Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-03519
StatusFinaled
Name RIVER WALK APARTMENTS
Site Address 1689 W SHORELINE Unit: DR
Project NameRIVER WALK APARTMENTS
Customer Number 
ePlanReviewNo
Description
River Walk Apartments Parking Garage * To construct a new 33,000 sq.ft Type IFr, S-3 parking garage under a post tensioned slab meeting the three hour occupancy separation requirements per UBC Section 311.2.2.1. and Section 311.9.2.2. is being used to meet the open parking garge requirements for exterior wall opening and travel distances. NOTE : This structure is required to have Standpipes per UBC Table 9-A. This project is located in the 100 year flood plain. Special inspection is required for concree, soil bearing, welding, and anchor bolts greater than A325. All construction per the approved plans and CABO/ANSI A117.1. DRH00-00161, PC# 1000-00 Grading permit # is BLD00-03479. MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/17/20027/17/20027/17/2002APASS
DetailsCarl Dependahl
rec'd eng's affidavit..ok
BLD-Final6/17/20026/18/20026/18/2002AFAIL
DetailsCarl Dependahl
need eng's clarification & add'l statements re MTI's affidavit. 6/18/2002 11:34:36 AM
BLD-Final6/17/20026/17/20026/17/2002PNR
DetailsCarl Dependahl
SCOTT ###-####
BLD-Final6/14/20026/14/20026/14/2002PNR
DetailsCarl Dependahl
scott ###-#### fn will recall 6/14/2002 5:19:33 PM
BLD-Final6/12/20026/13/20026/13/2002AFAIL
DetailsJim Storey
repair exit sign and move handrail in center stair to 34 to 38 inches . 6/13/2002 2:21:06 PM
BLD-Final1/16/20021/17/20021/17/2002APART
DetailsCarl Dependahl
###-####, rec'd eng's final report, ok for t/o 1/17/2002 1:25:28 PM
FIRE-Final Inspection1/16/20021/16/20021/16/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 1/16/2002 2:01:31 PM
BLD-Final1/14/20021/14/20021/14/2002PNR
DetailsCarl Dependahl
###-####, need engs report, all ok's 1/14/2002 6:06:08 PM
BLD-Final1/10/20021/10/20021/10/2002PCANC
DetailsRuss Owen
###-####
BLD-Aging Inspection12/10/200112/10/200112/11/2001 NR
DetailsCarl Dependahl
wip 12/11/2001 9:58:32 AM
BLD-Aging Inspection10/8/200110/8/200110/8/2001 NR
DetailsCarl Dependahl
apts...wip. 10/8/2001 10:46:28 AM
BLD-Aging Inspection8/7/20018/7/20018/7/2001 PASS
DetailsCarl Dependahl
wip 8/7/2001 9:28:27 AM
BLD-Conference6/7/20016/7/20016/7/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/7/2001 1:49:28 PM met w/ bldr onsite, need eng's report
BLD-Concrete5/25/20015/30/20015/30/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/25/2001 at 12:09:08. Contact: ###-####. covered with special insp. pending report. 5/30/2001 10:08:03 AM
BLD-Concrete5/23/20015/25/20015/25/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/23/2001 at 13:04:13. Contact: (208) p.t. deck###-####...pending spec insp reports; eng'r made site visit 5/25/2001 11:41:46 AM
BLD-Concrete5/17/20015/21/20015/21/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/17/2001 at 09:44:38. Contact: ###-####... PT slab...need eng's statement re plbg pipes, removed from col. caps 5/21/2001 2:27:59 PM
BLD-Conference5/17/20015/18/20015/17/2001APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/17/2001 at 09:43:38. Contact: ###-####.--cancel per scott kimball
BLD-Conference5/16/20015/16/20015/16/2001PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
BLD-Conference5/16/20015/16/20015/16/2001PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
BLD-Concrete4/27/20014/27/20014/27/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/27/2001 10:20:56 AM slab at grade, NE corner; conf w/ owner: need eng'r & spec insp's affidavits for pt slab..decking/shoring wip prior to pour..req'd meeting w/ eng'r 5-7-01
BLD-Concrete4/19/20014/20/20014/20/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/19/2001 at 19:20:56. Contact: ###-####. placed with special insp.pending report. 4/20/2001 3:28:27 PM
BLD-Concrete4/17/20014/18/20014/18/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/17/2001 at 11:43:59. Contact: ###-####. placed with special insp. pending report. 4/18/2001 2:45:16 PM
BLD-Foundation4/12/20014/12/20014/12/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/12/2001 at 08:47:57. Contact: ###-####. pend report, walls. 4/12/2001 5:11:49 PM
BLD-Conference4/2/20014/2/20014/2/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/2/2001 6:28:43 PM w/ Gary Z. re plbg c/n.
BLD-Foundation3/29/20013/30/20013/30/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/29/2001 at 12:31:14. Contact: ###-####. placed with special insp. pending report. 3/30/2001 1:47:22 PM
BLD-Footing3/26/20013/27/20013/27/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/26/2001 at 11:51:43. Contact: ###-####. wip mti on site 3/27/2001 9:53:17 AM
BLD-Footing3/22/20013/23/20013/23/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/22/2001 at 17:39:34. Contact: ###-####. col's; requested eng'r observe & report re p.t. deck, & overall for concrete (as designed ) deck is also 3hr occ sep. 3/23/2001 9:42:47 AM
BLD-Footing3/21/20013/22/20013/22/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/21/2001 at 17:07:53. Contact: ###-####...cols; met w/ contractor & spec insp onsite. pend report 3/22/2001 3:25:48 PM
BLD-Footing3/20/20013/21/20013/21/2001APART
DetailsJim Storey
###-#### placed with special insp. pending report. 3/21/2001 4:33:49 PM
BLD-Conference3/19/20013/19/20013/19/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 3/19/2001 4:41:29 PM rec'd eng'g resub...called arch John Price; need insps for concrete. called bldr, has had mti onsite, need to request city insps
BLD-Footing2/22/20012/23/20012/23/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 02/22/2001 at 15:23:14. Contact: ###-####. ftgs; pend spec. insp. reports 2/23/2001 12:45:24 PM
BLD-Footing2/16/20012/16/20012/16/2001PPART
DetailsTom Arcoraci
pouring at 12:00 as per bob a. put in inspection for footing Scott ###-#### wip 2/20/2001 9:58:19 AM