BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Carl Dependahl
|
|
|
rec'd eng's affidavit..ok
|
BLD-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | FAIL |
Carl Dependahl
|
|
|
need eng's clarification & add'l statements re MTI's affidavit. 6/18/2002 11:34:36 AM
|
BLD-Final | 6/17/2002 | 6/17/2002 | 6/17/2002 | P | NR |
Carl Dependahl
|
|
|
SCOTT ###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | P | NR |
Carl Dependahl
|
|
|
scott ###-#### fn will recall 6/14/2002 5:19:33 PM
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | FAIL |
Jim Storey
|
|
|
repair exit sign and move handrail in center stair to 34 to 38 inches . 6/13/2002 2:21:06 PM
|
BLD-Final | 1/16/2002 | 1/17/2002 | 1/17/2002 | A | PART |
Carl Dependahl
|
|
|
###-####, rec'd eng's final report, ok for t/o 1/17/2002 1:25:28 PM
|
FIRE-Final Inspection | 1/16/2002 | 1/16/2002 | 1/16/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 1/16/2002 2:01:31 PM
|
BLD-Final | 1/14/2002 | 1/14/2002 | 1/14/2002 | P | NR |
Carl Dependahl
|
|
|
###-####, need engs report, all ok's 1/14/2002 6:06:08 PM
|
BLD-Final | 1/10/2002 | 1/10/2002 | 1/10/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/11/2001 | | NR |
Carl Dependahl
|
|
|
wip 12/11/2001 9:58:32 AM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | NR |
Carl Dependahl
|
|
|
apts...wip. 10/8/2001 10:46:28 AM
|
BLD-Aging Inspection | 8/7/2001 | 8/7/2001 | 8/7/2001 | | PASS |
Carl Dependahl
|
|
|
wip 8/7/2001 9:28:27 AM
|
BLD-Conference | 6/7/2001 | 6/7/2001 | 6/7/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/7/2001 1:49:28 PM met w/ bldr onsite, need eng's report
|
BLD-Concrete | 5/25/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/25/2001 at 12:09:08. Contact: ###-####. covered with special insp. pending report. 5/30/2001 10:08:03 AM
|
BLD-Concrete | 5/23/2001 | 5/25/2001 | 5/25/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/23/2001 at 13:04:13. Contact: (208) p.t. deck###-####...pending spec insp reports; eng'r made site visit 5/25/2001 11:41:46 AM
|
BLD-Concrete | 5/17/2001 | 5/21/2001 | 5/21/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 09:44:38. Contact: ###-####... PT slab...need eng's statement re plbg pipes, removed from col. caps 5/21/2001 2:27:59 PM
|
BLD-Conference | 5/17/2001 | 5/18/2001 | 5/17/2001 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 09:43:38. Contact: ###-####.--cancel per scott kimball
|
BLD-Conference | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
|
BLD-Conference | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
|
BLD-Concrete | 4/27/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/27/2001 10:20:56 AM slab at grade, NE corner; conf w/ owner: need eng'r & spec insp's affidavits for pt slab..decking/shoring wip prior to pour..req'd meeting w/ eng'r 5-7-01
|
BLD-Concrete | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 19:20:56. Contact: ###-####. placed with special insp.pending report. 4/20/2001 3:28:27 PM
|
BLD-Concrete | 4/17/2001 | 4/18/2001 | 4/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 11:43:59. Contact: ###-####. placed with special insp. pending report. 4/18/2001 2:45:16 PM
|
BLD-Foundation | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/12/2001 at 08:47:57. Contact: ###-####. pend report, walls. 4/12/2001 5:11:49 PM
|
BLD-Conference | 4/2/2001 | 4/2/2001 | 4/2/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/2/2001 6:28:43 PM w/ Gary Z. re plbg c/n.
|
BLD-Foundation | 3/29/2001 | 3/30/2001 | 3/30/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/29/2001 at 12:31:14. Contact: ###-####. placed with special insp. pending report. 3/30/2001 1:47:22 PM
|
BLD-Footing | 3/26/2001 | 3/27/2001 | 3/27/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 11:51:43. Contact: ###-####. wip mti on site 3/27/2001 9:53:17 AM
|
BLD-Footing | 3/22/2001 | 3/23/2001 | 3/23/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/22/2001 at 17:39:34. Contact: ###-####. col's; requested eng'r observe & report re p.t. deck, & overall for concrete (as designed ) deck is also 3hr occ sep. 3/23/2001 9:42:47 AM
|
BLD-Footing | 3/21/2001 | 3/22/2001 | 3/22/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/21/2001 at 17:07:53. Contact: ###-####...cols; met w/ contractor & spec insp onsite. pend report 3/22/2001 3:25:48 PM
|
BLD-Footing | 3/20/2001 | 3/21/2001 | 3/21/2001 | A | PART |
Jim Storey
|
|
|
###-#### placed with special insp. pending report. 3/21/2001 4:33:49 PM
|
BLD-Conference | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/19/2001 4:41:29 PM rec'd eng'g resub...called arch John Price; need insps for concrete. called bldr, has had mti onsite, need to request city insps
|
BLD-Footing | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/22/2001 at 15:23:14. Contact: ###-####. ftgs; pend spec. insp. reports 2/23/2001 12:45:24 PM
|
BLD-Footing | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Tom Arcoraci
|
|
|
pouring at 12:00 as per bob a. put in inspection for footing Scott ###-#### wip 2/20/2001 9:58:19 AM
|