetailsJim Storey
wip 8/25/2003 10:03:57 AM
FIRE-Conference6/24/20036/25/20036/25/2003PPART
DetailsRick Jackson
###-#### calvin concourse A and B and the new terminal are now a networked fire alarm system; old terminal doesn't have alarms and the pump and sprinkler system will be left on until the building is ready for demo; outside bell isn't working on the old building 6/26/2003 2:24:29 PM
BLD-Conference6/24/20036/24/20036/24/2003PPASS
DetailsJim Storey
###-#### calvin
BLD-Conference6/16/20036/17/20036/17/2003PPASS
DetailsJim Storey
###-#### alvin 5:30pm 6/16/2003 3:50:34 PM walkways ok for temp occ. per phased aproved plan a and b access/ egress. 6/17/2003 6:47:28 PM
FIRE-Conference6/16/20036/17/20036/17/2003PPART
DetailsRick Jackson
###-#### alvin conducted alarm testing inspection from 5-7 pm; Linda Hartwell notified 6/18/2003 10:34:53 AM
BLD-Conference6/12/20036/13/20036/13/2003ACANC
DetailsJim Storey
###-#### alvin called and changed time to pm. 6/13/2003 10:45:56 AM
BLD-Final6/13/20036/13/20036/13/2003PPASS
DetailsJim Storey
ok for temp occ. of main termnal bldg. walk ways sch. for 6/17 to complet phase in of aproved plan. 6/13/2003 5:41:27 PM
BLD-Conference6/6/20036/12/20036/12/2003AFAIL
DetailsJim Storey
###-#### calvin ###-#### calvin it an surcerity membrane penatrations. 6/12/2003 1:18:48 PM
FIRE-Conference6/6/20036/12/20036/12/2003APART
DetailsRick Jackson
###-#### calvin main portion of new building on temp; using fire watch until all systems are monitored at new panel 6/13/2003 9:11:31 AM
BLD-Conference6/3/20036/5/20036/5/2003PFAIL
DetailsJim Storey
###-#### calvin ###-#### calvin gen test failled. 6/5/2003 2:46:38 PM
FIRE-Conference6/3/20036/5/20036/5/2003PFAIL
DetailsRick Jackson
###-#### calvin attempted to test the generator and it failed to provide power when building power was shut off 6/5/2003 5:17:44 PM
BLD-Framing/Rough-in5/30/20036/2/20036/2/2003APART
DetailsJim Storey
area b fire proofing 3 locations/ 2 lights. ceillings ok 6/2/2003 9:52:06 AM
BLD-Conference5/30/20035/30/20035/30/2003PCANC
DetailsJim Storey
###-#### calvin ###-#### calvin out of time. 5/30/2003 4:53:38 PM
BLD-Conference5/19/20035/21/20035/21/2003APART
DetailsJim Storey
###-#### calvin ###-#### calvin recieved oversized glazing for 3 rd floor ok. 5/21/2003 11:08:59 AM
FIRE-Conference5/19/20035/21/20035/21/2003APART
DetailsRick Jackson
###-#### calvin met with Jim Storey, Bill and Calvin about exit signs and requirements for final 5/21/2003 11:15:17 AM
BLD-Conference5/16/20035/19/20035/19/2003PPASS
DetailsJim Storey
###-#### all but 3 rd floor glazing doors ok 5/19/2003 4:13:11 PM
BLD-Final5/15/20035/16/20035/16/2003APART
DetailsJim Storey
list noted on plan with calvin mim. defic. left. 5/16/2003 11:26:27 AM
BLD-Conference5/14/20035/15/20035/15/2003ACANC
DetailsJim Storey
###-#### calvin
BLD-Conference5/12/20035/14/20035/14/2003APASS
DetailsJim Storey
fire shudder test on mail rm /slider bagage 2/messinene over look 3 dr floor ok. pending all others 5/14/2003 10:06:10 AM
BLD-Conference5/12/20035/13/20035/13/2003PFAIL
DetailsJim Storey
list of doors that no not meet listings or functioalty. 5/13/2003 5:05:13 PM
BLD-Conference5/12/20035/12/20035/12/2003PCANC
DetailsJim Storey
###-#### calvin
BLD-Conference5/8/20035/9/20035/9/2003APASS
DetailsJim Storey
###-#### calvin
FIRE-Conference5/7/20035/8/20035/8/2003APART
DetailsRick Jackson
CALVIN ###-#### verified operation of new smoke/fire dampers on third floor by horizontal exit - okay 5/8/2003 2:09:20 PM
BLD-Conference5/6/20035/6/20035/6/2003PFAIL
DetailsJim Storey
###-#### calvin 3rd floor 2hr wall not complet f/s/d ele problem, 5/6/2003 5:17:46 PM
BLD-Conference5/2/20035/5/20035/5/2003APART
DetailsJim Storey
CALVIN ###-####
BLD-Conference4/29/20034/30/20034/30/2003ACANC
DetailsJim Storey
###-####
BLD-Conference4/30/20034/30/20034/30/2003PFAIL
DetailsJim Storey
2 nd floor as noted with calvin. 4/30/2003 5:31:09 PM
BLD-Conference4/23/20034/24/20034/24/2003PPASS
DetailsJim Storey
CALVIN ###-#### basement fire stopping complet. 4/24/2003 5:02:18 PM
BLD-Conference4/22/20034/23/20034/23/2003AFAIL
DetailsJim Storey
###-#### calvin c/n listing for door butts as fire assembly/ justafy door closers in boiller rm with out side wind presure for self close and latch. 4/23/2003 10:40:37 AM
BLD-Conference4/18/20034/21/20034/21/2003PNH
DetailsJim Storey
###-#### ###-#### called left measage no call back. 4/21/2003 4:37:31 PM
BLD-Framing/Rough-in4/17/20034/18/20034/18/2003PPASS
DetailsJim Storey
RIGO CELL ###-#### CALL 1ST BEFORE INSP -FOR SECURITY DOORS IN TERMINAL 2 nd floor exit ok proto type/ basement override ok 4/18/2003 3:57:08 PM
BLD-Conference4/17/20034/17/20034/17/2003PPASS
DetailsJim Storey
CALVIN ###-#### verified tempered on glazing pannels at rotunda at half way point of instulation./ third floor fire stopping in progess. 4/17/2003 3:20:56 PM
BLD-Conference4/14/20034/15/20034/15/2003APASS
DetailsJim Storey
CALVEN ###-####
BLD-Conference4/11/20034/14/20034/14/2003APASS
DetailsJim Storey
CALVIN ###-#### colored coded 2 nd floor for opening protection. 4/14/2003 9:55:31 AM
BLD-Conference4/8/20034/11/20034/11/2003PCANC
DetailsJim Storey
DON ###-####
BLD-Conference4/8/20034/10/20034/10/2003AFAIL
DetailsJim Storey
calvin ###-####
BLD-Framing/Rough-in4/1/20034/3/20034/3/2003APART
DetailsJim Storey
first floor ok for ceilling all but restaroom and rental ares ajasent to south coridor. 4/3/2003 4:50:05 PM
BLD-Other4/3/20034/3/20034/3/2003PCANC
DetailsRick Jackson
see fire conference for this date 4/3/2003 5:03:21 PM
FIRE-Conference4/3/20034/3/20034/3/2003PPART
DetailsRick Jackson
met with Al Massi; Jim Story and Calvin about requirements for occupancy; requested written plan for sequence of events for fire alarm work and all areas sprinklered with preaction systems working
BLD-Conference3/24/20033/31/20033/31/2003APART
DetailsJim Storey
CALVIN; Phone #: ###-#### Internet Inspection Request from: Darla Downs meeting to start temp occ. main terminal all but area b. letter to follow. 4/1/2003 8:52:32 AM
FIRE-Conference3/28/20033/31/20033/31/2003APART
DetailsRick Jackson
830 met with Jim Storey and airport reps about occupancy for May 9th; area B won't be complete; will need plan for alarm monitoring with concourse A and B and new panel 3/31/2003 10:46:51 AM
FIRE-Conference2/24/20032/26/20032/26/2003ACANC
DetailsRick Jackson
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie rescheduled for 2/25 2/25/2003 12:30:38 PM
FIRE-Conference2/25/20032/25/20032/25/2003PPART
DetailsRick Jackson
all dampers checked - one not working on third floor at AHU 6 return; will recheck it at a later date 2/25/2003 3:40:18 PM
BLD-Conference2/21/20032/24/20032/24/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/21/2003 at 2:48:42 PM. Contact: ###-####. a line colm. floor septration ok. 2/24/2003 9:31:22 AM
FIRE-Sprinkler Rough-in2/19/20032/20/20032/20/2003AFAIL
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie not a sprinkler r/i' checked smoke/fire damper operation - basement dampers are all okay now; started checking other floors; first floor ceiling detectors at vestibules are sampling tube type on 2 west vestibules and should be in-duct detectors as the sampling tubes won't work properly due to location; several dampers on first and second floor not working and will need to verify operaration 2/21/2003 9:20:21 AM
BLD-Conference2/18/20032/19/20032/19/2003APASS
DetailsJim Storey
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie all basement areas with cilling grid ok for cover fire stopping and grid ok for cover. 2/19/2003 9:17:37 AM
BLD-Conference2/13/20032/14/20032/14/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/13/2003 at 11:34:16 AM. Contact: ###-####. coridor in basement ok for cover of ceilling all but chase in restaroom and securty rms . mech/ refegration rm/boiler rm pending insp basement. 2/14/2003 10:53:00 AM
FIRE-Final Inspection2/12/20032/14/20032/14/2003AFAIL
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung started checking smoke/fire dampers - damper at detector M1-82 not closing otherwise the basement dampers are okay 2/14/2003 12:28:37 PM
BLD-Conference2/12/20032/13/20032/13/2003AFAIL
DetailsJim Storey
basement fire stopping not complet/ ceilling grind ok in all but vestabules. 2/13/2003 9:54:36 AM
BLD-Conference2/11/20032/12/20032/12/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/11/2003 at 11:39:10. Contact: ###-####.out of time 2/12/2003 5:56:11 PM
FIRE-Sprinkler Rough-in2/7/20032/7/20032/7/2003PPART
DetailsRick Jackson
okay to cover area between rotunda and ticket area on second floor; need fireproofing in spots at the "fish"
BLD-Framing/Rough-in1/30/20032/5/20032/5/2003AFAIL
DetailsJim Storey
calvin-fire caulking for ceiling; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie basement fire stopping not instaled per the listing on insulated pipes min 1/2 to 1 1/2 with 5/8 depth and 1/4 bead. other penatrations not complet through out. wall continuity must be maintaned. 2/5/2003 9:41:04 AM
BLD-Conference1/27/20031/30/20031/30/2003APART
DetailsJim Storey
###-#### bill ###-#### bill meeting with fire and mech for alarm system function . 1/30/2003 12:30:00 PM
FIRE-Conference1/27/20031/30/20031/30/2003APART
DetailsRick Jackson
###-#### bill met with working group about smoke fire damper control 1/30/2003 12:39:00 PM
BLD-Wall cover1/15/20031/16/20031/16/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/15/2003 at 07:58:12. Contact: ###-####. visqueen verified to meet fire restant/ fire prooffing reports to be followed up with special insp. 1/16/2003 12:07:12 PM
BLD-Framing/Rough-in12/10/20021/3/20031/3/2003APART
DetailsJim Storey
fire stopping basement needed. 1/3/2003 10:33:26 AM
FIRE-Conference12/30/200212/30/200212/30/2002APART
DetailsRick Jackson
met with Steve of LEA Electirc; c/n issued - need detectors installed within 5 ft of smoke/fire dampers; need access doors at all dampers; will need to verify duct detector operation with air differential pressure test per Simplex manual instructions; duct detectors are installed at some smoke/fire dampers - plans show in-duct detectors; numerous pockets in computer room ceiling which will require detectors for pre-action system 12/30/2002 11:00:34 AM
BLD-Framing/Rough-in12/10/200212/26/200212/26/2002AFAIL
DetailsJim Storey
wip 3 rd floor top of corrordor gyp/ hydronic pipe fire stopping./ visqueen listing. 12/26/2002 10:39:48 AM
BLD-Framing/Rough-in12/10/200212/19/200212/19/2002APART
DetailsJim Storey
BLD-Final12/16/200212/17/200212/17/2002PCANC
DetailsJim Storey
calvin ###-####
BLD-Framing/Rough-in12/12/200212/17/200212/17/2002ACANC
DetailsJim Storey
###-#### JEFF
FIRE-Final Inspection12/16/200212/17/200212/17/2002PPART
DetailsRick Jackson
calvin -###-#### -pending fn occ insp okay to use a portion of the elevated walkway per letter of agreement with PDS/FD and airport 12/18/2002 11:28:21 AM
BLD-Framing/Rough-in12/12/200212/16/200212/16/2002AFAIL
DetailsJim Storey
FR JEFF- ###-#### fire stopping signage area of refuge/ exit/ remove doors/ handrail returns./ door hardware. 12/16/2002 4:47:21 PM
BLD-Framing/Rough-in12/10/200212/12/200212/12/2002AFAIL
DetailsJim Storey
###-#### HAS NOTHING TO DO WITH THE RESUBMITTLE. first floor floor penatrations missing ele plm/ floor pour back one location at entry of road way/ fire proofing patch/ main shaft flue pipe clearance/ shaft intagraty not complet at curtin wall./ base track to stud screws missing exterior walls east half of bld./membrane penatrations not per listing and not complet./ top of wall slip track protecrtion back of bathrooms not complet as well as fire tapping./ clean up all debri fron unuseable spaces. 12/12/2002 11:43:14 AM 12/12/2002 11:50:27 AM
FIRE-Conference11/25/200211/25/200211/25/2002PPART
DetailsRick Jackson
JEFF ###-#### FOR CONF met with Sam of TVFP about fire sprinklers for the temp ramp for the temp walkway; I was given some plans and will contact Sam Rogers and Bill A about it 11/25/2002 4:41:37 PM
BLD-Wall cover11/13/200211/13/200211/13/2002PPASS
DetailsJim Storey
shaft in basment at boiller ok.
BLD-Final10/22/200210/23/200210/23/2002PPART
DetailsJim Storey
partial final conc A restroom; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
FIRE-Final Inspection10/14/200210/14/200210/14/2002APART
DetailsRick Jackson
okay for new bathroom in concourse A 10/14/2002 9:25:58 AM
BLD-Wall cover9/27/20029/30/20029/30/2002APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/27/2002 at 12:42:00. Contact: ###-####.a concorce walkway c/n made ok on strucral joist. / skylight at rotunda missing 4 bolts and 2 need tightened./ curtian wall fire stopping in progess ok/ f&t caculation to justify basment coridor as well as smoke and flame listing for wall assemblie./ floor penatrations at first and second not complet./east walkway engineer to aprove backer plates at fpj ok to cover walls. 9/30/2002 2:50:53 PM
BLD-Framing/Rough-in8/29/20028/30/20028/30/2002APART
DetailsJim Storey
larry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 2h at top of wall ok on d line west to expantion joint in bldg./a concorse temp walk way colm joist at roof knife plate and bottom chord cut need justication. 8/30/2002 10:20:02 AM
BLD-Framing/Rough-in7/24/20027/25/20027/25/2002PPART
DetailsJim Storey
calvin ###-#### skylight calvin ###-#### need shop drawninings and pick up permit at city//skylight 7/25/2002 12:48:37 PM
BLD-Framing/Rough-in7/19/20027/19/20027/19/2002PPART
DetailsJim Storey
fr & skylight calvin- ###-####--per marlene ok to insp in ready status
BLD-Framing/Rough-in7/11/20027/11/20027/11/2002PPASS
DetailsJim Storey
###-####- larry --fr insp basement ok 7/11/2002 6:00:32 PM
BLD-Framing/Rough-in6/28/20027/1/20027/1/2002AFAIL
DetailsJim Storey
calvin-- ###-####--fr basement walk through maintane firewall deflection track top of wall and gyp. isi needs listings to address penatrations. 7/1/2002 11:41:03 AM
BLD-Conference6/19/20026/25/20026/25/2002APART
DetailsJim Storey
CALVEN ###-#### CALVEN deflection chart recieved from arch.###-#### 6/25/2002 1:43:26 PM
BLD-Conference5/21/20025/21/20025/21/2002PPASS
DetailsJim Storey
1. (Approved fabricators) Special inspections required by the 1997 UBC are not required where the work is done on the premises of a fabricator registered and approved by the building official to perform such work without special inspection. The approved fabricator shall submit a certificate of compliance that the work was performed in accordance with the approved plans and specifications to the building official and to the engineer or architect of record. (1997 UBC 1701.7)reviewed all submital with superviser to have fabracator SME steel fabracators meet ubc 1701.7 for aproval to discontinue third party insp. engineer of record letter as well as all documents required to meet 1701.7 are on file with the building dept. and aproved.
BLD-Conference4/8/20024/10/20024/10/2002APART
DetailsJim Storey
for conf bill -- ###-#### waiting for design plan. 4/10/2002 11:28:02 AM
BLD-Conference3/13/20023/15/20023/15/2002APART
DetailsJim Storey
for conf calvin ###-#### walk through with r jackson/ work inprogess./ plm common coridor wall and sofit need pre rock/ ele box protection/ transpher duct openings reduced/ 2 hr shaft next to rotunda maintaned at beam seats. 3/15/2002 1:50:01 PM
FIRE-Conference3/13/20023/15/20023/15/2002APART
DetailsRick Jackson
fire for conf--calvin - ###-#### met with Jim Storey and Calvin. r/i of basement alarms; need resubmittals on larm wiring and changes 3/15/2002 11:24:18 AM
BLD-Framing/Rough-in2/13/20022/14/20022/14/2002APART
DetailsJim Storey
interior systems insp--larry- ###-#### basement wall framing wip track sys ok job conf. 2/14/2002 11:20:37 AM
BLD-Conference1/22/20021/24/20021/24/2002PPART
DetailsJim Storey
###-#### 2:30 conference conf. to review rated const. of gyp.walls and occ. septrations before const begins 1/24/2002 2:21:09 PMwill need submitals for top of wall configurations at beams. 1/24/2002 3:33:45 PM
BLD-Framing/Rough-in1/10/20021/16/20021/16/2002APART
DetailsJim Storey
need to recieve engineers heat approval for beam camber of 6 line/ need engineers approval for not removing backer plsates on full pen welds to meet aws std. reviewed fireproofing material and hourly ratings required/ surface tempture min 40 deg. surface/ reviewed coridor wall conflict with 3 hr colms. 1/16/2002 11:42:01 AM
BLD-Framing/Rough-in1/10/20021/11/20021/11/2002APART
DetailsJim Storey
###-#### wip pending special insp report for first deck pour. 1/16/2002 7:42:40 AM
BLD-Foundation11/26/200111/26/200111/26/2001PPART
DetailsJim Storey
CALVIN ###-#### south east end wall at rotunda appears ok for cover. pending special insp. reports being keep on site. 11/26/2001 3:57:30 PM
BLD-Foundation10/24/200110/24/200110/24/2001PPART
DetailsJim Storey
###-#### CALVIN east /south ft placed with special insp.pending report. 10/24/2001 4:54:35 PM
BLD-Foundation10/8/200110/11/200110/11/2001PPART
DetailsJim Storey
###-#### kalven placed with special insp. pending report. 10/12/2001 3:40:21 PM
BLD-Foundation10/8/200110/9/200110/9/2001PPART
DetailsJim Storey
###-#### kalven center wall sec. north side of project ok pending special insp report for concrete. 10/9/2001 1:52:42 PM
BLD-Footing9/25/20019/27/20019/27/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/25/2001 at 12:06:07. Contact: . wip 9/28/2001 10:02:15 AM
BLD-Concrete9/10/20019/10/20019/10/2001PPART
DetailsJim Storey
CONCRETE- CALVIN -###-#### covered w/special insp. 9/10/2001 5:56:20 PM
BLD-Concrete9/4/20019/5/20019/5/2001PPASS
DetailsJim Storey
###-#### ###-#### CALVEN rebar a1-c ok wip pending special insp.report. 9/6/2001 1:42:44 PM